Professional Documents
Culture Documents
ELECTRICAL
BOOK 1 OF 2
1
2
3
4
5
6
DESCRIPTION
The course is divided into two parts, Electrical and Mechanical, two books for each,
with six units in Electrical and and ten units in Mechanical. The participants will
acquire necessary know ledge and skills needed to perform various performance tasks
in different electrical crafts, in accordance with the SEC standard field practices and
procedures.
OBJECTIVES
7
8
UNIT-1
9
10
UNIT-1
SEC NETWORK, STANDARDS AND GENERATORS
UNIT OVERVIEW
DESCRIPTION
Lesson 1.1 familiarizes the participants with different electrical crafts in SEC
Network and their Duties and Responsibilities, as Substation Maintenance Technician,
Relay Technician, Cableman, Lineman, Network Operator, Instrument Technician,
Power Plant Operator, Power Plant Electrician, Distribution Electrician, Water
Treatment Plant Operator, Telecom Technician, and SCADA Technician.
∑ Lesson 1.2 familiarizes the participants with SEC Standards for Transmission
Material Standards' Specifications (TMSS), Transmission Engineering
Specifications (TES), Transmission Construction Specifications (TCS).
Transmission Development Specifications (TDS), Saudi Electricity Company
Engineering Drawings' Standards (SEEDS), SEC Distribution Material
Specifications (SDMS), Design Standards for Construction of Distribution
Systems (SDCS), Customer Service Manual (CSM), Distribution Safety Manual
(DSM), Distribution Operation Manual (DOM), Distribution Maintenance M anual
(DMM), Distribution Planning Standards (DPS), Craft Certification Manuals
(CCMs).
This lesson demonstrates how the Standards/Manuals are accessed to keep up -to-date
records of stock items, documents and drawings.
In Lesson 1.3, generators and Excitation System include Stator, Rotor, Bearings,
Lubrication System, Thermocouples, Seal Oil System, Main Leads, Current
Transformers, Neutral Grounding Transformer and Resistor-Temperature Detectors,
Generator Frame, Generator Cooling, Hydrogen Blower and Cooler, Hydrogen Gas
System, Gland Seals System, Excitation System, Brush and Slip Ring Excitation,
Brushless Excitation, Parallel Operation of Generators.
The lesson concludes with Preventive Maintenance.
11
OBJECTIVES
Upon completion of this unit, the particip ants should be able to familiarize with:
∑ SEC Network
∑ Duties and Responsibilities of electrical Crafts in SEC Network as:
Substation Maintenance Technician, Relay Technician, Cableman, Lineman,
Network Operator, Instrument Technician, Power Plant Operator, Power Plant
Electrician, Distribution Electrician, Water Treatment Plant Operator, Telecom
Technician, SCADA Technician
Task 1.1-1 Power System Simulator–Generation, Transmission and Distribution
∑ Standards/Manuals and their Accessibility
Transmission Material Standards' Specifications (TMSS), Transmission
Engineering Specifications (TES), Transmission Construction Specifications
(TCS). Transmission Development Specifications (TDS), Saudi Electricity
Company Engineering Drawings ' Standards (SEEDS), SEC Distribution Material
Specifications (SDMS), Design Standards for Construction of Distribution
Systems (SDCS), Customer Service Manual (CSM), Distribution Safety Manual
(DSM), Distribution Operation Manual (DOM), Distribution Maintenance Manual
(DMM), Distribution Planning Standards (DPS), Craft Certification Manuals
(CCMs)
∑ Power Plant generators and their operation.
∑ Generator components and their functional characteristics including:
Stator, Rotor, Bearings, Lubrication System, Thermocouples, Seal Oil System,
Main Leads, Current Transformers, Neutral Grounding Transformer and Resistor-
Temperature Detectors (RTD), Generator Frame, Generator Cooling, Hydrogen
Blower and Cooler, Hydrogen Gas System, Gland Seals System.
∑ Excitation Systems including Brush and Slip Ri ng Excitation, Brushless Excitation
with Parallel Operation of Generators.
∑ Preventive Maintenance of generators in Power Plants.
Task 1.1-3: Operation of Polyphase generators using Power System Simulator
12
LESSON 1.1
SEC NETWORK
13
14
LESSON 1.1
SEC NETWORK
LESSON OVERVIEW
DESCRIPTION
This lesson familiarizes the participants with different electrical crafts in SEC
Network and their Duties and Responsibilities as Substation Maintenance Technician,
Relay Technician, Cableman, Lineman, Network Operator, Instrument Technician,
Power Plant Operator, Power Plant Electrician, Distribution Electrician, Water
Treatment Plant Operator, Telecom Technician, and SCADA Technician.
OBJECTIVES
15
16
17
GENERATION
The major Electrical Power System components are used either in generation or
transfer of elec tricity.
GENERATING SETS
Each generator in a power plant is driven by its own prime mover (driver). A
turbine or a motor is a prime mover . Each generator is attached to its own prime
mover to make up a single unit or a set. The term generating set includes both a
prime mover and a generator.
You know that electrical power output is proportional to mechanical power input.
A generator design capability (maximum output or maximum load) is expressed
in electrical units, such as 10 Mega-Watts (10 MW).
NETWORK
A network is an advanced type of electrical power system. An electrical network
consists of several power plants. They are connected together by transmission lines (or
cables) and switchgear ( Fig. 1.1-4). Each power plant in the network acts as part of a
"team" instead of working alone. The term "electrical power system" and "electrical
18
power network" are used to describe this team. "SEC electrical power generation
system" and "SEC network" both mean the same as the whole system involving all the
power.
However, the heat can also be provided by solar energy or nuclear fuel. The
superheated steam leaving the boiler then enters the steam turbine throttle, where it
powers the turbine and connected generator to make electricity. After the steam
expands through the turbine, it exits th e back end of the turbine, where it is cooled and
condensed back to water in the surface condenser. This condensate is then returned to
the boiler through high-pressure feed pumps for reuse. Heat from the condensing
19
steam is normally rejected from the condenser to a body of water, such as a river or
cooling tower. Steam turbine power plants operate on a Rankin cycle.
20
21
22
Load
The amount of electrical power needed or demanded by the user at any
particular moment of time is usually referred to as Load. The load can vary a
great deal from hour to hour, from day to day and from one part of the year to
another part. For example in the evening , more power is used for lighting and
cooking. On holidays, less power is used by industry and in very hot weather
more power is used for air conditioning. Before installing generators, it is
necessary to know how much electricity is likely to be needed by the user, as in
the following example.
23
In Fig . 1.1 -12 , user is a small town or village. If the maximum predicted load
(or estimated peak demand ) for electrical power by the village is taken as 10
MW, the generating capacity of the power plant must not be less than 10 MW. A
power system with all generating stations and all load areas connected in
parallel may be represented by a theoretical diagram as shown .
Here, the network is shown as "Reservoir " of electrical power with generating
stations "a", "b", "c" and "d" pumping power into the reservoir and load areas
A, B, C, D drain ing power out.
Network Acti on
In Fig. 1.1-13 , the large load area B (20 MW) is fed from station b with four
generators ; while load area C (5MW) is supplied by the single unit in station
"c", "a" producing 15 MW ; with 12 MW going to area A , 1MW to isolated area
E , and 2MW to being exp orted to area B .Note that area B requires 20 MW but
station "b" can produce a maximum of only 18 MW, as two of generating sets
are "off -line").
Power plant "c" (one generator) is also off-line, so plant "d" (four operational
generating sets is simultaneou sly supplying its own area D (23 MW)) plus area C
and area F (5MW + 2MW). At this particular time , there is zero flow in the
transmission line between plants "a" &"c".
24
Power System
The purpose of SEC electrical network is to generate and transfer electricity from the
generation plant to the user. SEC power plants are all connected together by
transmission lines and switchyards. The electrical grids in SEC involve many
generation plants. The grid system must be economical and reliable to eliminate or
reduce the need for additional stand -by generating units. Also, the grid system is more
reliable in satisfying the peak load, which takes place for several hours at particular
times of the day. The grid system allows the power plants to work as a team.
Switching and transmission substations connect the generators of the power plant to
the transmission lines.
25
Fig. 1.1-15 shows how a transmission system is interconnected. G1, G2 and G3 are
power plants that are hundred kilometers apart and 1, 2, 3, 4, 5, 6 and 7 are
interconnected bus bars and Transmission Lines (TL). Each has a circuit breaker (CB)
at both ends. SLs are transmission lines traveling to a load center, called Bulk Supply
Points (BSPs).
26
In BSPs, transmission voltage i s stepped down to suit sub -transmission stage of the
network. Fig. 1.1 -16 shows different stages of SEC-East power system from
generation to customer supply. Voltage levels for transmission within SEC
network are 380 kV, 230 kV, 115 kV and 69 kV. Electric power is generated at a
voltage level of 13.8 kV. A step-up power transformer is used to raise the
generation voltage up to the transmission voltage. To protect the system against
any failure, nearly all circuits are connected to the system through Circuit
Breakers , which are tripped open automatically on fault occurrence. Transmission
of electric power at high voltage reduces the conductor size required for traveling
long distances, the electric power losses and minimizes the voltage drop between
the sendi ng and receiving ends.
27
Switching Stations
Switching stations serve the purpose of sectionalizing the system. There are two
principal reasons for sectionalizing. The first is to disconn ect the system from
faulty or short circuits. Few short circuits are self -clearing. When a circuit or piece
of apparatus becomes defective , it is usually necessary to de -energize it to clear the
trouble. Most of the power circuits are connected to the system through Circuit
Breakers to avoid shutting down the whole system every time there is a short
circuit anywhere so that CBs are tripped open automatically. The second reason for
sectionalizing is to facilitate maintenance or new construction.
28
Distribution Substations
The distribution system is fed through grid substations. They are of a large capacity
and supply power to a large area through many primary feeders. Some are close to the
load but small and control only a few feeders, for example, a single circuit unit
substation. Each primary feeder is supplying several distribution substations. A
distribution substation is shown in Fig. 1.1-17. The distribution substation includes
two types of primary distribution and secondary distribution.
