COMMENT SHEET

CLIENT GIGL DRAWING/DOCUMENTS No-


BOUNDARY WALL LAYOUT & DETAILING FOR
PROJECT MBPL-II
SV-4013
SECTION III GIGLM-1004-SV4013-CS-DRW-LAY-R-6015
CONTRACTOR JSIW INFRASTRUCTURE PVT. LTD REV-3

SR.NO. EIL COMMENT/ OBSERVATION RESOLUTION/ ACTION

Comments provided in doc no : GIGLM-1004-SV4013-CS-DOC-


CAL-R-6016_Rev_03 to be followed for this document.
1 INCORPORATED
SBC considered foundation design is not as per approved
foundation philosophy.

SR.NO. GIGL COMMENT/ OBSERVATION RESOLUTION/ ACTION

PIPE ENTRY / EXIT TO BE REVIEWED W.R.T TO APPROVED


1 INCORPORATED
PLOT PLAN & PIPING GAD

Doc. GIGLM-1004-SV4013-CS-DRW-LAY-R-6015 Rev. 04

01-MAY-2020
RAJESH BHIMRAO THUL (B894)
1 of 25

Page 1 of 25
COMMENT SHEET
CLIENT GIGL DRAWING/DOCUMENTS No-
BOUNDARY WALL LAYOUT & DETAILING FOR
PROJECT MBPL-II
SV-4013
SECTION III GIGLM-1004-SV4013-CS-DRW-LAY-R-6015
CONTRACTOR JSIW INFRASTRUCTURE PVT. LTD REV-2

SR.NO. COMMENT/ OBSERVATION RESOLUTION/ ACTION


Comments provided in doc no : GIGLM-1004-SV4013-CS-DOC-
1 NOTED & INCORPORATED
CAL-R-6016_Rev_02 to be followed for this document

AS PER GEOTECHNICAL RECOMMENDATION


& APPROVED PHILOSOPHY THE CORROSION
2 Note for corrosion inhibiting admixture to be added. INHIBITING ADMIXTURE NOT
REQUIRED AND THE SAME HAS SUBMITTED
BY MAIL TO MS GIGL

Doc. GIGLM-1004-SV4013-CS-DRW-LAY-R-6015 Rev. 04

01-MAY-2020
RAJESH BHIMRAO THUL (B894)
2 of 25

Page 2 of 25
COMMENT SHEET
CLIENT GIGL DRAWING/DOCUMENTS No-
BOUNDARY WALL LAYOUT & DETAILING FOR
PROJECT MBPL-II
SV-4013
SECTION III GIGLM-1004-SV4013-CS-DRW-LAY-R-6015
CONTRACTOR JSIW INFRASTRUCTURE PVT. LTD REV-1

SR.NO. COMMENT/ OBSERVATION RESOLUTION/ ACTION


COMMENTS PROVIDED ON IP-03 (BOUNDARY WALL
DRAWING), SIMILAR COMMENTS SHALL BE FOLLOWED FOR
1 SV-4013 (BOUNDARY WALL DRAWING). THE COMMENTED INCORPORATED
IP-03 DRAWING IS ATTACHED AS ANNEXURE-1 FOR
COMPLIANCE.

Doc. GIGLM-1004-SV4013-CS-DRW-LAY-R-6015 Rev. 04

01-MAY-2020
RAJESH BHIMRAO THUL (B894)
3 of 25

Page 3 of 25
COMMENT SHEET
CLIENT GIGL DRAWING/DOCUMENTS No-
BOUNDARY WALL LAYOUT & DETAILING FOR
PROJECT MBPL-II
SV-4013
SECTION III GIGLM-1004-SV4013-CS-DRW-LAY-R-6015
CONTRACTOR JSIW INFRASTRUCTURE PVT. LTD REV-0

