Quotation and details of manual Door Elevator (Matted Steel MS Cabin) Goods.

We thank you for your valued inquiry referred above and based on the details,
we are pleased to submit our offer for the subject elevator, and further to add,
we hereby furnish the details for your perusal.

(Image: MS
Cabin).
2

Our Company

HAPPY Elevators was established in the year 2003 and supported by 100
dedicated employees catering to the 2000 elevators installed in undivided
Andhra Pradesh. We are happy to say our customers are satisfied with the
quality of our product and service comfort extended to them for more than a
decade. Our key success is our capability to make custom-built vertical
transport systems.

Our aim is to provide a quality and safe vertical transportation system at a reasonable
cost.

INDEX

1. Technical Specification

2. Price Schedule

3. Execution Schedule

4. Terms and conditions

5. Scope of work
3

1 TECHNICAL SPECIFICATION-A
The detailed specification of the
proposed HAPPY Elevator is here below

TYPE AND MODEL MRL 2:1 Ropeg Goods machine room required

NUMBER OF ELEVATORS ONE

CAPACITY & SPEED 3 Ton Goods 1M/SEC

TRAVEL HEIGHT 15.00 METERS

NUMBER OF FLOORS TO BE GROUND + 2FLOORS = 3FLOORS


SERVED

NUMBER OF LANDINGS TO BE GROUND+2LANDINGS= 3LANDINGS(ALLONONESIDE)


SERVED

REQUIRED PIT DEPTH 1500 MM


4

Price Schedule.
The price schedule for design, Supply, Installation, and testing of the subject
Elevator is here below:

Specification Rate per Elevator Taxes Total price.

G+2 Manual Door MS 10,00,000/- CGST+SGST (18%) 11,80,000/-


Cabin lift.

Machinery: Gear(Bharati Bhijli).


Controler: Hp Mount.
Doors: Manual doors.
Buttons: SS buttons.
Safety features: Emergency Alarm,
Emergency Door
opening lockset.
Emergency power
backup system.
Power backup:

Please feel free to reach us in case of any queries.

Payment Terms

30% of the contract value as interest-free mobilization advance.

60% of the contract value along with 100 taxes against readiness of materials
before dispatch.

10% of the contract value on completion of testing and commissioning before


handing over of elevator for regular use.

Note:

GST on supply of goods has been considered @18% being the rate
prevailing on the date of this quotation. However, if there is any
5

amendment or variation in the rates, the same shall be payable by


you as applicable, in addition to the prices stated herein.

The installation has been considered @18% being the rates


prevailing on the date of this offer. However, if there is any
amendment or variation of the rates, the same shall be payable by
you as applicable, in addition to the prices stated herein.

In case of any delay in completion of the building, arrangement of


permanent power supply, on-demand you shall pay the installation
amount due on completion of mechanical installation against the
notification.

Payment will be accepted only in the form of cheque/demand draft


payable at Hyderabad or local cheque in favors/scan elevators private
limited and no cash.

EXECUTION SCHEDULE

Execution of the contract starts from the day of technical and commercial
clearance (terms of payment) as agreed.Theentirescheduleof12weeks is
divided here below.

Engineering:-we require 1week for the following


(NOTE:-FROMTHEDATEOFLIFTSHAFT IS READY WITHPLASTING)

● Collecting Site details


● Preparation of GAD
● Submission of GAD and Approval from Purchaser

Manufacturing: - we require 3 weeks for the following

1. Procurement and process of standard items


6

2. Manufacture of contract-specific items


3. Testing and inspection of assembly and sub-assembly

Delivery at the site: -we require 1 week for delivery and unloaded at site.

Storage:-we require a minimum of 50Sq. Mtr covered is a free from dust,


water seepage with lockable arrangement preferably near to the elevator
shaft in the bottom floor. This storage remains exclusive for elevator
materials and necessary security if required to be provided by the purchaser.
Store to be made ready before dispatching of materials to the site.

Installation, testing and commissioning: -we require 8 weeks for


installation, testing, and commissioning from the date of handing over of
elevator shaft as per approved GAD.

NOTE:-This excludes purchaser scope of work


such as cladding on the entrance, arranging
power supply, etc.
PURCHASER SCOPE OF WORK

1. SCOPE OF WORK

Allpreparatorybuildingworksuchaselevatorshaftwithenclosureproperly
plastered and whitewashed during erection, waterproof dry and clean
elevator pit.

Any necessary tanking, lining or reinforcements in the elevator pit.


7

Light point in the elevator shaft opposite each landing and in the pit.

EntranceArchitraveorelevatorfacedecorationatallfloorlandings,allpainting job
except of elevator material.

230VSinglephase, 5A.Socketnearcontrolboardand415Vthreephase50HZA.C.power
supply with suitable switch fuseun it and earth leakage circuit breaker (ELCB) of
required capacity as per GAD within 5 meters of each elevator controller for testing
and commissioning and at ground floor for Erection/Installation, Timely provision of
permanent supplies for testing purposes.Effective double earthing from a separate
earth pitexclusively for elevators . Lighting arrestor and other electrical protective
devicthe es necessary to meet the local requirement. (Shaft lightening should be
independent the of main switch provided fthe or controlboard).electric wiring
between the client's main meter board to the client's main switchboard near
thecontroller.

A safe dry, lockable storage space with sufficient lighting and two
numbers three-pin plug points, of a minimum of 50 sq meters per
elevator near the elevator shaft on the ground or basement floor, shall
be made available during the entire installation period for storage of
the material at the site.

Shaft Reduction Channels, if required, and hoisting beam/ hook in the


roof slab in the machine room.

Dryandcleanmachineroomwithprovisionofcrossventilationandexhaustfa
n, sufficient machine room lighting, a lockable door, provision of rain
protection guard on doors and windows, a direct approach from
terrace to machine room by stairs or rigid ladder with handrails and
fall protection rails, and Load hook of capacity specified in GAD above
the machine location.
8

Casting/making of foundation (sickle) for M/C, buffer, Rope anchoring,


Deflection pulley, etc. Ragboltgroutingforfixingdoorhangers.

All electrical wirings &earthling for the lighting & other electrical
fittings in the elevator shaft shall be carried from your end and the
same is excluded from the Happy’s scope of the work

COMPANY SCOPE OF WORK

Supply and fixing of Anchor bolt by drilling hole with Hammering


M/C for Car&cwt. bracket in the case of RCCshaft.

● Proper guarding and close fencing of the elevator shaft


● Providing and fixing of Sill Angle for fixing of landing doors in case of
automatic doors.
● Supply of rag bolt for grouting and fixing wherever required.

● Transportation, Erection, Packaging and Forwarding,
loading/ unloading, installation, testing,
and commissioning charges.
● One Year - Warranty and Guaranty.

Accepted

For HAPPY Elevators For and behalf of purchaser


9

Authorized Signatory Authorized Signatory

Date:- Date:-

You might also like