Primary Distribution
Primary distribution takes the power from the grid or 115 kV/13.8 kV distribution
substations to the final step -down operat ions for residential areas.
Secondary Distribution
This is the part of the system through which the power finally reaches a large
number of the customers, except the industries and other large-usage consumers.
29
Secondary distribution feeders are mainly the buried cable (UG) between the LV
panel and the minipillar.
Industrial Customers
Small industrial customers are served directly by the primary feeders or possibly
from the sub -transmission system. Large industrial customers are fed directly from
the sub-transmission system and very large industrial customers may be served
from the transmission system (Fig . 1.1-18).
30
31
32
33
34
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
35
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
36
TASK 1.1-1
POWER SYSTEM SIMULATOR
GENERATION, TRANSMISSION AND DISTRIBUTION
OBJECTIVES
To become familiar with several operational modes of SEC Power System
Simulator:
∑ Loading a Generating Unit
∑ Isolati ng Generating Unit
∑ Loading Transmission Line
∑ Isolating Transmission Line
∑ Energizing Industrial Load
SAFETY PRECAUTIONS
∑ Wear required safety equipment
∑ Keep a safe distance from energized equipment
∑ Follow your trainer's directions .
PROCEDURE
The participant must write down their own task steps according to instructor's
demonstration for their own performance.
37
38
LESSON 1.2
39
40
LESSON 1.2
SEC STANDARDS AND MANUALS
LESSON OVERVIEW
DESCRIPTION
This lesson familiarizes the participants with SEC Standards for Transmission
Material Standards' Specifications (TMSS), Transmission Engineering Specifications
(TES), Transmission Construction Specifications (TCS). Transmission Development
Specifications (TDS), Saudi Electricity Company Engineering Drawings' Standards
(SEEDS), SEC Distribution Material Specifications (SDMS), Design Standards for
Construction of Distribution Systems (SDCS), Customer Service Manual (CSM),
Distribution Safety Manual (DSM), Distribution Operation Manual (DOM),
Distribution Maintenance Manual (DMM), Distribution Planning Standards (DPS),
Craft Certification Manuals (CCMs).
OBJECTIVES
Upon completion of this lesson, the participants should be able to be familiar with:
∑ SEC Standards/Manuals and their Accessibility:
Transmission Material Standards' Specifications (TMSS), Transmission
Engineering Specifications (TES), Transmission Construction Specifications
(TCS). Transmission Development Specifications (TDS), Saudi Electricity
Company Engineering Drawings' Standards (SEEDS), SEC Distribution Material
Specifications (SDMS), Design Standards for Construction of Distribution
Systems (SDCS), Customer Service Manual (CSM), Distribution Safety Manual
(DSM), Distribution Operation Manual (DOM), Distribution Maintenance Manual
(DMM), Distribution Planning Standards (DPS), Craft Certification Manuals
(CCMs).
41
42
INTRODUCTION
It is very important for an engineer to know all the details of SEC standards and
perform his duties appropriately and reasonalbly as required. The engineer should
know the purpose of the distribution and transmission standards and be familiar with
the Accessibility to Standards/Manuals.
A - DISTRIBUTION STANARDS
ϊϳ
ί ϮΘϟ
ΕΎϣΪΧ
ωΎτ ϗ- Ε˯
ήΟϹ
ϭΕΎϔ
λϮϤϟ
Ϟϴϟ
Ω
http://sec2/dist_cust/dist/DistStandard/index.asp
Ε˯
ήΟϹ
ϭΕΎϔ
λϮϤϟ
SDMS ϊϳ
ί ϮΘϟ
ΩϮϣ
ΕΎϔ
λϮϣ
SDCS-1 Δϴ
ϮϬϟ
ΕΎϜΒθϠ
ϟ
ϲΎ
θϧϹ
Ϣϴ
Ϥμ Θϟ
SDCS-2 Δϴ
ο έϷ
ΕΎϜΒθϠ
ϟ
ϲΎ
θϧϹ
Ϣϴ
Ϥμ Θϟ
SDCS-3 ϊϳ
ί ϮΘϟ
ΕΎϜΒηξ ϳ
έ΄Θ
ϟ
ϲΎ
θϧϹ
Ϣϴ
Ϥμ Θϟ
DOM ϊϳ
ί ϮΘϟ
ΕΎϜΒη
ϞϴϐθΗ
Ϟϴϟ
Ω
DMM ϊϳ
ί ϮΘϟ
ΕΎϜΒη
ΔϧΎ
ϴλ
Ϟϴϟ
Ω
DSM ϊϳ
ί ϮΘϟ
ΕΎϜΒη
ϰϠϋ
ϞϤόϠ
ϟ
Δϣϼδϟ
Ϟϴϟ
Ω
DPS ϊϳ
ί ϮΘϟ
ΕΎϜΒης ϴ
τ ΨΗ
Ϟϴϟ
Ω
43
44
356' 0 6 1 0 HW
DO
2 [ LGH
6XUJ H
$ UUHVW
HUV 0 12/1422
Low Voltage Molded Case Circuit Breakers For
376' 0 6 1 1 02/1424
Service Connections
Molded Case Circuit Breakers For Low Voltage
376' 0 6 2 0 01/2006
Distribution Panels 400 Amps
Molded Case Circuit Breakers For Low Voltage
376' 0 6 3 0 01/2006
PMT Cabinet 200 Amps
376' 0 6 4 Interface Low Voltage Main Circuit Breakers 0 02/2006
406' 0 6 1 Bottom Connected Kilo-Watt-Hour Meters 1 12/1423
406' 0 6 2 Electronic Kilo-Watt-Hour Meters 5 02/2007
426' 0 6 1 Fiber Glass Reinforced Polyester Meter Boxes 3 02/2007
436' 0 6 1 MV Shunt Power Capacitor Bank up to 36 kV 0 03/2005
436' 0 6 2 MV Step Voltage Regulators up to 36 kV 0 03/2005
506' 0 6 1 Current Transformers up to 36 kV 0 05/2004
516' 0 6 1 Distribution Transformers up to 36 kV 2 04/2004
566' 0 6 1 8 QLW
6XEVW
DWLRQV
N9
˺˼̄́ kV 1 04/2004
566' 0 6 2 3DFNDJ H
6XEVW
DWLRQV
N9
˺˼̄́ kV 1 04/2004
The (SDCS-01) standard specifies the design, materials and installation practices to be
applied in the construction of MV and LV single and double circuit lines of overhead
distribution system with the use of octagonal steel poles as line supports. It is intended
to assist the engineers and field personnel to achieve standardization in construction
and to ensure a satisfactory and economical level of service without operating
restrictions so that the operational errors should be minimal for safety and reliability.
45
http://sec2/dist_cust/dist/DistStandard/SDCS2/index.htm
NUMBER ,7 ( 0
' ( 6&5 , 3 7 , 2 1 REV DATE
The (SDCS-02 – PART-1) construction standard s pecifies the design and installation
practices to be applied in the construction of MV and LV cable of underground
distribution system.
The (SDCS-02 – PART-2) construction standard specifies the design of meter room
and method of installation of KWH meters inside the meter rooms and building insets.
http://sec2/dist_cust/DistStandard/SDC3/index.htm
NUMBER 1 ,7( 0
' ( 6&5 , 3 7 , 2 REV DATE
PART 1 Underground Network Grounding 0 05/2005
PART 2 Overhead Network Grounding 0 05/2005
46
' 20
&2 ' ( ,7( 0
' ( 6&5 , 3 7 , 2 1 REV. DATE
DOM- 01- 01 Preparation of Distribution Operation Manual 0 04/2004
DOM- 01- 02 Lock And Locking Arrangement 0 04/2004
DOM- 01- 03 Operation between Control Center 0 12/2004
DOM- 01-04 Hold Tags 0 12/2004
DOM- 01- 05 Inspection Of VIP Customer Generators 0 12/2004
DOM- 01- 06 Operation Accident Error Investigation 0 05/2005
DOM- 01- 07 Work Permits 0 Not Yet
DOM- 01- 08 Load Readings 0 03/2006
DOM- 02- 01 Operation Of Switchgears 0 05/2005
DOM- 02- 02 Operation Of Package Substations 0 05/2005
The (DOM- 01- 01) Standard describes the guidelines for the preparation of
Distribution Operations' Manuals (DOM). The primary purpose of DOM is to provide
precise and adequate information to the engineer engaged in the operation of
distribution equipment and network. DOM will ensure that Operation of distribution
equipment and lines is carried out in accordance with international standards and
practices in consideration with cost effectiveness, safety and reliability.
47
The (DOM- 01- 04) Standard describes the guidelines for distribution power lines and
associated equipment below 69 kV and pro vide tagging and locking procedure s to be
implemented before issuing Electrical Work Permits. The purpose of this is to
safeguard persons and property from hazards arising in construction, Operation or
Maintenance Activities.
48
The (DMM-03-04) provides precise and adequate information on the pole numbering
system of MV O/H distribution feeders (34 .5 kV and below ).
49
NUMBER ,7( 0
' ( 6&5 , 3 7 , 2 1 REV. DATE
01- 01 Δϴ
ϮϬϟ
ϊϳί ϮΘϟ
ΕΎϜΒηϲϓ
ι ϮϠ
Ψϟ
Ϟϴ
ϟΩ 0 12/2004
01- 02 Δϳ
ΪϠΠϟ
ϡΎϤϛϷ
ϭΕί Ύ
ϔϘ
ϟ
Ϟϴ
ϟΩ 0 2004
01- 03 Ι Ω
ϮΤϟ
ϰϠ
ϋΓήτ ϴ
δϠϟ
Δϴ
δϴ
ήϟ
Δτ Ψϟ
0 2005
06-00 Δϴ
Ύ
θϧϹ
ΕϻϭΎ
ϘϤϠ
ϟ
Δϣϼδϟ
ΞϣΎ
ϧήΑ 0 5/12/2005
02-00 Δϴ
μ Ψθϟ
ΔϳΎ
ϤΤϟ
ΕΪόϣ
Ϟϴϟ
Ω 0 12/12/2005
02-20 Δϣϼδϟ
Δϳ
άΣ
Ϟϴ
ϟΩ 0 12/12/2005
8- DISTRIBUTION PLANNING STANDARD (DPS)
The “Distribution Planning Standard” provides a guideline to the Planning Engineers
in the Saudi Electricity Company for the Planning of Distribution Network.