SR.NO. COMMENT/ OBSERVATION RESOLUTION/ ACTION


EPC Contractor to submit Approved Boundary wall layout
1 superimposing with Approved Top survey drawing for checking INCORPORATED
existing NGL level.
EPC to submit Seismic Zone map superimposing with pipe line
2 routing for section with All stations marked for Seismic zone ATTACHED IN DRAWING
checking.
Document for General notes for Civil,Structural, Geotech,
3 Architectural,Construction to be submitted for review and ATTACHED IN DRAWING
reference of this document to be added in all drawings.
Foundation design philosophy to be submitted for review and Revised Foundation design philosophy is under
approval.As per discussion in meeting held on 22.10.2019 with preparation and the same will be submitted shortly.
4
client, in absence of foundation design philosophy document is Mean while it is requested to review the boundary
commented in CODE-3. wall layout and detailing for SV-4013

Separate design calculation for each structures for each station to


5 be submitted.A common design calculation of a similar type of INCORPORATED
structure is not acceptable.Contractor to ensure the same.
Contractor to refer drawing no. A286-000-16-48-1001 attached in
6 Bid document for design and drawing preparation of boundary INCORPORATED
wall.
Contractor to incoporate all comments in Comment resolution
7 NOTED
sheet (CRS) attached in BID document.
GENERAL CIVIL COMMENTS:
1 FGL shall be as per approved overall plot plan. NOTED
All the plant co-ordinates shall be as per approved overall plot
2 NOTED
plan.
Co-ordinates of the boundary wall/ compound wall shall be as per
3 NOTED
approved overall plot plan.
Type of boundary wall/ compound wall shall be as per approved
4 NOTED
overall plot plan.
Height of boundary wall/ compound wall shall be as per approved
5 NOTED
overall plot plan.
DETAILS OF COMPOUND WALL/ BOUNDARY WALL, NOTES,
SPACING, CONCERTINA COIL, ETC., SHALL BE FOLLOWED
6 AS PER DRAWINGS (A286-000-16-47-3001, A286-000-16-47- NOTED
3007 AND A286-000-16-47-3011), AS APPLICABLE, ATTACHED
WITH THE TENDER.

Doc. GIGLM-1004-SV4013-CS-DRW-LAY-R-6015 Rev. 04

01-MAY-2020
RAJESH BHIMRAO THUL (B894)
4 of 25

Page 4 of 25
Atit Shah <atit@jsiwinfra.com>

MBPL Sec-03 & 07: Request for observation on use of Corrosion inhibiting
admixtures in soil
Atit Shah <atit@jsiwinfra.com> Tue, Dec 17, 2019 at 2:21 PM
Reply-To: atit@jsiwinfra.com
To: Section 3 <gigl.mbplsection3@gspc.in>
Cc: Section 7 <gigl.mbplsection7@gspc.in>, Pramod Yenge <pramod@gspc.in>, Amitava Mukherjee
<Amitava.m@gspc.in>, JSIW INFRA ALPESHBHAI <apatel@jsiwinfra.com>, aboxi@jsiwinfra.com,
rakeshsingh@jsiwinfra.com, jsiw.giglmbpl3@gmail.com, JSIW-GIGL-MBPL Sec-7 <jsiw.giglmbpl7@gmail.com>,
kamlesh.jsiw@gmail.com

Dear Sir,

With reference to the part 2 of Clause no 3.2 of document no A286-000-16-60-SP-0009 Rev-03 wherein it is
recommended to take remedial action for foundations due to aggressiveness of Sub-soil/ water as per Geo-technical
recommendation for each station. Based on the approved Geo-technical report for all station, IS 456:2000 and
attached recommendation of geo-technical agency, we would like to clarify that the chemical content of soil at each
station is well within the permissible limits and also the underground water is not encountered in any of the station up
to depth of 15 meter. So therefor it is prove that there is no requirement of addition of any admixture for corrosion
resistance since there is no effect on embedded steel of underground concrete.

In view of above said clarification, we would like to start the concrete casting work at all station without add any type
of admixture for corrosion resistance.

Regards

ATIT SHAH
JSIW Infrastructure Pvt Ltd,

D-901, Ganesh Meridan,

Opp. Kargil Petrol Pump,

S. G. Highway, Sola,

Ahmedabad.

