NO PEKERJAAN SPESIFIKASI VOL SAT MATERIAL UPAH HARGA JUMLAH

1 Survey 1,0 lot - 4.550.000 4.550.000 4.550.000


2 Mod-demob main power & tools permit, Covid test (antigen - pcr) 1,0 lot - 19.500.000 19.500.000 19.500.000
- - - -

1 Pekerjaan galian 8,80 m3 - 195.000 195.000 1.716.000


2 Buang tanah & gragal Radius 3km 8,80 m3 - 325.000 325.000 2.860.000
3 Lantai kerja tebal 50mm k-150 1,20 m3 846.081 175.594 1.021.675 1.226.010
4 Pasir urug tebal 50mm 1,20 m3 195.975 35.276 231.251 277.501
5 Pembesian, Tulang utama 4-D13 sengkang Ø10 - 150 Rebar fy =240 mpa, fy = 360 mpa 119,97 kg 17.550 3.250 20.800 2.495.376
6 Begesting Playwood, kaso 5x7 2,85 m2 125.215 102.586 227.801 649.234
7 Pengecoran k-250, semen type 1 2,38 m3 1.365.000 214.500 1.579.500 3.759.210
8 Embeded plate, thick = 10mm , rebar Ø10 - 150 dim, 150x300x6mm, ss400 40,43 kg 20.800 15.600 36.400 1.471.652
- - - -

1 Pekerjaan galian 2,70 m3 - 195.000 195.000 526.500


2 Buang tanah & gragal Radius 3km 2,70 m3 - 325.000 325.000 877.500
3 Lantai kerja tebal 50mm k-150 0,10 m3 846.081 175.594 1.021.675 102.167
4 Pasir urug tebal 50mm 0,10 m3 195.975 35.276 231.251 23.125
5 Pembesian, Tulang utama 4-D13 sengkang Ø10 - 150 Rebar fy =240 mpa, fy = 360 mpa 41,99 kg 17.550 3.250 20.800 873.392
6 Begesting Playwood, kaso 5x7 1,58 m2 125.215 102.586 227.801 359.926
7 Pengecoran k-250, semen type 1 0,72 m3 1.365.000 214.500 1.579.500 1.137.240
8 Embeded plate, thick = 10mm , rebar Ø10 - 150 dim, 150x300x6mm, ss400 25,70 kg 20.800 15.600 36.400 935.480
- - - -

D.1 Pipe suport drain LPS - - - -


L 50x50x4 ss400 4,00 ea - - - -
U 100x50x5x7,5 ss400 4,00 ea - - - -
D.2 Pipe suport valve 12in - - - -
H 200x200x8x12 ss400 79,80 kg 20.800 15.600 36.400 2.904.720
Plate 10mm ss400 25,12 kg 20.800 15.600 36.400 914.368
Chemical angkur m12 Hilti RE-500 8,00 ea 227.500 130.000 357.500 2.860.000
D.3 Paint work Finish 100micron, jotun, hempel 2,0 m2 58.500 45.500 104.000 208.000

Total 50.227.401