TABLE OF CONTENTS
1. DISTRIBUTION PLANNING CRITERIA
1.1 Introduction 1.7 Power Factor
1.2 Definitions 1.8 Voltage Fluctuation
1.3 General Principles 1.9 Standard Distribution Voltage
1.4 Frequency 1.10 Voltage Drop
1.5 Harmonics 1.11 Voltage Regulation
1.6 Phase Unbalance 1.12 Standard Loading Conditions
50
51
B-TRANSMISSION STANDARDS
http:// e-dhq-webapp2/Tp- Reports/standards/ index/tssd_home.aspx
52
53
54
Standard (TES-P-104-3) covers the selection of a specific type and size of power
cable based on particular applications and conditions in the system of Saudi Electricity
Company (SEC), Transmission Network .
Standard (TES-P-104-4) has been prepared as a guide for the splicing & termination
of insulated cables with copper or aluminum conductor that will be used for 110, 115,
132, 230 and 380 kV underground cable circuits in the system of Saudi Electricity
Company (SEC), Transmission Network .
The purpose of the "Substation Design Standards" (TES-P-119) is to clearly define the
design philosophy and practices to enable the design engineer to develop cost effective
designs of SEC substations. This standard covers the primary transmission within the
voltage range of 110 kV to 380 kV.
55
ϝϮμ ϔ
ϟ
ΕΎϳ
ϮΘΤϣ
ϝϭϷ
Ϟμ ϔ
ϟ Δϴ
Ύ
ΑήϬϜϟ
ΔϣΪΨϟ
ϢϳΪϘ
Η
ΔϤψϧ
ϷΔϣΎ
όϟ
ΕΎγΎϴδϟ
˺˺ ϝΎ
μϳ Ϲ
ς Α
Ϯο
˺˻ Δϳ
άϐΘϟ
ΩϮϬΟ
˺˼
ϡΪΨΘγϻ ωϮϧ
ΐ δΣ ϦϴϛήΘ θϤϟ
ϒϴ ϨμΗ
˺˽
ΪΣϮϟ
ΐ Ϡτϟ ΪϳΪΤΗ β γ
ϲϧ
ΎΜ
ϟ
Ϟμ ϔ
ϟ ϢΪϟ
Δϴ ΎΑήϬϜϟ
ΔϣΪΨϟ
ϝΎ μϳ ·ΕΎΒϠσΓ
˻˺ Δϴ Ύ
ΑήϬϜϟΔϣΪΨϟ ϝΎ μϳ ·ϞΣ ήϣ
˻˻ Δϓ Ύο Ϲ ΕΎΒϠσ
˻˼ Δϳ ϮϘΘϟΕΎΒϠ
σ
˻˽ Δ ΰΠΘϟ ΕΎΒϠσ
˻˾ ϊϴ ϤΠΘϟ ΕΎΒϠσ
˻˿ Ω
ΪϋϥϭΪΑ ΔϜΒθϟ
ϦϣΓήηΎΒϣ
Γήϴϐμ ϟ
ϝΎ ϤΣϸϟ Δϴ
ΎΑήϬϜϟ ΔϣΪΨϟ
ϝΎ μϳ ·
˻̀ ϝϮΠϟΝ
ήΑϭ
ΔϴϧϼϋϹΕΎΣϮϠ ϟΔϴΎΑήϬϜϟ
ΔϣΪΨϟ ϝΎ μϳ ·ΕΎΒϠσ
˻́ ˯ΎΑήϬϜϠϟ
Δϳ
ΩϮόδϟ
Δϛήθϟ
ϖϓ
ήϤϟ
Δϴ ΎΑήϬϜϟ
ΔϣΪΨϟ
ϝΎ μϳ ·ΕΎΒϠσ
˻̂ ΐ Ϡ σήϴ ϴϐΗΪϬΟ
˻˺˹
ΓέΪϘϟ
βϔ ϨΑ
Ω Ϊϋήϴ ϴϐΗΐ Ϡσ
Κϟ
ΎΜϟ
Ϟμ ϔ
ϟ ΔΘϗΆϤϟ
ΔϴΎΑήϬϜϟ
ΔϣΪΨϟ ϝΎ μϳ ·ΕΎΒϠσ
˼˺ ˯ΎθϧϹ
ν ήϏϷ ΔΘϗ ΆϤϟ
Δϴ
Ύ ΑήϬϜϟ ΔϣΪΨϟ ϝΎμϳ ·
˼˻ ΕΎΒγΎϨϤϠϟ
ΔΘϗ ΆϤϟ
Δϴ
Ύ ΑήϬϜϟ ΔϣΪΨϟ ϝΎμϳ ·
56
ϊ Α
ήϟ
Ϟμ ϔϟ
ΕΩ Ϊόϟ
˽˺ ΕΩ Ϊόϟ ϭΕΪΣϮϟ ΩΪϋΪϳ ΪΤΗ
˽˻ ΕΩ Ϊόϟΐ ϴ ϛήΗ ϊϗ Ϯϣ
˽˼ Ύ
ϬΗ˯ήΟ· ϞϤϜΘ δΗϢϟ ϭ ΔΒϛήϣ ΕΩ Ϊϋϊϣ ϞϣΎ όΘ ϟΔϴϔϴϛ
˽˽ ϞϴΠδΘϟ
Ϧϋ Δϔ ϗϮΘϤϟ ΕΩ Ϊόϟ
ϊ ϣ ϞϣΎ όΘ ϟΔϴϔϴϛ
˽˾ ϢϴϣήΘ ϟ
ϭ ϡΪϬϟ
ΐ ΒδΑ ΩΪόϟ Δϟί·
˽˿ ΓΩϮϘ ϔ ϤϟΕΩ Ϊόϟ
ϊ ϣϞϣΎ όΘ ϟΔϴϔϴϛ
˽̀ Δϴ
γΎ ϴ
ϗήϴϐϟ
ϊ σ ϮϘϟϭΔϠτ όΘϤϟ ϊ σ ϮϘ ϟ
ϝ ΪΒΘγ
ϊ ϣ ϞϣΎ όΘ ϟΔϴϔϴϛ
β ϣΎ Ψϟ
Ϟμ ϔ
ϟ ΔϴΎΑήϬϜϟ ΔϣΪΨϟ ΓΩΎϋ·ϭ Ϟμ ϓ
˾˺ ΪϳΪδΘϟ
ϡΪϋΐ ΒδΑ Δϴ ΎΑήϬϜϟ ΔϣΪΨϟ ΓΩΎ ϋ·ϭ Ϟμ ϓ
˾˻ ϙήΘ θϤϟ
ΐ Ϡ σ ϰϠ ϋ ˯Ύ
˱ ϨΑ
Δϴ ΎΑήϬϜϟ ΔϣΪΨϟ
Ϟμ ϓ
˾˼ Δϴ
Ϥγήϟ ΕΎϬΠϟ ΐ ϠσϰϠ ϋ ˯Ύ
˱ ϨΑΎ ϬΗΩΎ ϋ·ϭ ΔϴΎΑήϬϜϟ ΔϣΪΨϟ
Ϟμ ϓ
˾˽ ΔϴΎ
ΑήϬϜϟ ΕΪϳ ΪϤΘϟ˯Ϯγ ΐ ΒδΑ Δϴ ΎΑήϬϜϟ ΔϣΪΨϟ
Ϟμ ϓ
˾˾ ϝΎϤΣϷ ΓΩΎ ϳί ΐ ΒδΑ Δϴ ΎΑήϬϜϟ ΔϣΪΨϟ
Ϟμ ϓ
˾˿ ΩΪόϟΓ˯ήϗ Ϧϣ ϦϜϤΘϟ ϡΪόϟ
Δϴ ΎΑήϬϜϟ ΔϣΪΨϟ
Ϟμ ϓ
˾̀
ϖϓ ήϤϟΔϳΎϤΣ ϡΎψϧ ΔϔϟΎΨϣ ΐ ΒδΑ ΔϴΎΑήϬϜϟ ΔϣΪΨϟ Ϟμ ϓ
˾́ ϙϼϬΘγ ϻήϴΗ
Ϯϓ
ήϴ Ϗ ΕΎϘ ΤΘ δϣ ΩϮΟϭ ΐ ΒδΑ Δϴ ΎΑήϬϜϟ ΔϣΪΨϟ
Ϟμ ϓ
˾̂ ϙϼϬΘγ ϞΠδΗ ϻ ϲΘϟ
ΕΩ Ϊόϟ Ϧϋ Δϴ ΎΑήϬϜϟ ΔϣΪΨϟ
Ϟμ ϓ
˾˺˹ Δϛήθϟ
ΕΪόϣ ϝϼϐΘγ ΐ ΒδΑ Δϴ ΎΑήϬϜϟ ΔϣΪΨϟ
Ϟμ ϓ
˾˺˺ ϙήΘθϤϟϞΒϗϦϣ ΔϣΪΨϟ ΓΩΎϋ· έήϜΗ ΐ ΒδΑ ΔϴΎΑήϬϜϟ ΔϣΪΨϟ Ϟμ ϓ
˾˺˻
Ϊϴϔ
ΘδϤϟ
ΐ ϠσϰϠ ϋ˯Ύ
˱ ϨΑς γ ϮΘϤϟς ϐπ ϟ ΕΎϜΒθϟ ΔϴΎΑήϬϜϟ ΔϣΪΨϟ
Ϟμ ϓ
α ΩΎ δϟ
Ϟμ ϔ
ϟ Δϔ ϳήόΘ ϟ
˿˺ ΔϴΎ ΑήϬϜϟ ΔϗΎτϟ
ϊϴ ΑέΎ όγ ΔϔϳήόΗ
˿˻ ΓέϮΗΎ ϔϟ
Ω Ϊϋ·ϭ ΩΪόϟΔϧ Ύϴ
λ ϭ Γ˯ήϗ ΔϔϳήόΗ
˿˼ ΓΪϳ ΪΠϟ ΕΎΒϠ τϠ ϟ
ϝΎ μϳ Ϲ Δϔ ϳ
ήόΗ
˿˽ ϊϴϤΠΘϟ
ϭ ΔΰΠΘϟ ϭΔϳϮϘ Θϟϭ ΔϓΎο Ϲ ΕΎΒϠσ ϝΎ μϳ ·Δϔ ϳήόΗ
˿˾ ΩΪϋϥϭΪΑ Γήϴ ϐμ ϟ
ϝΎ ϤΣϸϟ Δϴ ΎΑήϬϜϟ ΔϣΪΨϟ ϝΎ μϳ · ΔϔϳήόΗ
˿˿ Ϧϴ ϣ΄Θϟ ϡϮγέ
˿̀ Ϧϴ
ϣ΄Θϟ
ϡϮγ έϭΔϔ
ϳήόΘϟ
ΔϤϴϗ
Ϟϴμ ΤΗ
˿́
ϦϴϛήΘ
θϤϟϦϣΔΑϮϠ
τ Ϥϟ
ΔϴϠ
όϔϟ
ϒϴ ϟ
ΎϜΘϟ
˿̂
ϯήΧ
ϡϮγέ
˿˺˹ ϦϴϛήΘθϤϠϟ
ώϟΎ
ΒϤϟ
ΓΩΎϋ·
˿˺˺
ϙϼϬΘγϻ
Δϔϳ
ήόΘϟ
ϲΨϳέΎΘϟ
ϞΠδϟ
ϊ ΑΎ
δϟ
Ϟ˰
μϔϟ
ΔϣΎ
όϟ
ϖϓήϤϟ
ΔϳΎϤΣ
̀ ˺ ΔϛήθϟΕΎϜϠΘϤϣϑϼΗ ·
Ι ΩϮΣ
̀ ˻
ΕΩ
Ϊόϟ
ΎΑΔϘϠόΘ
Ϥϟ
ΕΎ ϣήϐϟ
ϭ ΕΎϔϟΎΨϤϟ
ϦϣΎ
Μ ϟ
Ϟμ ϔ
ϟ ήϴΗϮϔϟ
Ϟϴμ ΤΗϭέΪλ ·ϭ Γ˯ήϗ
́ ˺ ΕΩΪόϟ
Γ˯ ήϗ
́ ˻
ήϴΗ
Ϯϔϟ
ϊϳί ϮΗϭέΪλ ·
́ ˼
ϙϼϬΘ γ ϻ
ΏΎ δΣ Δϴϔϴϛ
57
́ ˽
ϙϼϬΘ γ ϻ ήϴΗ ϮϓώϟΎΒϣϞϴμ ΤΗ
́ ˾ ήϴΗϮϔϟ
Ϟμ ϓϭ ϊϴ ϤΠΗ
́ ˿ ϙϼϬΘγ ϻ
ήϴΗϮϓ ΔϤϴ ϗϞϴμ ΤΗ ϞϴΟ΄Η
́ ̀
Γ˯ήϘϟ
˯ΎτΧ ΔΠϴ Θϧ ήϴ Η
Ϯϔϟ
ϴΤμ Η
́ ́ ΓέϮΗΎϔϟϲϓ Ϛϟ Ύ
ϤϟϢγ
ήϴϴ ϐΗ
́ ̂ Δϴϋήϔϟ Ε ΩΪόϟ
Γ˯ ήϗϡΎψϧ
́ ˺˹
ϙϼϬΘγϻήϴ
Η
ϮϔΑ
Δλ Ύ
Ψϟ
ϦϴϛήΘθϤϟ
ϱϭΎ Ϝη ϊ ϣϞϣΎ όΘ
ϟΔϴϔϴϛ
ϊγΎΘ ϟ
Ϟμ ϔ
ϟ Δϴ
Ϩϔ
ϟ
˯Ύ
τ ΧϷ
ϭϝΎ
τ ϋϷ
ΔΠϴΘϧ
Ϧϴ
ϛήΘθϤϟ
ήϴΗϮϓ
ΕΎϳ ϮδΗϭ ΕΩ Ϊόϟ
κ Τϓ
̂˺ Ύ
ϬΘϣϼγ Ϧϣ Ϊϛ΄ΘϠϟΕΩ Ϊόϟ
κ Τϓ
̂˻ ϙήΘθϤϟ
ΐ Ϡ σϰϠϋ˯Ύ ϨΑΕΩ Ϊόϟ
κ Τϓ
ήηΎ
όϟ
Ϟμ ϔ
ϟ ΕΪόϤ ϟ
ϭΕΩ ΪόϟϞϘϧ
˺˹˺
ΕΪόϤϟ
ΕΩ ΪόϟϞϘϧβ γ
58
The On-the-Job Training Manual, Volume II, contains general information and the
technical training requirements for the On -the-Job Training Program. It is intended to
guide the training and qualification of OJT trainees for craft certification in Grade
Code 45-2 status. It is also the source for the contents of a personal On-the-Job
Training Manual to be issued to each trainee. This personal training manual for the
trainee should contain the following items:
59
The Technical Career Development Manual, Volume III, contains general information
and the technical training requirements for craft certification in Grade Codes 46
through 48. It is intended as a guide for the training and qualification of craft
employees. It is also the source for the contents of a personal Technical Career
Development Manual issued to each trainee.
ADMINISTRATIVE GUIDELINES-I
1. INTRODUCTION TO THE CRAFT CERTIFICATION MANUAL
The Craft Certificat ion Manual documents the SEC-EOA Craft Certification
