Ref:-SLE-19/0209/002 Date: 02-09-2022

Sania Corner
Scheme 33, 18-C, Gulzar-e-Hijri,
Karachi.

SUBJECT: Supply & Installation of 02 x Units of Semi-Imported


Passenger & Cargo Elevators for Sania Corner Project

Dear Respected Sir,

First of all we would like to express our thanks for giving us the
opportunity to participate as a lift contractor for your project. We are
pleased to submit that you would not compromise on quality and safety of
the passenger. We are proud to say that your satisfaction is our priority.

We hereby given you a detail of which covers our packages as per


specification. The system which we offering you are one of the safest,
durable and trouble free operation for the long period that our offer will
meet your requirement.

Thanking you and assuring you best services and co-operation at all times
& we look forward to being associated with you on this prestigious project.

_______________________________
Best Regards,
SKY LINK ELEVATOR
(ARSALAN RAZZAQ BHATTI)
“Director”
ELEVATOR SPECIFICATIONS
CAPACITY : 08 PASSENGERS

STOPS : B+G+1…..12 = 14/14 Stops/Opening


DOORS : 800mm Manual Swing Doors + 700mm
Automatic Landing Doors

POWER SUPPLY : 3 PHASE 380V, 50 Hz

CONTROL PANEL : V.V.V.F (Inverter) Micro Processor Control


System (Made in China = MONARCH).

MOTOR : V.V.V.F Gearless Machine Complete with


Sheave & Break having P=8.5 KW (China).

GUIDE RAILS : Standard 5m Guide Rails with Fish Plate

TRAVELING CABLE : With heavy duty PVC Core

WIRE ROPE : Special Steel Core Rope of elevator grade


∅10mm (Brand-Kiska) Made in Korea
CABIN : Full design Cabin Made of S.S Cabin with
Fancy False ceiling COP, Intercom
system, Blower fan & Lights, having
Cabin Min. WxD =(1000x1900) mm

COUNTER WEIGHT & FILLERS : Counter weight Made of MS Channel “4x2”


made of Concrete Covered MS Steel Sheet.

WIRING MATERAIL : Power wiring for Machine is Pakistan Cable


Lift Communication wiring to be imported.

LANDING INDICATORS : Digital Indicators of directions position at


all floors.
SAFFTY DEVICE:

1) Over Speed Governor & its emergency rope.


2) Phase Failure protection.
3) Heavy Duty Hydraulic Buffers.
4) Final Limit Switches.
5) Floor Sensors
6) Door Safety Switches and mechanical inter locking system.
7) Elevator Safety Gear Device
TECHNICAL FEATURES
 (THE TIME THE DOOR REMAINS OPENED):
For merely External call signal, 1-2 seconds: and in case of both Internal selected
signal and external call signals, 2tseconds.

 CALL FOR OPERATION OF THESE FLOORS :


In case that the elevator is yet not started but. The door is closed or is being
closed; pressing the call button of this floor will make the door lock open.

 DOOR INTERLOCKED PROTECTION:


Only when all doors are interlocked and closed may the elevator be able to run,
otherwise if will stop.

 POSITION-LIMIT PROTECTION:
If the elevator detects a limit switch, the entire System during upwards
(downwards) running, it will immediately permanently stop.

 LIMIT PROTECTION:
If the elevator triggers a limit switch, the entire system will be de-energized.

 TROUBLE-SHOOTING OF ELEVATOR:
In case of trouble, the system will automatically locate the possible causes and
show the trouble message.

 ASSESSMENT OF IMMUNITY :
This function is able to correctly asses the grounding of the control panel and
shaft wires.
MAINTENACE AND SERVICE
 ELEVATOR MONTHLY MAINTENANCE:
Our 12 month quality warranty begins after the installation elevator of each
material/equipment.
During our warranty period, we will send our maintenance technician to
maintain the elevator on site for Free. The maintenance cycle will be controlled
on a monthly basis. If any problems occur during the warranty period, our
company specialist will solve them on priority basis from the moment of
notification. Before the due to the quality warranty, we will thoroughly inspect
and test the elevator free of charge for our clients and resolve existing problems
if any. During our warranty period, client can contact us via our 24-hour cell
number.

 SIGN THE MAINTENANCE AND REPAIR CONTRACT WITH OUR CLIENT:


After Signing the contract with our client we will send our specialist to repair
and maintain the elevator on site, on a regular basis of every 30 days, we respect
our client, arrangements if they have any special requirement is terms of repair
and maintenance Schedule. Our client can call our 24 hour hotline for emergency
service. We provide a thorough inspection annually free of charge, and will
repair the elevator at the most favorable price if needed.

 AFTER THE QUALITY WARRANTY PERIOD IS DUE:


The replacement parts should ensure the consistent, sage and efficient operation
of the elevator, after signing the repair and maintenance contract, the spare parts
will be supplied to our client’s at most favorable price.

 TECHNICAL TRAINING:
We will send our maintenance specialists on site to train two members of
personnel free of charges for our clients.

 WARRANTY:
Defect Liability Period for this contract shall be 12 months after next day of
installation of all electrical & mechanical equipment’s/part. Further after
handing over of all units to client we shall remain responsible for 12 months free
service and maintenance of the installed equipment.
 VALIDITY OF OFFER:
 This offer is valid for a period of 15 days from the date of Submission.

 EXCLUSIONS:
 All civil works like cutting, chipping filling etc. for fixation of equipment.
 Single phase electricity during installation.
 Three phase electricity during commissioning & shaft lighting.
 Electrical DB, Circuit breaker and main cable in Machine room.
 Cost of Supply & fixation/dismantling of MS Scaffolding in elevator shaft.
 Cost of dividing H-Beams & accessories and its fixation in elevator shaft.
 Permanent Shaft Lightings inside machine room & shaft with a single
Phase supply socket in pit area along with 02 way switch in pit.
 Tools & Elevators Material Storage area with Lockable doors & it safety &
Security.

 INCLUSIONS:
 All manpower & tools required for supply, installation & testing of elevator.
 All coordination material for supply & transportation of material at site.

 INSTALLATION SCHEDULE:-
 Installation time of all elevators will be 90 days after completion of all
civil related works & handing over of shaft from client end.

 PRODUCT WARRANTY:-
 Warranty of all products is valid for a period of twelve (12) months after
Installation of equipment’s/materials.
 SUPPLY & INSTALLATION PRICE & CONDITION:-
The Total Sales Price for SANIA CORNER Gulzar-e-Hijri Project Karachi, Elevator
Material Amount is PKR. 11,610,000 & Local Works-Installation Amount is
PKR. 1,400,000. As per mentioned specifications and according to below
mentioned payment terms.

No. of Unit Price Total Local Total


S.# Description Units PKR Amount Works Local
PKR Per Unit Works
PKR
Passenger
01 Type Machine 01 5,555,000 700,000
Room Elevator 11,610,000 1,400,000
Cargo Type
02 Machine Room 01 6,055,000 700,000
Elevator

NET PRICE 02 PKR = Rs. 13,010,000 (Without any Taxes)

 PAYMENT TERMS & CONDITIONS:-


For Elevator Equipment/Material:-
Condition of Payment
- 70% Advance
- 30% Upon Supply of Complete Elevators @ Site
For Local Works:-
Condition of Payment
- 30% On Mobilization of Teams & Starting of Installation Works at Site
- 30% On Completion of Mechanical Works
- 30% On Completion of Electrical Works

- 10% On Handing Over of Elevators