Name of work:Furnace Construction at Nepal Rastra Bank
Location: Nepal Rastra Bank,JanakpurDham
QUANTITY ESTIMATE

SN Description Unit No L(m) B(m) H(m) Quantity Remarks


A. Construction Works

Providing and laying Brick Masonry Work


in Cement mortar in Foundation / structure
complete excluding Pointing and
1.0
Plastering, as per Drawing and Technical
Specifications.cement sand mortar (1:4)
(SS:25.1)

Wall m3 2.00 2.45 0.23 2.30 2.59


2.00 3.00 0.23 2.30 3.17
2.00 1.50 0.23 0.90 0.62
2.00 2.00 0.23 0.90 0.83
Total 7.22 M3
Providing and placing of 12.5 mm. thick
cement sand plaster work 1:4 on wall.(All
2.0
complete as per specifications )

Wall m2 2.00 2.45 2.30 11.27


2.00 3.00 2.30 13.80
4.00 1.75 0.90 6.30
Total 31.37 m2
Providing and fixing of the fire cotton in
3.0 between the sandwiches of the wall along
the chicken mesh
1.00 1.00
Total 1.00 Job
Dismantling of the brick structure and
disposing of the items at proper place as
4.0 directed by NRB.(Site Clearance of the
Place also included before & after
construction)
m2 1.00 1.00 Job
PCC for RCC @1:1.5:3 all complete as per
5.0 technical specifications & drawing
(Reinforcement and formwork included )
Sill Band m3 1.00 10.80 0.23 0.10 1.08
Lintel Band 1.00 10.80 0.23 0.15 1.62
Total 2.70 m3

Prepared and Submitted By Checked by Approved by