Professional Documents
Culture Documents
Summary Gantt
Construction - Progress
Milestone
What we have Achieved +/-
against Major Milestones
2
Comment on key influencing factors
TOC Hours
TOC - Costs
Manpower
Manpower
Project Shape
Performance
Progressed Dates
Where we are today
Building 24 - Community Centre 1
Baseline Dates
Progressed Dates
Baseline Dates
v Current planned completion
Building 27 - Community Centre 1 Progressed Dates
Baseline Dates Where we said we would be date
Building 23 - High Security Progressed Dates
Baseline Dates
date
Baseline Dates
30 Comment on
Remove exterior scaffolding key influencing
3-Aug-05 3-Aug-05factors
0
Building 28
20 Structural Steel Complete 29-Jun-05 14-Jul-05 14-Jul-05 -11
Building 30
20 Structural Steel Complete 1-Aug-05 29-Jul-05 29-Jul-05 +1
Building 29
18 Ready for precast 13-Jul-05 20-Jun-05 20-Jun-05 +16
(- days behind)
Draft - SG Guide v1.6
Building 24
96 Ready for structural steel 21-Jul-05 21-Jul-05 21-Jul-05 -1
SERVICES Buried Services 44909.84 0.00 44909.84 6458.90 38236.00 44694.90 214.94 2105 Hrs
BUILD 26 v
Building 26 - General Accommodation 15611.83 1743.00 17354.83 381.27 18633.18 19014.45 -1659.62 -1377 Hrs
BUILD 25
What we have spent
Building 25 - General Accommodation 15436.63 1743.00 17179.63 585.40 16570.35 17155.75 23.88 35 Hrs
BUILD 28 Building 28 - General Accommodation 15494.58 343.00 15837.58 5598.91 9196.66 14795.57 1042.01 1177 Hrs
BUILD 30 Building 30 - General Accommodation 15515.58 343.00 15858.58 7536.28 7487.36 15023.64 834.94 1154 Hrs
BUILD 24 Building 24 - Community Centre 1 5306.32 205.00 5511.32 2765.01 2076.75 4841.76 669.56 463 Hrs
BUILD 27 Building 27 - Community Centre 1 5667.99 205.00 5872.99 3282.07 1987.50 5269.57 603.42 496 Hrs
BUILD 19 Building 19 - Industries 2 13291.07 1400.00 14691.07 164.00 15286.99 15450.99 -759.92 -756 Hrs
BUILD 18 Building 18 - Industries 1 10070.31 207.00 10277.31 48.00 11570.95 11618.95 -1341.64 -1212 Hrs
BUILD 17 Building 17 - Laundry / Kitchen 11446.62 1415.00 12861.62 1160.81 13478.35 14639.16 -1777.54 -1708 Hrs
BUILD 16 Building 16 - Gymnasium 10720.73 890.00 11610.73 1206.87 11036.91 12243.78 Actual
-633.05 -345 Hrshours
BUILD 11 Building 11 - Spiritual Space 6561.13 91.00 6652.13 1987.06 5307.66 7294.72
(as performed)
-642.59 -448 Hrs
BUILD 15 Building 15 - Programmes 1 5620.97 70.00 5690.97 1708.17 3906.17 5614.34 76.63 151 Hrs
BUILD 45 Building 45 - Programmes 2 7500.66 168.00 7668.66 2290.07 4223.05 6513.12 1155.54 1259 Hrs
BUILD 46 Building 46 - Programmes 3 5335.82 78.00 5413.82 1975.79 3000.70 4976.49 437.33 387 Hrs
BUILD 47 Building 47 - Programmes 4 6422.74 203.00 6625.74 2850.18 3750.15 6600.33 25.41 Forecast hours
298 Hrs
BUILD 13 Building 13 - Health 9726.39 249.00 9975.39 4506.93 5352.79 9859.72 115.67 428 Hrsat completion