Ph: 097277 13500

From: KCT Consultancy Services [mailto:kctconser@yahoo.com]


Sent: 16 December 2019 17:51
To: A t Shah <atit@jsiwinfra.com>
Doc. GIGLM-1004-SV4013-CS-DRW-LAY-R-6015 Rev. 04
Cc: 'JSIW INFRA ALPESHBHAI' <apatel@jsiwinfra.com>; aboxi@jsiwinfra.com
Subject: Re: MBPL Sec-03 & 07: Request for observa on on use of Corrosion inhibi ng admixtures in soil
[Quoted text hidden]

01-MAY-2020
Letter for JSIW.PDF
RAJESH BHIMRAO THUL (B894)
5 of 25

Page 5 of 25
K.C.T. Consultancy Servicel Regd. No. : ABfTC/ReniE-I/S294
O.No. AB-Tender-5604-2012
Soil Testing, Material Testing, Surveying PAN: AAIFK4674L
ServicesTax No : AAIFK 4674lSTOOl
NABL (ISO/IEC : 17025) Accredited
Prof.Dr. K.C. Thaker (scope of our accreditation available on fflW.nabl-indla.orgj
B.E.(C), M.Tech (S.M.)(I.I.T.Bombay)
Ph.D.(I.I.T.Bombay)
F.I.E.; (India) F.I.G.S. M.I.S.T.E.; F.A.C.C.E
Adj. Prof. : D. D. Uni. Nadi'ad
Regd. Office .
$,9
ISO 9001 :2015 C.rtl"ed Company

"KCTHOUSE,'
Dr. K.K. Thaker Shayona Silver Estate Part-2, Tel. 7096034034-35035-36036
B.E (C) (Gold Medalist) BIh.Silver Oak College of Engineenng. Mobile 9825064378
M. E. (Geotech); Ph.D. (Geotech), M.B.A. (Finance) Nr. Lambda, Beside Auda Water Tank, E-mail kctconser@ya~oo:com
M.I.E.; M.I.G.S.; M.G.I.C.E.A.; F.A.C.C.E S.G.Road, Gota, Ahmedabad - 382481 Website www.kctcs.in

Ref. No.:
Date:

Date - 16112/2019

Subject: - Regarding use of corrosion inhibitors for stations of section 3 for Mehsana Bhatinda
Pipeline.

To - JSIW

Dear Sir,

From the results of chemical analysis it can be concluded that it falls in class 1 oftabl~ 4 of IS
456:2000 from standpoint of view of (S03) content and (chloride) content being less than 500
mg per litre, with this chemical mark-up the soil may be considered as insignificantly corrosive
to the embedded reinforcement steel and therefore corrosion inhibitors may not be necessary.

Thanking you

Ic('<--~
Thaker
K.K.

Doc. GIGLM-1004-SV4013-CS-DRW-LAY-R-6015 Rev. 04

01-MAY-2020
RAJESH BHIMRAO THUL (B894)
6 of 25

Page 6 of 25
REFERENCE DRAWING / DOCUMENTS

NOTES :-

TYPE-C
(Y)

TYPE-A(X) TYPE-A(Y)

TYPE-A(Y)
TYPE-C
(X)

TYPE-A(X)
LEGEND:-

TYPE-C
(Y) TYPE-A(Y)

CLIENT:
GSPL INDIA GASNET LIMITED

GSPL INDIA GASNET LIMITED

CONSULTANT:
ENGINEERS INDIA LIMITED

TPIA:
CERTIFICATION ENGINEERS INTERNATIONAL LTD.

EPC CONTRACTOR: JSIW Infrastructure Pvt.Ltd

DEC:
PETROCON ENGINEERS & CONSULTANTS

PROJECT:

MEHSANA–BATHINDA PIPELINE PROJECT

TITLE: BOUNDARY WALL LAYOUT & DETAILING


FOR SV-4013
Doc. GIGLM-1004-SV4013-CS-DRW-LAY-R-6015 Rev. 04 SIZE:
SCALE:
SHEET:

01-MAY-2020
RAJESH BHIMRAO THUL (B894)
7 of 25

Page 7 of 25
TYPE - C (Y)

GSPL INDIA GASNET LIMITED

GSPL INDIA GASNET LIMITED

ENGINEERS INDIA LIMITED

CERTIFICATION ENGINEERS INTERNATIONAL LTD.