System. The Craft Certification System ensures that technicians are:
∑ Qualified
∑ Certified
This Craft Certification Manual will be used by the Operational Organizations and by
Training and Education Department (TED) personnel involved in the qualification and
certification of technicians. Specifically, Telecommunications Division
Superintendents, Assistant Division Superintendents, Supervisors/Foremen,
designated Craftsman Trainers and Craft Evaluators, OJT Analysts, Senior
Training Coordinator, Division Training Coordinator and the technicians all have a
role in the process and will use this manual.
60
This manual describes two programs. The first is the On-the-Job Training Program
(OJTP) for Grade Code 45- 02 Status trainees engaged in full -time training. This is a
full-time mentor program, which means, that the trainee is in close contact with his
mentor (Qualified Technician Trainer) for three (3) years. The goal is to compl et e
al l trai ni ng and to qual ify on al l tasks per formed b y Tel ecommuni cat ions
Operations/Maintenance Technician IV (GC 45). The trainee accomplishes task
qualification and certification in the workplace. The On-the-Job Training Program for
Telecommunications Operations/ Maintenance Technician is administered by the
Telecommunications Division in direct association with the SEC-EOA Central
Training Institute (TED), Job Skills Training Division (JSTD) and On-the-Job
Training Administration Unit (OJTAU).
Vo lu me I: Administrative Guidelines
This describes the Craft Certification System purpose and benefits and how the system
61
62
ADMINISTRATIVE GUIDELINES-II
This Craft Certification System consists of two distinct but related programs. The first
is the On-the-Job Training Program. This is a full-time mentor program, which means
63
that the trainee is in close con tact with his mentor ( Qualified Craftsman Trainer). The
goal is to complete training and become certified to perform Telecommunications
Technician IV job tasks. Trainees at GC 45-2 status must satisfactorily complete the
OJT assignment tasks and TQCs relev ant to GC 45-1 Duties in Volume II, Appendix-
B/C to be eligible for job certification. The Program is administered by the
Information Technology and Communications (IT&C) in association with the SEC-
EOA Central Training Institute (SECTI), Job Skills Traini ng Division (JSTD) and On-
the-Job Training Administration Unit (OJTAU).
The second program is the Technical Career Development Program (TCDP), which is
for employees in grade codes 46, 47 and 48, who will be trained part time On-the-Job
in conjunction with regular work assignments. As shown in Table 1, the Career
Progression and Training Matrix, lists the standard Career Progression, Training, and
Certification requirements applicable to this program.
64
A task is a distinct work activity that produces a complete work product or service.
Keep in mind that each duty will consist of one or more tasks and, in turn, each t ask
will require the performance of several task steps.
A Task Qualification Card (TQC) has been developed for each job task contained in a
Duty and Task List produced as a result of the job analysis. A TQC describes the
individual steps for performing the task and the standards to which it must be
performed. In the Craft Certification System, the trainees must qualify on each task
covered by a TQC.
This Craft Certification System consists of two distinct but related programs. The first
is the On-the-Job Training Program. This is a full -time mentor program, which means
that the trainee is in close contact with his mentor ( Qualified Craftsman Trainer). The
goal is to complete training and become certified to perform Telecommunications
65
The second program is the Technical Career Development Program, which is for
employees in grade codes 46, 47 and 48, who will be trained part time On-the-Job in
conjunction with regular work assignments. As shown in Table 1, the Career
Progression and Training Matrix, lists the standard Career Progression, Training, and
Certification requirements applicable to this program.
The Volume III of the Craft Certification Manual is organized in Appendices A-F,
providing Telecommunications Area specific information and data to support training
in Telecommunications Operations/Maintenance Technician jobs, as follows:
66
67
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
68
LESSON 1.3
69
70
LESSON 1.3
GENERATIORS AND EXCITATION SYSTEM
LESSON OVERVIEW
DESCRIPTION
Lesson 1.3 on generators and Excitation System includes Stator, Rotor, Bearings,
Lubrication System, Thermocouples, Seal Oil System, Main Leads, Current
Transformers, Neutral Grounding Transformer and Resistor-Temperature Detectors
(RTD), Generator Frame, Generator Cooling, Hydrogen Blower and Cooler,
Hydrogen Gas System, Gland Seals System. The Excitation System is discussed
covering Brush and Slip Ring Excitation, Brushless Excitation with Parallel Operation
of Generators.