BUILD 07 Building 7 - Services 12523.90 80.00 12603.90 2495.08 7854.28 10349.36 2254.54 2004 Hrs
BUILD 10 Building 10 - Papamauri 11288.04 3195.00 14483.04 1523.24 15167.00 16690.24 -2207.20 -1755 Hrs
BUILD 04 Building 4 - Entry Building 25974.68 1718.00 27692.68 6279.12 25161.58 31440.71 -3748.03 -1751 Hrs
BUILD 09 Building 9 - Visits 13330.93 354.00 13684.93 5241.28 8682.55 13923.83 -238.90 458 Hrs
BUILD 03 Building 3 - Assets and Properties 5774.24 376.00 6150.24 2222.09 3836.20 6058.29 91.95 -46 Hrs
BUILD 21 Building 21 - Remand 17231.87 472.00 17703.87 1384.23 16141.23 17525.46 178.41 494 Hrs
BUILD 20 Building 20 - Separates / Management 16035.81 552.00 16587.81 4943.56 13992.48 18936.05 -2348.24 -887 Hrs
BUILD 14 Building 14 - At Risk 13085.41 451.00 13536.41 5048.38 9490.45 14538.83 -1002.42 -1070 Hrs
BUILD 36 Building 36 - Community Centre 2 5258.99 1792.00 7050.99 623.95 6882.10 7506.05 -455.06 -824 Hrs
BUILD 37 Building 37 - Self Care 4130.45 62.00 4192.45 160.00 4466.90 4626.90 -434.45 -277 Hrs
BUILD 38 Building 38 - Self Care 4123.94 62.00 4185.94 192.00 4220.90 4412.90 -226.96 23 Hrs
Draft - SG Guide v1.6
BUILD 39 Building 39 - Self Care 4123.94 62.00 4185.94 224.00 3667.90 3891.90 294.04 412 Hrs
BUILD 40 Building 40 - Self Care 4123.94 62.00 4185.94 359.38 3851.15 4210.53 -24.59 23 Hrs
BUILD 41 Building 41 - Self Care 4123.94 62.00 4185.94 384.00 3617.15 4001.15 184.79 258 Hrs
BUILD 42 Building 42 - Self Care 4123.94 62.00 4185.94 633.28 3290.15 3923.43 262.51 342 Hrs
BUILD 43 Building 43 - Self Care 4123.94 62.00 4185.94 750.96 3167.69 3918.65 267.29 506 Hrs
BUILD 44 Building 44 - Self Care 4123.94 62.00 4185.94 775.39 2674.94 3450.33 735.61 411 Hrs
FENCING Security Fencing 22654.98 0.00 22654.98 9968.73 7932.50 17901.23 4753.75 3338 Hrs
All TOCProject:
Hours Accumulated as a Resource 4.
Resource
AUCKLAND REGION WOMEN'S CORRECTIONS FACILITY level based
on a 40 hour
working week
1000
750 persons
500 persons
Date
1-Feb-05 1-Mar-05 1-Apr-05 1-May-05 1-Jun-05 1-Jul-05 1-Aug-05 1-Sep-05 1-Oct-05 1-Nov-05 1-Dec-05 1-Jan-06 1-Feb-06 1-Mar-06 1-Apr-06 1-May-06 1-Jun-06 1-Jul-06
Budgeted and Actual TOC Hours to Complete 5.
Title : Budgeted and Actual TOC Hrs to Complete
Cost Estimate
TOC Hours are for on-site labour only. Earned Value Date of Report Data: 28 Nov05
Time Now Excludes fitout work
Budget Cost Recoverable Value Date Report Printed: 14 Dec 05
Budget Ceiling Actual Cost Chargeable Value
Hrs
600000.00
500000.00
400000.00
200000.00
Date
0.00
1-Sep-04 1-Oct-04 1-Nov-04 1-Dec-04 1-Jan-05 1-Feb-05 1-Mar-05 1-Apr-05 1-May-05 1-Jun-05 1-Jul-05 1-Aug-05 1-Sep-05 1-Oct-05 1-Nov-05 1-Dec-05 1-Jan-06 1-Feb-06 1-Mar-06 1-Apr-06 1-May-06 1-Jun-06 1-Jul-06