JSIW Infrastructure Pvt.Ltd

PETROCON ENGINEERS & CONSULTANTS

MEHSANA–BATHINDA PIPELINE PROJECT

BOUNDARY WALL LAYOUT & DETAILING


FOR SV-4013
Doc. GIGLM-1004-SV4013-CS-DRW-LAY-R-6015 Rev. 04

01-MAY-2020
RAJESH BHIMRAO THUL (B894)
8 of 25

Page 8 of 25
TYPE - C (X)

GSPL INDIA GASNET LIMITED

GSPL INDIA GASNET LIMITED

ENGINEERS INDIA LIMITED

CERTIFICATION ENGINEERS INTERNATIONAL LTD.

JSIW Infrastructure Pvt.Ltd

PETROCON ENGINEERS & CONSULTANTS

MEHSANA–BATHINDA PIPELINE PROJECT

BOUNDARY WALL LAYOUT & DETAILING


FOR SV-4013
Doc. GIGLM-1004-SV4013-CS-DRW-LAY-R-6015 Rev. 04

01-MAY-2020
RAJESH BHIMRAO THUL (B894)
9 of 25

Page 9 of 25
TYPE - A (Y)

GSPL INDIA GASNET LIMITED

GSPL INDIA GASNET LIMITED

ENGINEERS INDIA LIMITED

CERTIFICATION ENGINEERS INTERNATIONAL LTD.

JSIW Infrastructure Pvt.Ltd

PETROCON ENGINEERS & CONSULTANTS

MEHSANA–BATHINDA PIPELINE PROJECT

BOUNDARY WALL LAYOUT & DETAILING


FOR SV-4013
Doc. GIGLM-1004-SV4013-CS-DRW-LAY-R-6015 Rev. 04

01-MAY-2020
RAJESH BHIMRAO THUL (B894)
10 of 25

Page 10 of 25
TYPE - A ('X')

GSPL INDIA GASNET LIMITED

GSPL INDIA GASNET LIMITED

ENGINEERS INDIA LIMITED

CERTIFICATION ENGINEERS INTERNATIONAL LTD.

JSIW Infrastructure Pvt.Ltd

PETROCON ENGINEERS & CONSULTANTS

MEHSANA–BATHINDA PIPELINE PROJECT

BOUNDARY WALL LAYOUT & DETAILING


FOR SV-4013
Doc. GIGLM-1004-SV4013-CS-DRW-LAY-R-6015 Rev. 04

01-MAY-2020
RAJESH BHIMRAO THUL (B894)
11 of 25

Page 11 of 25
TYPE-C
(Y)

. 6 37
9
39

TYPE-A(X) TYPE-A(Y) 61
0.7
40

TYPE-A(Y)
50
8.6
39 TYPE-C
(X)

TYPE-A(X)

. 4 02
9
39
TYPE-C
(Y) TYPE-A(Y)

Doc. GIGLM-1004-SV4013-CS-DRW-LAY-R-6015 Rev. 04

01-MAY-2020
RAJESH BHIMRAO THUL (B894)
12 of 25

Page 12 of 25
FINAL APPROVED DRAWINGS/ DOCUMENTS ALONG THE CRS SHALL BE SUBMITTED (HARD
AND SOFT COPIES) AS PER THE CONTRACT REQUIREMENTS. REFER ATTACHED MINOR
COMMENTS FOR CONTRACTOR'S COMPLIANCE.