The lesson concludes with Preventive Maintenance.
OBJECTIVES
71
72
INTRODUCTION
AC generators (Alternators)are the productionpoints of electricalenergy with nominal
frequency and voltage. Alternators are driven by turbines (SteamGas),
or as shown in Fig.
1.3-1.
73
THEORY OF OPERATION
frequency (f) that depends on speed of rotation (n) and number of poles (p) of the
Alternator.
74
pn
f= Hz
120
Where: N = Speed of rotatio f = Cycle per second (Hertz)
p = Total number of magnetic poles
A three-phase Generator has three separate but identical armature windings that are
acted on by one system of rotating magnets. Each winding, called a phase, consists of
a set of armature coils.
GENERATOR COMPONENTS
STATOR
All synchronous generators have the same type of stator winding. This is wound in the
slots of the laminated core, as shown in Fig. 1.3-4. The stator is supported on flexible
mountings within the frame.
75
ROTOR
The construction of the rotor depends on the speed of the prime mover (Steam or Gas
Turbine) and the frequency and rated power of the Generator.
The rotor is supported on bearings installed in bearing brackets installed at each end of
the Generator Frame.
76
77
GENERATOR FRAME
The Generator frame is fitted with gland seal assemblies around the rotor where it
penetrates the frame. These seals enable the frame to
provide a gas tight enclosure around the
stator and rotor. The enclosure needs to be gas tight because modern Turbine generators
usually have some form of internal Hydrogencooling system,as shown in Fig. 1.3-7.
78
BEARINGS
The bearings are electrically insulated from the frame in order to prevent any stray
currents from the rotor sparking between the journal and the bearing surfaces. This type
of sparking, called arcing, could damage thebearing surfaces.
The lubrication oil system keeps the bearings of the turbine, Generator and exciter
supplied with lubricating oil (lube -oil). The system also provides oil for other moving
parts. The main oil pump is on the rotor shaft. The main oil pump circulates the
lubricating oil throughout the turbine system.
THERMOCOUPLE
79
CURRENT TRANSFORMERS
80
GENERATOR COOLING
Small generators usually below 30 Mega-Watts are cooled by circulating air through
the rotor and stator.Units that are rated between 30 and 200 Mega-Watts are cooled by
circulating Hydrogen between the rotor and stator. This type of cooling is called
Conventional Hydrogen Cooling. Units larger than 200 Mega-Watts are cooled by
circulating Hydrogen through hollow passages inside the stator coils.This is called Inner-
Cooling.
81
The windings inside the stator and on the rotor shaft develop a lot of heat as electric
current flows through them. The heat can damage the rotor windings or the stator
stacks. To prevent heat damages, a co oling medium circulates through the stator. This
keeps the temperature from getting too high. In the stator, the cooling medium is
Hydrogen gas. To remove heat from the components inside the Generator; the
Hydrogen is circulated around the hot components. Fig. 1.3-12(a) shows the flow path
of Hydrogen inside the Generator casing with four Hydrogen coolers with Oil seals
sealing each end of the rotor, two circulating fans and the stator. The arrows in the
illustration indicate the direction of the Hydrogen flow. The fans at each end of the
rotor blow the Hydrogen around the hot components. The heat absorbed by the
Hydrogen is then removed by cooling water flowing through the coolers.
Hydrogen gas coolers (Heat Exchangers) control the temperature of the circulating
Hydrogen. Hydrogen is cooled by water that passes through the finned tubes in the
coolers. In each section, the cooling water enters the inlet water chamber, flows
through the finned tubes in the cooler, changes direction in the return-water chamber at
the top and then leaves the cooler at the bottom. Hydrogen is passed through the cooler
by the blower.
82
Generator cooling is needed to remove the heat energy produced by the large currents
flowing through the conductors. This includes the direct current flowing though the
rotor windings as well as the alternating current being induced in the stator coils.
83
∑ The way to overcome this disadvantage is to avoid mixing the Hydrogen and air
together.
∑ Before any Hydrogen is pumped into thegenerator, the air is removed first bypurging
carbon dioxide.
∑ Carbon dioxide is non reactive gas that can be safely mixed with air in any
combination.
∑ The carbon dioxide is pumped into the bottom of the Generator. As it fills the
Generator frame, it pushes the air to the top. This air is removed by a piping
arrangement that vents the air to the atmosphere outside the building
.
∑ During operation, Hydrogen is kept from mixing with outside air by the glandseal or
seal oil system.
84
∑ The Hydrogen gas system controls the safe handling of the Hydrogen that is used to cool
the Generator. It also provides a means of monitoring and maintaining the Hydrogen
condition during operation,
as shown in Fig. 1.3-15.
∑ The system functions include filling and emptying the Generator cavities, as already
described;maintainingand indicating the pressure, density
and purity ofthe Hydrogen
within the Generator; indi cating the presence of liquid in the Generator and finally
drying the Hydrogen and removing water vapor from theGenerator.
85
∑ The seals are located around the rotor shaft where it penetrates the Generator bearing
brackets.These oil type gland seals are mounted inside the Generator inboard of the
rotor bearings.
∑ The function of the seal oil sy
stem is to supplyoil to these gland seals, both to operate
the seals and to lubricate them.
∑ The system is comprised of the gland seal assemblieswith their associated oil unit
located on the floor beneath the
generator, as shown inFig. 1.3-17.
86
EXCITATION SYSTEMS
EXCITER
∑ The excitationsystem also regulatesthe output of the main Generator bycontrolling the
amount of Direct Current supplied to the field windings.
∑ The rotor is made into an electromagnetby Direct Current flowing through the field
windings. The strength of the rotor'
s flux field depends on the amount of Direct Current in
the field windings. This in turn regulates the level of electrical output from the main
Generator.
87
88
89
One of the principle advantages of this system is that many of the major components
(main exciter armature windings and rectifier wheel) are mounted on the same exciter
rotor shaft, as shown inFig. 1.3-22.
90
This entire rotating assembly is supported at two locations on a journal areabetween the
circulating blower and the armature windings and by the couplingwhere it attaches to the
Generator rotor.
The voltage regulator performs two functions. First it electronically rectifies the
Alternating Current to Direct Current and secondly, it controls the amount of Direct
Current delivered to the exciter's stationary field. From the armature coils, Alternating
Current flows to the rectifier wheel on the exciter rotor , as shown Fig. 1.3-23.
The rectifier wheel changes the Alternating Current electricity to Direct Current
electricity. This actually happens in an arrangement of diode assemblies that are installed
inside the wheel. Thus the arrangement of diode assemblies in the rectifier wheel
maintains a Direct Current that flows from the axial leads in the exciter's rotor shaft through
the coupling connection to the axial leads into the main Generator'
s rotor shaft, as shown in
Fig. 1.3-24.
91
1. Permanent magnet pilot exciter provides power to the voltage regulator, which
controls the stationary field of the AC exciter.
2. The output from the rotating armature of the AC exciter is fed along the shaft to
silicon diodes mounted in the wheel on the shaft.
3. The wheel serves as the mounting for both the diodes and fuse.
the The output of the
AC exciter is rectified by the silicon diodes, the resultant Direct Current being
carried along the shaft to the rotating field to th
e AC Generator.
4. The rotating components are solidly connected together with no external leads
between the exciter and the Generator field.
92
93
The terminal voltage of the Generator is measured with a voltmeter and adjusted by varying
the excitation current until it is entical
id with the network voltage. The frequency is adjusted
by altering the speed of rotation of the Generator. A double frequencymeter {Synchro -
scope), as shown inFig. 1.3-27, with separate instruments for network and Generator can be
used to compare the frequencies.The phase sequence is checked with the aid of a phase -
sequence indicator. The sequence can be alteredchanging
by terminal connections.
After the Generatorhas been connectedin parallel,the loads are distributed. The excitation
current of the Generator and the power output of the prime mover are adjusted. If the power
input to the synchronousGeneratoris increasedafter it has been brought on line, it delivers
active power to the energy supply network. The rotor
then leads the rotating field set up in the
stator under load bythe load angle, which increases with the rise in non
-reactive load output
.
94
The active power delivered by the synchronous Generator is controlled by altering the
driving power input to the Ge
nerator. A change in the excitation current results in a change in
the reactiveload output. If the excitationcurrent is increasedafter the Generatorhas been
brought on line, the Generator contributesinductive reactive power to the energy supply
network. If the excitation current is reduced, it withdraws inductive reactive power from the
network. The amount and type of reactivepower deliveredby a synchronousGeneratoris
governed bythe excitation current
. To prevent the rotor speed fluctuating sharpl
y in response
to sudden changes in load, synchronous generators often have a damping winding
constructed like the squirrel cage winding in a squirrel
cage motor.
PREVENTIVE MAINTENANCE
Preventivemaintenanceaims to increasethe reliabilityand extend the lifetime ofgenerators
by providingappropriateservicingat the right time. It consists of annual system inspections
and component replacementsbased on a Generator-specific maintenance schedule. The
formation of defects in large synchronous machinesnormally
is a long process, so systematic
preventive maintenance can prevent unplanned shutdowns.
BENEFITS
COMPREHENSIVE MAINTENANCE
Preventivemaintenance includes the labor and parts needed to perform on -site work as
specified bythe maintenance schedule, as follows:
95
Once the maintenancework has been completed and the inspectiondata fully analyzed,a
detailedservicereport is provided. This includes recommendations for service actions (such
as “excitationsystem requires upgrading”),and for spare parts and special tools for future
actions. On-site training can be undertaken with maintenance work
.
The effectivenessof the preventive maintenance work depends on the quality of the
information provided by
the system manufacturer.
