He shall be responsible for controlling the coordination between all involved parties to
ensure Safety, Quality, controlling the progress of work, civil and MEP clearance prior to
starting tiling work, and ensuring final approval is obtained prior to starting the next
activity.

Notifying the QC engineer and issuing the checklist (inspection request for
approval/checklist – Annex A, including all clearances as applicable in a timely manner
when work is ready for inspection.

Accompanying the Engineer’s representative for ongoing inspection and obtaining his
approval to proceed with the next activity.

The QA/QC Department is responsible for the overall inspection and documentation of
works in compliance with the work procedure and Project Specifications and shall be
responsible for coordination with Client for inspection activities and close out of the
NCR, if any.

The Survey Department is responsible for all the layouts / setting out and for
establishing the reference elevations related to the work.

He shall be responsible for controlling the coordination between all involved parties to
ensure Safety, Quality, controlling the progress of work, civil and MEP clearance prior to
starting tiling work, and ensuring final approval is obtained prior to starting the next
activity.

Notifying the QC engineer and issuing the checklist (inspection request for
approval/checklist – Annex A, including all clearances as applicable in a timely manner
when work is ready for inspection.

Accompanying the Engineer’s representative for ongoing inspection and obtaining his
approval to proceed with the next activity.

The QA/QC Department is responsible for the overall inspection and documentation of
works in compliance with the work procedure and Project Specifications and shall be
responsible for coordination with Client for inspection activities and close out of the
NCR, if any.

The Survey Department is responsible for all the layouts / setting out and for
establishing the reference elevations related to the work.

Accompanying the Engineer’s representative for ongoing inspection and obtaining his
approval to proceed with the next activity.
Project Doc. # Location Rev.

The QA/QC Department is responsible for the overall inspection and documentation of
works in compliance with the work procedure and Project Specifications and shall be
responsible for coordination with Client for inspection activities and close out of the
NCR, if any.

The Survey Department is responsible for all the layouts / setting out and for
establishing the reference elevations related to the work.

The QA/QC Department is responsible for the overall inspection and documentation of
works in compliance with the work procedure and Project Specifications and shall be
responsible for coordination with Client/Consultants for inspection activities and close
out of the NCR/ SON, if any, with Consultants representatives.

The Survey Department is responsible for all the layouts / setting out and for
establishing the reference elevations related to the work

Health and Safety Risks


 Before entering the area of operation, all staff will go through the health and
safety introduction. Employees will only be provided access permissions when
they have completed their induction.
 Before entering the area of operation, all staff will go through the health and
safety introduction. Employees will only be provided access permissions when
they have completed their induction.

 Access and egress onto the rear of any vehicle or trailer will be through a ladder
fastened to the truck or trailer’s side.
 No permit Job.

Controlling Health and Safety Risks


 Before beginning any activity, ensure that the work permit and any
accompanying documentation, such as RAMS, are signed and approved.
 Approved RAMS will be made available on-site, and job-specific dangers and
controls will be explained to all individuals participating in the job.
 Ascertain that every PPE is evaluated for job applicability, constraints,
capabilities, and compatibility with other PPE.
Project Doc. # Location Rev.

 Approved RAMS will be made available on-site, and job-specific dangers and
controls will be explained to all individuals participating in the job.
 Ensure that staff has received manual handling training.
 Use mechanical devices to avoid needless heavy manual handling of materials.

 Prior to beginning any job on site, all staff must get a safety induction/training.
 Job supervisors must have a pre-job STARRT/TBT meeting to inform workers
about job-specific dangers.

 Conduct a site examination to verify proper access/egress for job operations.


Maintain a clean working environment.
 There is lone working allowed.
 Maintain adequate housekeeping in the workspace.
 Notifying the QC engineer and issuing the checklist (inspection request for
approval/checklist – Annex A, including all clearances as applicable in a timely
manner when work is ready for inspection.
 Use the proper tools for the job. Do not utilize a tool or accessory for a task for
which it was not designed. Ensure that tools are inspected by a competent
person and that a record is kept. Color-coded as needed.
 Access and egress onto the rear of any vehicle or trailer ill be through a ladder
fastened to the truck or trailer’s side.
 No permit Job.
 Conduct a site examination to verify proper access/egress for job operations.
Maintain a clean working environment.
 There is lone working allowed.
 Maintain adequate housekeeping in the workspace.
 Use the proper tools for the job. Do not utilize a tool or accessory for a task for
which it was not designed. Ensure that tools are inspected by a competent
person and that a record is kept. Color-coded as needed.
 Access and egress onto the rear of any vehicle or trailer ill be through a ladder
fastened to the truck or trailer’s side.
 No permit Job.
 Conduct a site examination to verify proper access/egress for job operations.
Maintain a clean working environment.
 There is lone working allowed.
 Maintain adequate housekeeping in the workspace.
 Use the proper tools for the job. Do not utilize a tool or accessory for a task for
which it was not designed. Ensure that tools are inspected by a competent
person and that a record is kept. Color-coded as needed.
Project Doc. # Location Rev.

 Access and egress onto the rear of any vehicle or trailer ill be through a ladder
fastened to the truck or trailer’s side.
 No permit Job.