SWL: 5 TONS
This manual provides Installation , operation and maintenance information for the Fixed frame Gravity
lowered davit . Reference the serial number of the Davit when ordering spare parts.
Warning: It is the responsibility of the user to maintain and use the Davit in a safe manner. Failure to
do so can be dangerous and result in severe injury, fatality or property damage. All use and
maintenance shall conform to Manufacturer and any other regulatory agency requirements. An
inspection and maintenance log shall be kept and complied with.
Warranty
We warrant that our equipment is free from defect. Our liability is limited to the repair, or, at our
option, supply of a replacement, f.o.b. our factory, of any parts which proved to be defective due to
faulty material or workmanship within twelve months after shipment of the equipment from our
factory at Bahadurgarh. Normal wear and the consequence of improper use or application are not
covered by this warranty.
This warranty is expressly in lieu of any other express or implied warranties including any implied
warranty of merchantability or fitness and or any other obligation on the part of the seller
M S ENGINEERS
1073/1, Main Najafgarh Road,
Opposite Sector-9A, Bahadurgarh-124507, Haryana
Phone: 7678219407
Email: sales@mseotcranes.in
www.mshoistocranes.com
1
2
Table of Contents
Section I.
3
Installation of Hoist
A. Mounting of Davit
a. 1. The foundation needs to be completed prior supply of material at site , Pls ensure
foundation bolts are aligned as per drawing sent to you in order to ensure easy installation
on site .
B. Installation of Davit winch
a. Installation of the davit winch should be done after installation of the davit, same will
ensure that the wire ropes are aligned with the pulleys fitted on the Davit structure.
b. Davit winch foundation to be adequately designed and if possible to be connected to the
davit foundation by means of RCC beam structure .
C. Electrical
All Wiring must conform to National Electric Code Standards, in addition to any state and local
requirements.
1. Requirements:
The voltage supplied to this hoist must match the specification on the customer’ order to M S
ENGINEERS (3 PHASE 440V SUPPLY). Please ensure proper electrical supply to the
control panel as per design .
Please ensure adequate capacity of the wiring to supply power to the Davit winch motor
keeping in mind the high current requirement for the 3 phase motor .
4
Section II
Davit operation
M S ENGINEERS, recommends following the guidelines listed in Section II to properly operate your Davit .
These items are only a guide presented by M S ENGINEERS. The Hoist Operator MUST be instructed in the
safe and proper operation of hoist. The Hoist Operator must follow comply with regulatory agency requirements.
Please review the following Safe Hoisting Practices before using any M S ENGINEERS lifting appliance . These
practices MUST be employed during operation of the davit . Please nominate the hoist operator(s) for training in
operational , same will be carried out once by MS Engineering after installation of the Hoist.
The following must be performed after the Davit installation has been completed .
Wire Rope: The Wire Rope must be secured to the dead ending of the system. The length of the wire
rope must be adjusted so that both winch drums have the same level of layering of the wire ropes . If
equal wires are not wound on the winch drum ,both floating blocks will not move with the same speed ,
thus will cause imbalance of the boat . Ensure the wires are evenly layered on the winch drum , uneven
layering can cause sudden slippage of wire and excessive loads on the Davit structure .
5
B. Push Button Station
The Davit winch motor is controlled at the push button station. Push Button Stations are
configured specific to your requirements. There are always hoist UP and DOWN buttons. There is
a master switch installed to disconnect power to the push button station , same to be switched off
after use.
Circuit breakers are installed inside the electrical control box to protect against overloading of the
circuits and damage due to short circuit.
C. Safe Practices
Hand operated and electric hoists and trolleys of all types are designed with the safety of the
operating personnel first in mind. Your own safety and that of your fellow workers will be assured
when overhead materials handling equipment is used as recommended by the manufacturer.
Disregarding such recommendations endangers life and property. Following are the basic safety
rules worthy of your careful consideration and attention.
g. Ensure people inside the boat are safely seated before operating the winch
h. Do not jog controls unnecessarily. Hoist motors are general high torque, high slip
types. Each start causes an in rush of current greater than the running current and
leads to overheating and heat failure, or burn-out, if continues to excess
6
D. Structure
i. Davit structure will be subject to shearing forces during operation, thus visual inspection of
the structure should be performed and checked for deformations or cracks as mentioned in
the maintenance instructions
ii. Do not hang the boat midway for continued periods . Swinging of the boat can couse
damage to the davit foundations . It is recommended that the boat be stowed while resting
on the buffers provided for arresting swinging of the boat
iii. When lifting the boat , it is strongly recommended to avoid jerks by intermittent operation
of the winch . Please hoist the boat fully till the limit switch operates.
E. Lubrication:
1. HOOK BLOCKS:
Bearings pressed in Hook Blocks are pre-lubricated and regular lubrication is not required
2. PULLEYS :
a. All pulley bearings are pre lubricated and regular lubrication is not required
b. Please ensure steel ropes are well greased at all times to avoid mechanical
damage to the sheaves and the wire ropes . Greasing will also arrest rusting of
the wire ropes.
Refer to the Wiring Diagram in this manual to determine the particular configuration for you Davit.
Section III.
Maintenance of Davit
M S ENGINEERS, Inc. recommends following the guidelines listed in Section III to properly maintain
your hoist . Maintenance logs must be kept and all updated mandatory standards supersede the
following information.
MAINTENANCE SCHEDULE .
( PLEASE ENSURE PROPER PPE IS WORN BEFORE CARRYING OUT ANY
MAINTENANCE )
WEEKLY MAINTENANCE
1. Slack Davit wires by lowering the boat to water level and inspect for broken strands and
kinks . Grease wires if required.
7
2. Check electrical wires for insulation damage and loose connections
MONTHLY MAINTENANCE
1. Slack Davit wires fully / Unwind from winch drums , wipe old grease and apply fresh grease.
2. Check wire retention arrangement on pulleys for abrasion damage , repair if required
ANNUAL MAINTENANCE
5 YEARLY MAINTENANCE
8