Doc. GIGLM-1004-SV4013-CS-DRW-LAY-R-6015 Rev. 04

01-MAY-2020
RAJESH BHIMRAO THUL (B894)
13 of 25

Page 13 of 25
COMMENT SHEET
CLIENT GIGL DRAWING/DOCUMENTS No-
BOUNDARY WALL LAYOUT & DETAILING FOR
PROJECT MBPL-II
SV-4013
SECTION III GIGLM-1004-SV4013-CS-DRW-LAY-R-6015
CONTRACTOR JSIW INFRASTRUCTURE PVT. LTD REV-3

SR.NO. EIL COMMENT/ OBSERVATION RESOLUTION/ ACTION

Comments provided in doc no : GIGLM-1004-SV4013-CS-DOC-


CAL-R-6016_Rev_03 to be followed for this document.
1 INCORPORATED
SBC considered foundation design is not as per approved
foundation philosophy.

SR.NO. GIGL COMMENT/ OBSERVATION RESOLUTION/ ACTION

PIPE ENTRY / EXIT TO BE REVIEWED W.R.T TO APPROVED


1 INCORPORATED
PLOT PLAN & PIPING GAD

GENERAL CIVIL COMMENTS:


.
CONTRACTOR TO FURNISH THE CONSOLIDATED
Doc. GIGLM-1004-SV4013-CS-DRW-LAY-R-6015
COMMENT Rev. 04 RESOLUTION SHEET (CRS) (i.e. comments/

resolution provided since first submission to latest submission


of drawing) WITHOUT CRS THE DRAWINGS SHALL NOT
BE REVIEWED AND SHALL BE DEEMED AS NULL & VOID.
01-MAY-2020
RAJESH BHIMRAO THUL (B894)
14 of 25

Page 14 of 25
COMMENT SHEET
CLIENT GIGL DRAWING/DOCUMENTS No-
BOUNDARY WALL LAYOUT & DETAILING FOR
PROJECT MBPL-II
SV-4013
SECTION III GIGLM-1004-SV4013-CS-DRW-LAY-R-6015
CONTRACTOR JSIW INFRASTRUCTURE PVT. LTD REV-2

SR.NO. COMMENT/ OBSERVATION RESOLUTION/ ACTION


Comments provided in doc no : GIGLM-1004-SV4013-CS-DOC-
1 NOTED & INCORPORATED
CAL-R-6016_Rev_02 to be followed for this document

AS PER GEOTECHNICAL RECOMMENDATION


& APPROVED PHILOSOPHY THE CORROSION
2 Note for corrosion inhibiting admixture to be added. INHIBITING ADMIXTURE NOT
REQUIRED AND THE SAME HAS SUBMITTED
BY MAIL TO MS GIGL

Doc. GIGLM-1004-SV4013-CS-DRW-LAY-R-6015 Rev. 04

01-MAY-2020
RAJESH BHIMRAO THUL (B894)
15 of 25

Page 15 of 25
COMMENT SHEET
CLIENT GIGL DRAWING/DOCUMENTS No-
BOUNDARY WALL LAYOUT & DETAILING FOR
PROJECT MBPL-II
SV-4013
SECTION III GIGLM-1004-SV4013-CS-DRW-LAY-R-6015
CONTRACTOR JSIW INFRASTRUCTURE PVT. LTD REV-1

SR.NO. COMMENT/ OBSERVATION RESOLUTION/ ACTION


COMMENTS PROVIDED ON IP-03 (BOUNDARY WALL
DRAWING), SIMILAR COMMENTS SHALL BE FOLLOWED FOR
1 SV-4013 (BOUNDARY WALL DRAWING). THE COMMENTED INCORPORATED
IP-03 DRAWING IS ATTACHED AS ANNEXURE-1 FOR
COMPLIANCE.