IN SERVICE REPORTS
96
MAINTENANCE SCHEDULE
Experienceindicatesthat generators become more likely to fail after a number of years in
operation.In the case of synchronous generatorsthis typicallyoccurs after 5-10 years. The
main reason is ageing of the components,but operatingconditionsalso play a major role.
Failure of a component may result in damage to other parts of the machine, includingthe
stator and rotor. The maintenance schedules, as shownTable
in 1.3-1 are based on extensive
know-how providing an effectiveand systematicmeans of maintaininga specific type of
Generator.The maintenanceintervalsare planned accordingto those of the diesel engine to
avoid unnecessary shutdown time. The maintenance sch edules comply with any
specificationsissued by the component suppliers.Environmentaland operatingconditions
are also taken into account. Tough conditions, such as high ambient temperatures,high
vibrationlevels, humidity, dirt, or heavy loads can sign ificantlyshorten component lifetime
and more frequent maintenanceand component replacementintervals.In order to ensure
optimum performanceover the entire lifetime of a generator, it is recommended that
annual inspections are carried out in addition t o regular maintenance.
97
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
98
TASK 1.3-1
OBJECTIVES
1. Write the steps required to operate two 3 phase AC generators in parallel and study
the loading effect on system frequency.
PROCEDURE
If the difference is big and the synchronization device indication rotates at fast
speed press the excitation winding control switch for motor to upper si de to control
its speed (control frequency value) and at the same time press the excitation to
raise the voltage reading until it reach 600 Volts and the frequency reading 60 Hz
so that the output voltages for the two generators are equal.
99
3. Connect the Bus-Tie switch when the synchroscop e pointer is at or very close
to12 o'clock position.
4. Connect some different loads to feed them via generator no.1 and generator
no.3. Supervise the frequency and voltage readings for the two generators.
Readjust the voltage and frequency reading to reach 600 volt and 60 Hertz
again, if needed.
5. Disconnect the loads . Then stop and disconnect the two generators safely.
V V V A
1 -RUN / START Control Switch
F A V A 2 -DC Motor -3 / 125 V Supply Switch 's
10
3 -Gen -3 Excitation Isolator Switch
KW V A 4 -DC Motor -3 Raise / Lower Excitation
Control Switch
5 -Gen -3 Raise / Lower Excitation
Control Switch
51
7 8
6
51
5 4
9
51
1
3 2 G-3
32
100
UNIT-2
101
102
UNIT-2
MOTORS AND POWER TRANSFORMERS
UNIT OVERVIEW
DESCRIPTION
OBJECTIVES
103
104
LESSON 2.1
105
106
LESSON 2.1
TYPES OF MOTORS, PROTECTION AND CONTROL
LESSON OVERVIEW
DESCRIPTION
This lesson discusses Types of Motors, Protection and Control and concludes with
Preventive Maintenance.
OBJECTIVES
107
108
DC MOTORS
Motors (AC & DC) are as important component s in a Power System as in industry . A
power plant of generating capacity of 1600 MW utilizes an approximate total of
10,000 motors for reliable operation of the plant; AC & DC motors, drive pumps,
fans, control valves etc. In all power plants, there are many auxiliary types of
equipment such as pumps, compressors and fans. These auxiliaries are driven by
electric motors (AC/DC). The auxiliaries driven by the DC motors are generally used
for standby functions. There are many motors at the plant that get thei r power from a
DC source such as, Emergency oil pump, seal oil pump, turning gear motor and so on.
TYPES OF DC MOTORS
There are three basic types of DC motors
, as shown in Fig. 2.1-2.
109
All of these motors are identical in construction, but they are different inthe methods of
connection and the way field current and armature currents are changed, either by
change in mechanical load (Torque) or by controller external to the motor.
SERIES MOTORS
OPERATING CHARACTERI
STICS
As shown in Fig. 2.1-3(b), we can deduce series motor
load characteristics as follow:
∑ Series motor speed can be controlledby varyingthe Fig. 2.1-3(b) Series Motor
armaturevoltage or field current. Load characteristics
110
APPLICATIONS
SHUNT MOTOR
By designing a field winding with many turns, a small current can set up a strong
magnetic field. Therefore, the resistance of the field windings is relatively high and is
connected directly across the line voltage for which motor is designed. Field windings
are only necessary to produce flux in an electromagnetic circuit. The windings would not
be necessary if the poles are made of permanent magnetic materials. Such materials
would not b e practical since the flux could not be changed and one of the advantages of
DC motor speed control would be lost.
APPLICATIONS
111
COMPOUND MOTOR
OPERATING CHARACTERI
STICS
∑ Predominantly
, series or shunt characteristic Fig. 2.1-5 Compound Motor
depending on compounding
APPLICATIONS
∑ Driving fly
wheel masses (Presses, stamping plants, shearing plants)
DC MOTOR STARTING
The difficulty with this arrangement is in starting the motor. The low armature resistance
causes a very high starting current if the armature winding is directly across the line.
The starting current must be limited by connecting a starter resistance. After the motor
has accelerated to its rated speed, counter emf (cemf)
oppose starting current and reduce to
acceptable limit.
Any break in the field circuit will cause the cemf to go nearly to zero,
resultingin the same
inrush of current as if the starter resistance were not used when starting. This is a very
dangerous situation that will cause the motor speed to increase beyond safe limits. The no
field release will cause the handle to fall back
to the off position.
112
Direct current motors are easily reversed. By reversing either the armature or the field
connections changes the direction of flux set up by the poles with respect to the
armature. The North Pole will besouth and vice versa with respect to the armature.
The wide ranges of possible speed variations permit extensiveuses of DC motors. If rated
voltage is applied to the field and armature circuits, the motor will operate at rated
nameplate speed. If the armature voltage is reduced, but the flux is maintained with
rated voltage on the field, the speed will be reduced in proportion to the reduced
voltage.
113
An excellent control method for medium size and smallerDC motors is the use of Silicon
Controlled Rectifiers (SCR). These solid state devices can convert AC to DC very
efficiently and at the same time control the DC voltage. SCRs are available for currents
of hundreds of amperes and can be used to control medium size DC motors by armature
voltage control from rated speed to zero. To increase the speed of the DC motor above
rated speed is quite simple as reduction of flux increases speed.
AC MOTORS
Fig. 2.1-9(a) shows some of important AC motor types.
INDUCTION MOTORS
Asynchronousor induction motors are the most commonly used electricalpower unit on
account of their simplicityand cheapness of constructionand their reliabilityof operation.
Accordingto the type of rotor employed,they are classifiedas squirrelcage motors or slip
ring motors, as shown inFig. 2.1-9(b).
114
The squirrel cage induction motor is by far the most commonly used type of AC
motor. It
is economical to build ha ving good operating characteristics and r equires virtually no
maintenance. Small fractional horsepower sizes usually are woundfor single phase, but
over 1 HP, three-phase operation is more practical for higher Horse Power. The three-
phase windings produce more uniform torque. Single -phase motors are used mostly in
residences where a three-phase power supply is usually not available or necessary.
Construction
The three-phase squirrel cage induction motor has two circuits, a stator and a rotor. The
stator consists of three (phase) windings placed symmetrically in a slotted, laminated sheet
steel magnetic circuit.Fig. 2.1-10 illustrates the parts of a three-phase induction motor.
115
116
The starting current will be high, but of short duration and decreases as the rotor
approaches the speed of the rotating field. The rotor cannot reach the synchronous speed.
If it could, no flux would cut the rotor and there would be no induction or rotor current or
torque and the motor would slow down.
The actual rotor speed slips behind the rotating field sufficiently so it can induce enough
current to produce the torque needed to satisfy the demands of the mechanical load.This
inability to keep up with the synchronous speed is an important measure of an ni duction
motor's performance and is called Slip. It may be measured in revolutions per minute. It
also is expressed in percent of synchronous speed. When written as a decimal
, its symbol
is "S"or Percent slipS %.
NSYN - N rotor
s% = ¥100
NSYN
As mechanical load is increased, the motor slows down slightly. This increases the slip,
induces more current in the rotor secondary and by transformer action an increase in
current and power is drawn by the stator from the power supply.
An induction motor with
no load draws only a magnetizing current. The power input is small, only to provide for
rotational losses. This causes the motor to operate with a very
117
118
As this rotating magnetic field is increasing in one direction, then decreasing and then
increasing in the other direction, a current is induced in the squirrel cagerotor bars.There
are two magnetic fieldsinduced in the squirrel cage induction motor
:
Therefore, a mechanical force is produced on the rotor bars (Right Hand Rule). This
force causes the rotor to get a torque in the direction of rotation of the stator magnetic
field. The rotor always rotates in the same direction as the rotating field of the stator. The
rotating magnetic field of the stator rotates once during every complete cycle of alternating
current. The speed of the rotating magnetic field of the stator is called the Synchronous
Speed of induction motor.If the supply frequency is 60Hz; the magnetic field rotates at:
1. Shaft 6. Frame
119
The wound rotor motor has an insulated winding with the same pole configuration as
the stator. By means of three slip rings on the rotor shaft, the windings can be connected
to three wye-connected external resistors, to reduce starting currents. As the motor
accelerates, the resistances may be removed andthe rotor shorted at the brushes. When
short-circuited, the rotor performs the same as the squirrelcage rotor. The same resistors,
if rated for continuous duty, may be used as a variable speed control. Resistance in the
rotor circuit will increase slip for a particular value of the torque. This results in
decreasing speed. Fig. 2.1-16(c) shows a wiring diagram of a wound rotor motor
connected to its controlling resistors.
Wound rotor motors are used where very high starting torques are necessary such as
for compressors or where control speed is required below synchronous speed. Because
of I2R losses in resistors, the efficiency is decreased as compared to an ordinary
polyphase induction motor.
120
SYNCHRONOUS MOTORS
Synchronous motors are built from the smallest clock motors to t hose of thousands of
horsepower. Large motors, as shown in Fig. 2.1-17(a), can be adjusted to draw a
leading current, thereby correcting the PF of a load with low lagging PF, perhaps
because of under-loaded induction motors.
