Ministry of Megapolis and Western Development
Colombo Port City Development Project.
Completion Certificate for Land Plot No. 3-01-05
Project : Colombo Port City Development Project
Issued to : CHEC Port City Colombo (Private) Limited
Certificate No: 040/MMWD/CPCC/UDA/LP 3-01-05
cope of the Certificate
This certificate covers the completion of the Land Plot number 3-01-05 as illustrated in the
attached drawing number 14004 TO-P63 001 of the Reclamation Works of Colombo Port City
Development Project and all the completion tests as described in Part B of Schedule 17 in the
Tripartite Agreement dated 12" August 2016 signed between the Government of Sri Lanka
(“GOSL”), Urban Development Authority (“UDA”) and CHEC Port City Colombo (Private)
Limited (“Project Company”)
This Completion Certificate is issued to the Project Company in response to their request letter
reference CPCC/MOM& WD/EPC/015813 dated 18" October 2019.
Undertaking by the Project Company
Under the terms and conditions of the Tripartite Agreement dated 12" August 2016, we hereby
certify that in the opinion of the Project Company the Reclamation Works of the Land Plot
number 3-01-05 as illustrated in the attached drawing number 148004 TO-P63 001 of the
Colombo Port City Development Project has been completed. Further, we certify that all
completion tests as described in Part B of Schedule 17 of the Tripartite Agreement have been
completed in connection with the said Land Plot. We also undertake to comply with Clauses 19
and 20 of the Tripartite Agreement which deals with she rectification of defects, if any, during
the defects liability period, in connection with the said completed Land Plot.
In addition to that, in ease of damage caused to this Land Plot number 3-01-05 which may occur
while carrying out the Associated Works (refer Part C of Schedule 17) adjacent to this Land Plot
after issuance of this Certificate, we hereby agree to rezover and rectify such damages caused to
this Land Plot number 3-01-05 as required by the Tripartite Agreement.
Jiang Houliang
Managing Director
CHEC Port City Célombo (Private) LimitedCertificate of the Government of Sri
Ministry of Megapolis and Western Development (“MMWD") hereby certify that the Land Plot
number 3-01-05 has been successfully completed based on the Employers’ Quality
Representative's (EQR) Report reference BES280/EQR-LTR-282/GHEN/Col dated 30”
September 2019.
This Completion Certificate is issued subject to clauses 18.4, 19 and any other relevant
provisions in the Tripartite Agreement.
The defects liability period will be one year from the effective date of this Completion
Certificate and all the terms and conditions cited in the Tripartite Agreement are applicable to the
defects liability period as well.
‘The validity of land guarantees, insurance bonds and insurances should be extended according to
the terms and conditions of the Tripartite Agreement to cover the above defects liability period.
In the event of the Contractor's failure to remedy any of the defects, errors or malfunctions
brought to his notice by the Consultant/ Client, action would be taken against the Project
‘Company under the terms and conditions of the Tripartite Agreement.
The “Certificate of Making Good Defects” for the Land Plot number 3-01-05 specified in this
Completion Certificate will be issued separately by the GOSL under the clause 19.5 of the
Tripartite Agreement, if applicable, at the end of the defects liability period upon successful
rectification of all the defects by the Project Company.
Final Completion Certificate wil! be issued as per the clause number 184.5 of the Tripartite
‘Agreement, subject to fulfill the terms and conditions stipulated therein.
The effective Completion Date for Land Plot numaber 3-01-05 is 25" October 2019
Recommended by Certified by Approved by:
4. —*
E Gonaduwage Mr. Nihal Fethando Eng, Nihal Rupasinghe |
Deputy Project Director Project Director The Secretary
ial Femarde
ric Greer Camb Pat)
ty tages 4 arena