Doc. GIGLM-1004-SV4013-CS-DRW-LAY-R-6015 Rev. 04

01-MAY-2020
RAJESH BHIMRAO THUL (B894)
16 of 25

Page 16 of 25
COMMENT SHEET
CLIENT GIGL DRAWING/DOCUMENTS No-
BOUNDARY WALL LAYOUT & DETAILING FOR
PROJECT MBPL-II
SV-4013
SECTION III GIGLM-1004-SV4013-CS-DRW-LAY-R-6015
CONTRACTOR JSIW INFRASTRUCTURE PVT. LTD REV-0

SR.NO. COMMENT/ OBSERVATION RESOLUTION/ ACTION


EPC Contractor to submit Approved Boundary wall layout
1 superimposing with Approved Top survey drawing for checking INCORPORATED
existing NGL level.
EPC to submit Seismic Zone map superimposing with pipe line
2 routing for section with All stations marked for Seismic zone ATTACHED IN DRAWING
checking.
Document for General notes for Civil,Structural, Geotech,
3 Architectural,Construction to be submitted for review and ATTACHED IN DRAWING
reference of this document to be added in all drawings.
Foundation design philosophy to be submitted for review and Revised Foundation design philosophy is under
approval.As per discussion in meeting held on 22.10.2019 with preparation and the same will be submitted shortly.
4
client, in absence of foundation design philosophy document is Mean while it is requested to review the boundary
commented in CODE-3. wall layout and detailing for SV-4013

Separate design calculation for each structures for each station to


5 be submitted.A common design calculation of a similar type of INCORPORATED
structure is not acceptable.Contractor to ensure the same.
Contractor to refer drawing no. A286-000-16-48-1001 attached in
6 Bid document for design and drawing preparation of boundary INCORPORATED
wall.
Contractor to incoporate all comments in Comment resolution
7 NOTED
sheet (CRS) attached in BID document.
GENERAL CIVIL COMMENTS:
1 FGL shall be as per approved overall plot plan. NOTED
All the plant co-ordinates shall be as per approved overall plot
2 NOTED
plan.
Co-ordinates of the boundary wall/ compound wall shall be as per
3 NOTED
approved overall plot plan.
Type of boundary wall/ compound wall shall be as per approved
4 NOTED
overall plot plan.
Height of boundary wall/ compound wall shall be as per approved
5 NOTED
overall plot plan.
DETAILS OF COMPOUND WALL/ BOUNDARY WALL, NOTES,
SPACING, CONCERTINA COIL, ETC., SHALL BE FOLLOWED
6 AS PER DRAWINGS (A286-000-16-47-3001, A286-000-16-47- NOTED
3007 AND A286-000-16-47-3011), AS APPLICABLE, ATTACHED
WITH THE TENDER.

Doc. GIGLM-1004-SV4013-CS-DRW-LAY-R-6015 Rev. 04


CONTRACTOR'S RESPONSIBILITY TO
ENSURE COMPLIANCE OF THESE
COMMENTS.

01-MAY-2020
RAJESH BHIMRAO THUL (B894)
17 of 25

Page 17 of 25
Atit Shah <atit@jsiwinfra.com>

MBPL Sec-03 & 07: Request for observation on use of Corrosion inhibiting
admixtures in soil
Atit Shah <atit@jsiwinfra.com> Tue, Dec 17, 2019 at 2:21 PM
Reply-To: atit@jsiwinfra.com
To: Section 3 <gigl.mbplsection3@gspc.in>
Cc: Section 7 <gigl.mbplsection7@gspc.in>, Pramod Yenge <pramod@gspc.in>, Amitava Mukherjee
<Amitava.m@gspc.in>, JSIW INFRA ALPESHBHAI <apatel@jsiwinfra.com>, aboxi@jsiwinfra.com,
rakeshsingh@jsiwinfra.com, jsiw.giglmbpl3@gmail.com, JSIW-GIGL-MBPL Sec-7 <jsiw.giglmbpl7@gmail.com>,
kamlesh.jsiw@gmail.com

Dear Sir,

With reference to the part 2 of Clause no 3.2 of document no A286-000-16-60-SP-0009 Rev-03 wherein it is
recommended to take remedial action for foundations due to aggressiveness of Sub-soil/ water as per Geo-technical
recommendation for each station. Based on the approved Geo-technical report for all station, IS 456:2000 and
attached recommendation of geo-technical agency, we would like to clarify that the chemical content of soil at each
station is well within the permissible limits and also the underground water is not encountered in any of the station up
to depth of 15 meter. So therefor it is prove that there is no requirement of addition of any admixture for corrosion
resistance since there is no effect on embedded steel of underground concrete.