PRINCIPLEOF OPERATION
When the stator winding of a three phase synchronous machine is connected to a three
phase network, a rotating field is set up in the machine. As shown in Fig. 2.1-17(b), if
the rotor is started in the direction of rotation of the rotati ng field, the north pole of the
121
OPERATING CHARACTERISTICS
APPLICATIONS
122
Fig. 2.1-18 shows that each phase consists of two windings . If connected across 460V,
the phase voltage will be (460/ 3 ) and the voltage across the individual phase
winding will be 133V (266/2). This connection is used for high voltage .
Fig. 2.1-19 shows a parallel star connected motor. In this example, the full supply voltage
is connected across each winding. The parallel star connection consists of two single
windings per phase star connections, connected in parallel.This connection is used for low
voltage.
123
Fig. 2.1-20 shows that each phase consisting of two windings per phase connectedin series.
Therefore, connected to 460V, the voltage across each winding is 230V, (460/2). This
connection is used for high voltage
Fig. 2.1-21 shows a parallel delta connected motor consisting of twosingle windings per
phase delta connections, connected in parallel. Therefore, the voltage across each phase
and therefore, each winding is230V.
124
As seen before, the rotor can never attain the synchronous speed or there will be no
cutting of the magnetic lines. The ratio between the difference of synchronous and rotor
speeds is called the slip NS.and gives the following relationship:
NS - Nr 120 F
N= = NS (1- S) = (1- S)
N P
To change the speed of the induction motor, you either change the frequency or the
number of poles. As the frequency is fixed by the generation, the only way to change
speed is to changethe number of poles by the followingtwo methods:
1. To have completely separate winding sets of poles. For example, two, four, six or
eight. All the necessaryleads are brought outof the stator to a drumcontroller through
which the necessarychangein connecti
on is made.
Fig. 2.1-22 below shows the coils carrying current for one phase of a three
phase four pole
motor winding. Fig. 2.1-22A shows the connection for high speed and Fig. 2.1-22B shows
the connection for low speed operation. The consequent pole means that if there are any
two similar poles beside each other consequently there should be a different pole between
them.
125
STARTING CONCEPTS
All single-phase motors have one primary problem. That is, how to make them self-
starting. A 2-pole stator winding and rotor, only remains stationary and hums without
turning. If two identical windings are connected in parallel to a single-phase source, the
magnetic field produced willalternate but not revolve. Thetwo windings are equivalent to
one winding, as shown in Fig. 2.1-23.
Fig. 2.1-24 shows connections for splitting one phase, i.e., by establishing two
magnetic fields, which are 90∞ out of phase. This is necessary for the starting instant,
after starting and the rotor reaches 75% of its normal speed, a centrifugal switch opens
and disconnects theauxiliary poles winding.
126
CAPACITORSTARTMOTOR
127
Capacitor
Centrifugal Switch
There are many mechanisms to achieve
centrifugal switch function. The basic idea
is that it closes a circuit when the shaft is
standstill and opens the circuit (starting
winding) when the shaft attains75% of its
normal speed. The following Fig. 2.1-28
shows two mechanisms of centrifugal
switch and its application in capacitor start
motor.
128
arrangement. The rotor is the typical squirrel cage. Therefore, speed is a function of line
frequency and the number ofstator Poles.
Universal Motor
A universal motor operates on DC as well on AC up to 60Hz. It develops more horse
power per pound than any other AC motor. This high ratio of power to weight is
accomplished by the high speed developed (Armature speeds of over 20,000 rpm). It is built
to suit the following applications:
Applications
129
Theory of Operation
The idea is to operate a DC series motor on AC supply. The field of a DC series motor is
wound with fewer turns and larger wire than the DC shunt motor. Therefore, the
inductive effect is less and the magnetic field is approximatelythe same as when AC is
applied. Because the field and armature
are in series, the currents IA (Armature current) and
IF (Field current) are the same in both. There is no time lag between their magnetic fluxes
and the motor will operate satisfactorily.One of the most outstanding features of a
universal motor is that it has the highest horsepower-per-pound ratio of any AC motor
because of its abilityto operate at high speeds. A typical 1/2 HP, 1750 rpm induction
motor weighs about 30 pounds and has a 5/8 inch shaft. A 1/2 hp, 19.000 rpm universal
motor weighs2 1/2 pounds and has5/16 inch shaft. The advantages of universal motors over
induction motors are high starting torque, adjustable speed capabilities, small size and
economy.
SpeedControlof UniversalMotor
Speed control of a universal motor is quite simple because speed is sensitive to both voltage
and magnetic flux changes. A rheostat or adjustable transformer, as shown
Fig.in2.1-31, can
vary the speed from zero to maximum speed control of a small universal motor.
MOTORCONTROLS
MOTORCIRCUIT ELEMENTS
As shown inFig. 2.1-32, the elements from which motor circuit is built: are
∑ Motor disconnecting means ∑ Motor overcurrent protection
∑ Motor controller (Contactor) ∑ Motor branch circuit overcurrent
protection
130
NOTES
1. C and D are called motor starters.
2. A, B and C are called combination starters,
A and B maybe:
∑ Safety switches ∑ Motor circuit switches ∑ Circuit breakers
BRANCH CIRCUITS
The NEC defines a branch circuit as the portion of a wiring system extendingbeyond the
final overcurrent device protecting the circuit. All power wiring to a motor must be
protected. Means used for branch circuitprotection are Circuit Breakers and Fuses.
CIRCUIT BREAKERS
131
132
The heater element is connected in series with the motor circuit. Tripping is
accomplished by the relay, which opens the motor control circuit. Bimetallic OL opens
motor control circuit when the heat produced deflects the bimetallic strip as shown Fig.
in
2.1-35.
STARTERS (CONTACTORS)
Most motor applications require the use of remote control devices to start and stop the
motor. Magnetic contactors, as shown below are commonly used to provide this
function. Contactors are also used to control distribution of power in lighting and
heating circuits, as shown in Fig. 2.1-36.
133
134
The sequence of operations here is a little more complex. When the start button is
pressed, the coil of magnetic motor starter M is energized and the motor starts,
provided the running overload current is within the values of the overload relay OL.
However, there is one very important difference. A normally open contact of magnetic
motor starter M seals around the start button to latch the circuit. To stop the motor, the
STOP button is pressed, which, in turn, opens the latching contact M de-energizing
the coil of magnetic motor starter M, and stopping the motor.
135
See Fig. 2.1-41 for a list of common symbols used in ladder diagrams and motor
control circuits.
PREVENTIVE MAINTENANCE
The aims of the preventive maintenance program are increased reliability, optimized
performance and extended lifetime. It recommends that electrical machines are
maintained throughout their lifetime in order to ensure maximum availability and to
eliminate unplanned repair costs.
Maintenance Schedule
The maintenance schedule provides an effective and systematic means of maintaining
a specific motor. Each product family has a unique maintenance schedule based on
manufacturer's recommended instruct ion manual. The maintenance schedules comply
with any specifications issued by the component suppliers and they also take
environmental and operational conditions into account.
136
Motors need regular maintenance and it is recommended that a systematic long term
preventive maintenance program is implemented in line with the regular maintenance
schedules. This ensures optimum performance over the motor’s entire lifetime and
provides the best possible return on motor assets.
137
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
____________________________________________________________________
138
TASK2.1-1
OBJECTIVES
SAFETY PRECAUTIONS
PROCEDURE
139
2. Connect the control circuit, as shown in Fig. 2.1-1 below using wire size 14 AWG.
This is standard way of connecting Start/Stop push button.
3. Connect the other Stop/Start push button control, as shown. This will act as a remote
Stop/Startunit using no. 14 wire.
140
LESSON 2.2
TRANSFORMER COMPONENTS,
OPERATING VOLTAGES AND
COOLING SYSTEM
141
142
LESSON 2.2
TRANSFORMER COMPONENTS, OPERATING
VOLTAGES AND COOLING SYSTEM
LESSON OVERVIEW
DESCRIPTION
OBJECTIVES
143
144
The three phase Power transformers installed in transmission sub stations are normally
constructed and operated at the higher voltages in the range of primary 380 kV, 115
kV/69 kV.
145
CONSERVATOR
The conservator or expansion tank system is
the first transformer oil preservation system.
The oil surface area in contact with the air is
at a minimum and is relatively cool,
minimizing sludging. The connecting pipe
between the conservator and main tank is of
a small diameter inhibiting interchange of
oil between them. Oil in the transformer is
always under a positive pressure and the Fig. 2.2-2 Conservator Expansion
in Fig. 2.2-2.
NITROGEN BLANKET
There is a Nitrogen (N2) blanket put into the sealed tank type transformer, which is
used to keep moisture out and pressure up .
146
BREATHERS
All power transformers other than totally sealed types have a Breather. As the liquid
expands and contracts due to temperature cycling, air must be permitted to enter or
leave the Conservator tank. The simplest Breather contains a f ilter to prevent moisture
from entering the transformer. Silicagel crystals are one example of the drying reagent
used in dehydrating Breathers.
147
These crystals are blue in color when dry and turn pale pink as they become moisture
laden, at which time they should be removed and/or dried. Fig. 2.2-5(a) shows the
positions of a dehydrating Breather in the transformer (Mitsubishi type) and Fig. 2.2-
5(b) shows the construction of dehydrating Breather .
(c)
Fig. 2.2-6 Winding Temperature Indicators
148
BUSHINGS
High voltage terminals of the transformer need insulators to insulate high voltage from
ground. These insulators are called Bushings.
Maintenance of Bushings
For oil-filled bushings, the oil level can be
checked through the oil -filling plug or sight glass,
as shown in Fig. 2.2-8.
149
150
151
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
____________________________________________________________________ _
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
152
LESSON 2.3
153
154
LESSON 2.3
POWER TRANSFORMER TESTS
LESSON OVERVIEW
DESCRIPTION
In this lesson, different tests are carried out to check the transformer and cooling
oil during the service period and the results are compared with normal manufacturer's
test standard data as part of regular maintenance.
