He shall be responsible for controlling the coordination between all involved parties to
ensure Safety, Quality, controlling the progress of work, civil and MEP clearance prior to
starting tiling work, and ensuring final approval is obtained prior to starting the next
activity.
Notifying the QC engineer and issuing the checklist (inspection request for
approval/checklist – Annex A, including all clearances as applicable in a timely manner
when work is ready for inspection.
Accompanying the Engineer’s representative for ongoing inspection and obtaining his
approval to proceed with the next activity.
The QA/QC Department is responsible for the overall inspection and documentation of
works in compliance with the work procedure and Project Specifications and shall be
responsible for coordination with Client for inspection activities and close out of the
NCR, if any.
The Survey Department is responsible for all the layouts / setting out and for
establishing the reference elevations related to the work.
He shall be responsible for controlling the coordination between all involved parties to
ensure Safety, Quality, controlling the progress of work, civil and MEP clearance prior to
starting tiling work, and ensuring final approval is obtained prior to starting the next
activity.
Notifying the QC engineer and issuing the checklist (inspection request for
approval/checklist – Annex A, including all clearances as applicable in a timely manner
when work is ready for inspection.
Accompanying the Engineer’s representative for ongoing inspection and obtaining his
approval to proceed with the next activity.
The QA/QC Department is responsible for the overall inspection and documentation of
works in compliance with the work procedure and Project Specifications and shall be
responsible for coordination with Client for inspection activities and close out of the
NCR, if any.
The Survey Department is responsible for all the layouts / setting out and for
establishing the reference elevations related to the work.
Accompanying the Engineer’s representative for ongoing inspection and obtaining his
approval to proceed with the next activity.
Project Doc. # Location Rev.
The QA/QC Department is responsible for the overall inspection and documentation of
works in compliance with the work procedure and Project Specifications and shall be
responsible for coordination with Client for inspection activities and close out of the
NCR, if any.
The Survey Department is responsible for all the layouts / setting out and for
establishing the reference elevations related to the work.
The QA/QC Department is responsible for the overall inspection and documentation of
works in compliance with the work procedure and Project Specifications and shall be
responsible for coordination with Client/Consultants for inspection activities and close
out of the NCR/ SON, if any, with Consultants representatives.
The Survey Department is responsible for all the layouts / setting out and for
establishing the reference elevations related to the work
Access and egress onto the rear of any vehicle or trailer will be through a ladder
fastened to the truck or trailer’s side.
No permit Job.
Approved RAMS will be made available on-site, and job-specific dangers and
controls will be explained to all individuals participating in the job.
Ensure that staff has received manual handling training.
Use mechanical devices to avoid needless heavy manual handling of materials.
Prior to beginning any job on site, all staff must get a safety induction/training.
Job supervisors must have a pre-job STARRT/TBT meeting to inform workers
about job-specific dangers.
Access and egress onto the rear of any vehicle or trailer ill be through a ladder
fastened to the truck or trailer’s side.
No permit Job.