In view of above said clarification, we would like to start the concrete casting work at all station without add any type
of admixture for corrosion resistance.

Regards

ATIT SHAH
JSIW Infrastructure Pvt Ltd,

D-901, Ganesh Meridan,

Opp. Kargil Petrol Pump,

S. G. Highway, Sola,

Ahmedabad.

Ph: 097277 13500

From: KCT Consultancy Services [mailto:kctconser@yahoo.com]


Sent: 16 December 2019 17:51
To: A t Shah <atit@jsiwinfra.com>
Doc. GIGLM-1004-SV4013-CS-DRW-LAY-R-6015 Rev. 04
Cc: 'JSIW INFRA ALPESHBHAI' <apatel@jsiwinfra.com>; aboxi@jsiwinfra.com
Subject: Re: MBPL Sec-03 & 07: Request for observa on on use of Corrosion inhibi ng admixtures in soil
[Quoted text hidden]

01-MAY-2020
Letter for JSIW.PDF
RAJESH BHIMRAO THUL (B894)
18 of 25

Page 18 of 25
K.C.T. Consultancy Servicel Regd. No. : ABfTC/ReniE-I/S294
O.No. AB-Tender-5604-2012
Soil Testing, Material Testing, Surveying PAN: AAIFK4674L
ServicesTax No : AAIFK 4674lSTOOl
NABL (ISO/IEC : 17025) Accredited
Prof.Dr. K.C. Thaker (scope of our accreditation available on fflW.nabl-indla.orgj
B.E.(C), M.Tech (S.M.)(I.I.T.Bombay)
Ph.D.(I.I.T.Bombay)
F.I.E.; (India) F.I.G.S. M.I.S.T.E.; F.A.C.C.E
Adj. Prof. : D. D. Uni. Nadi'ad
Regd. Office .
$,9
ISO 9001 :2015 C.rtl"ed Company

"KCTHOUSE,'
Dr. K.K. Thaker Shayona Silver Estate Part-2, Tel. 7096034034-35035-36036
B.E (C) (Gold Medalist) BIh.Silver Oak College of Engineenng. Mobile 9825064378
M. E. (Geotech); Ph.D. (Geotech), M.B.A. (Finance) Nr. Lambda, Beside Auda Water Tank, E-mail kctconser@ya~oo:com
M.I.E.; M.I.G.S.; M.G.I.C.E.A.; F.A.C.C.E S.G.Road, Gota, Ahmedabad - 382481 Website www.kctcs.in

Ref. No.:
Date:

Date - 16112/2019

Subject: - Regarding use of corrosion inhibitors for stations of section 3 for Mehsana Bhatinda
Pipeline.

To - JSIW

Dear Sir,

From the results of chemical analysis it can be concluded that it falls in class 1 oftabl~ 4 of IS
456:2000 from standpoint of view of (S03) content and (chloride) content being less than 500
mg per litre, with this chemical mark-up the soil may be considered as insignificantly corrosive
to the embedded reinforcement steel and therefore corrosion inhibitors may not be necessary.

Thanking you

Ic('<--~
Thaker
K.K.

Doc. GIGLM-1004-SV4013-CS-DRW-LAY-R-6015 Rev. 04

01-MAY-2020
RAJESH BHIMRAO THUL (B894)
19 of 25

Page 19 of 25
REFERENCE DRAWING / DOCUMENTS

NOTES :-

TYPE-C
(Y)

TYPE-A(X) TYPE-A(Y)

TYPE-A(Y)
TYPE-C
(X)

TYPE-A(X)
LEGEND:-

TYPE-C
(Y) TYPE-A(Y)

CLIENT:
GSPL INDIA GASNET LIMITED

GSPL INDIA GASNET LIMITED

CONSULTANT:
ENGINEERS INDIA LIMITED

TPIA:
CERTIFICATION ENGINEERS INTERNATIONAL LTD.

EPC CONTRACTOR: JSIW Infrastructure Pvt.Ltd

DEC:
PETROCON ENGINEERS & CONSULTANTS

PROJECT:

MEHSANA–BATHINDA PIPELINE PROJECT

TITLE: BOUNDARY WALL LAYOUT & DETAILING


FOR SV-4013
Doc. GIGLM-1004-SV4013-CS-DRW-LAY-R-6015 Rev. 04 SIZE:
SCALE:
SHEET:

01-MAY-2020
RAJESH BHIMRAO THUL (B894)
20 of 25

Page 20 of 25
TYPE - C (Y)

GSPL INDIA GASNET LIMITED

GSPL INDIA GASNET LIMITED

ENGINEERS INDIA LIMITED

CERTIFICATION ENGINEERS INTERNATIONAL LTD.

JSIW Infrastructure Pvt.Ltd

PETROCON ENGINEERS & CONSULTANTS

MEHSANA–BATHINDA PIPELINE PROJECT

BOUNDARY WALL LAYOUT & DETAILING


FOR SV-4013
Doc. GIGLM-1004-SV4013-CS-DRW-LAY-R-6015 Rev. 04

01-MAY-2020
RAJESH BHIMRAO THUL (B894)
21 of 25

Page 21 of 25
TYPE - C (X)

GSPL INDIA GASNET LIMITED

GSPL INDIA GASNET LIMITED

ENGINEERS INDIA LIMITED

CERTIFICATION ENGINEERS INTERNATIONAL LTD.

JSIW Infrastructure Pvt.Ltd

PETROCON ENGINEERS & CONSULTANTS

MEHSANA–BATHINDA PIPELINE PROJECT

BOUNDARY WALL LAYOUT & DETAILING


FOR SV-4013
Doc. GIGLM-1004-SV4013-CS-DRW-LAY-R-6015 Rev. 04

01-MAY-2020
RAJESH BHIMRAO THUL (B894)
22 of 25

Page 22 of 25
TYPE - A (Y)

GSPL INDIA GASNET LIMITED

GSPL INDIA GASNET LIMITED

ENGINEERS INDIA LIMITED

CERTIFICATION ENGINEERS INTERNATIONAL LTD.

JSIW Infrastructure Pvt.Ltd

PETROCON ENGINEERS & CONSULTANTS

MEHSANA–BATHINDA PIPELINE PROJECT

BOUNDARY WALL LAYOUT & DETAILING


FOR SV-4013
Doc. GIGLM-1004-SV4013-CS-DRW-LAY-R-6015 Rev. 04

01-MAY-2020
RAJESH BHIMRAO THUL (B894)
23 of 25

Page 23 of 25
TYPE - A ('X')

GSPL INDIA GASNET LIMITED

GSPL INDIA GASNET LIMITED

ENGINEERS INDIA LIMITED

CERTIFICATION ENGINEERS INTERNATIONAL LTD.

JSIW Infrastructure Pvt.Ltd

PETROCON ENGINEERS & CONSULTANTS

MEHSANA–BATHINDA PIPELINE PROJECT

BOUNDARY WALL LAYOUT & DETAILING


FOR SV-4013
Doc. GIGLM-1004-SV4013-CS-DRW-LAY-R-6015 Rev. 04

01-MAY-2020
RAJESH BHIMRAO THUL (B894)
24 of 25

Page 24 of 25
TYPE-C
(Y)

. 6 37
9
39

TYPE-A(X) TYPE-A(Y) 61
0.7
40

TYPE-A(Y)
50
8.6
39 TYPE-C
(X)

TYPE-A(X)

. 4 02
9
39
TYPE-C
(Y) TYPE-A(Y)

Doc. GIGLM-1004-SV4013-CS-DRW-LAY-R-6015 Rev. 04

01-MAY-2020
RAJESH BHIMRAO THUL (B894)
25 of 25

Page 25 of 25