OBJECTIVES
TRANSFORMER TESTS
Different tests are carried out to check the transformer characteristics, as shown
in Table 2.3 -1.
Table 2.3 -1 Transformer Tests
1. Ratio test 2. Polarity Test
3. Impedance Test 4. Insulation Resistance
5. Resistance of Winding 6. No Load Losses Test
7. No Load Current Test 8. Core Insulation Voltage Test
9. Temperature Rise Test 10. Impulse Voltage Test
11. Noise Level Test 12. High Voltage Test
13. Induced Voltage Test 14. Bushing Power Factor Test
155
X2 X1 X1 X2
20 V 20 V
80 V V V
120 V
100 V 100 V
H2 H1 H2 H1
(a) Subtractive (b) Additive
Fig. 2.3-1 Method used to determine Polarity Markings
156
157
A
windings can be measured simply by
V
Voltmeter/Ammeter method, as shown BATTERY K1 WINDING
in Fig. 2.3-5.
All test readings should be recorded for comparison with past results. Insulation
deteriorates with time and test readings are means for monitoring the conditions of
transformer insulation over time.
158
TRANSFORMER OIL
Power transformers are mostly cooled by oil and usually the first thing checked in
determining the condition of a transformer is the oil. In a transformer, oil not only acts
as insulation but also provides a medium carrying heat away from the windings.
Hence, it should not only have high dielectric strength, but should also have low
viscosity to provide good heat transfer. It should also be free of sulphur and other
corrosive agents, which might injure the insulation, conductors and other metallic
parts. It should not permit moisture particles to remain in suspension but allow them
to settle quickly to the bottom, and it should be free from sludging under normal
operationing (heat) conditions.
OIL TESTS
∑ Appearance test ∑ Color test ∑ Odor test
∑ Interfacial tension test ∑ Crackle test ∑ Neutralization test
∑ Dielectric breakdown voltage test ∑ Dissolved gas-in-oil analysis test
159
Heat the sample rapidly over until it begins to boil. If any audible crackling occurs,
this indicates the presence of moisture.
For this test, motorized oil set test kit is used, as shown in Test Kit of Fig. 2.3-7. The
oil is tested between two, one inch diameter circular electrodes set in a standard test
cup. The electrodes are usually set with spacing between them of 2.5 mm and these
electrodes are parts of an adjustable AC high potential test set.
1. Mains supply switch
2. Mains on indicator lamp
3. Manual auto switch
4. HV indicator lamp
5. Auto start push button
6. HV over load switch
7. Speed selector switch
8. Voltage control hand wheel
9. Mains fuse
10. Scale
11. Oil drip tray
12. Electrode Supports
13. Electrode
14. Cover
160
SUMMARY
∑ The insulation resistance of a transformer should be at least 1 MW for each 1000
Volts of test voltage.
∑ In a transformer, oil acts as insulation and also provides a medium for heat tra nsfer
from the windings for cooling.
∑ Do not attempt to sample oil from energized sealed transformers.
GLOSSARY
TTR: Transformer Turns Ratio HV: High Voltage
LV: Low Voltage PPM: Parts per Million
FORMULAS
I1 ¥ N1 = I2 ¥ N2
I1 N2 V1Z1 V1 Z2
= = = ¥
I2 N1 V2 Z2 V2 Z1
161
REVIEW EXERCISE
1. The insulation resistance of a transformer should be at least _______ for each 2000
Volts of test voltage.
a) 1 KW b) 2 MW
c) 1 MW d) 2 KW
2. If the insulation resistance of a transformer falls below 1 MW for each 1000 Volts
of test voltage, the presence of ________ or ________ _____ may be indicated.
162
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
____________________________________________________________ _________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
163
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
164
UNIT-3
TRANSMISSION SUBSTATIONS
165
166
UNIT-3
TRANSMISSION SUBSTATIONS
UNIT OVERVIEW
DESCRIPTION
OBJECTIVES
Upon completion of this unit the participants should be able to familiarize with:
∑ Transmission Substation Components, Operating Voltages and Diagrams
Components: Switch Gear, Transformer, Relays
Operating Voltages: 115, 230, 380 kV
Diagrams: Layout and Single Line Diagrams
Transmission Towers/Lines and Maintenance
Standard Poles, Towers and Switchyard Structures, Steel Towers, Overhead
Transmission Lines (115, 230, 380 kV), Substation Switchyard
Circuit Breakers: Bulk, Air, Gas, Vacuum Circuit Breaker, Breaker Operating
mechanism, Breaker Motion Analyzer
167
168
LESSON 3.1
TRANSMISSION SUBSTATION
COMPONENTS, OPERATING
VOLTAGES AND DIAGRAMS
169
170
LESSON 3.1
TRANSMISSION SUBSTATION COMPONENTS,
OPERATING VOLTAGES AND DIAGRAMS
LESSON OVERVIEW
DESCRIPTION
OBJECTIVES
171
172
SUBSTATION TYPES
Although, there are generally four types of substations, there are substations that are
combinations of two or more types:
1. Step-up Transmission Substation
2. Step-down Transmission Substation
3. Distribution Substation
4. Underground Distribution Substation
The Step-Up Transmission Substation (Fig. 3.1-2) receives electric power from a
nearby generating power plant and uses a large power transformer to increase the
173
High voltage (HV) AC 69 kV, 115 kV, 138 kV, 161 kV, 230 kV
Extra-high voltage (EHV) AC 345 kV, 500 kV, 765 kV
Ultra-high voltage (UHV) AC 1100 kV, 1500 kV
Direct-current high voltage (DC HV) ±250 kV, ±400 kV, ±500 kV
Fig. 3.1-2 Step-Up Transmission Substation
A substation can have Circuit Breakers that are used to switch generation and
transmission circuits in and out of service as needed or for emergencies requiring
shut-down or redirection of power to a circuit. The specific voltages leaving a step -up
transmission substation are determined by the cu stomer needs of the utility supplying
power and to the requirements of any connections to regional grids. The typical DC
voltage is either positive or negative polarity. A DC line has two conductors, one
positive and the other negative.
174
3- DISTRIBUTION SUBSTATIONS
Distribution substations (Fig. 3.1-4) are located near to the end-users. Distribution
substation transformers change the transmission or sub -transmission voltage to lower
levels for use by end-users. Typical distribution voltages vary from 34,500 Y/19,920 V
to 4,160Y/2400 V. The 34,500 Y/19,920 V is interpreted as a three-phase circuit with a
grounded neutral source.
175
This would have three high-voltage conductors or wires and one grounded neutral
conductor, a total of four wires. The voltage between the three phase conductors or
wires would be 34,500 Volts and the voltage between one phase conductor and the
neutral ground would be 19,920 Volts. From here the power is distributed to
industrial, commercial and residential customers.
176
SUBSTATION COMPONENTS
The major components of a typical substation are, as shown in Table 3.1-1.
177
CIRCUIT BREAKER
The Circuit Breakers (Fig. 3.1-6) are simple
devices, which cut off the power circuit whenever
the current jumps above a safe level until the
electrical personnel on duty can fix the problem .
POWER TRANSFORMERS
178
OH transmission lines (69/115 kV). Steel towers are used for transmission lines
(69/115/230/380 kV). In some cases, wooden poles are carrying some of the
distribution line equipment, such as transformers, fuse cutouts, voltage regulators.
SWITCHYARDS
Switchyards (Fig. 3.1-10) are the places where a transmission line terminates to
buses as an outgoing or incoming line or terminates to an equipment bushing. The
following figures show examples of wooden poles, transmission towers and
switchyard structures.
179
POWER DELIVERY
Electric power leaves the power plants and moves through a complex network of
overhead power lines and underground cables to reach the customers (Fig. 3.1-11).
SEC strives to maintain steady state voltage within limits established by the SEC
standards. However, all electric distribution systems are subject to occa sional voltage
variations. These variations, even when within limits, can cause the sensitive electrical
equipment within your facility to operate incorrectly. Our electric system is designed
to sense unsafe or unstable conditions that affect the flow of electricity on a power
line, such as certain power quality events caused by acts of nature or construction
mishaps.
When the distribution system senses a disturbance, the electric current is automatically
interrupted by a device called Recloser, which is si milar to a fuse or Circuit Breaker.
180
In most instances, within a few seconds, this electrical device will safely reclose the
circuit to restore power and help isolate the effect. Occasionally, the device will
reopen because the problem still exists or because the devices still sense unsafe
conditions, causing momentary interruptions and flickering lights. The overall
reliability of the circuit is actually increased when Reclosers are used. The operation
of such devices means that the system is operating effe ctively. Without these devices,
a power interruption would continue until a utility employee could manually restore
the power.
The technical staff is working hard to eliminate as many of the causes of these
interruptions as they can. In addition to performing upgrades to the equipment, they
are involved with major tree trimming initiatives to lessen the likelihood of storm-
related outages. They are also coordinating with construction contractors to educate
them on the safe and proper excavation methods to use around our buried
underground lines.
SUMMARY
∑ A substation is a high-voltage electric system facility used to switch generators,
equipment and c ircuits or lines in and out of power system.
∑ A transmission bus is used to distribute electric power to one or more transmission
lines.
∑ The Step-down transmission substations are located at switching points in an
electrical grid connecting different parts of a grid sourcing power to sub-
transmission lines or distribution lines.
∑ The sub-transmission voltage lines serve as a sour ce to distribution substations.
∑ The Distribution substation transformers transform the sub -transmission voltage to
lower levels for use by end-users varying from 34,500 Y/19,920 Volts to
4,160Y/2400 Volts.
∑ Switchyards are the places where a transmission line terminates to buses as an
outgoing or incoming line or terminates to an equipment bushing.
GLOSSARY
OH: Over -Head EHV: Extra-High Voltage
LV: Low Vol tage UHV: Ultra-High Voltage
HV: Hi gh Vol tage
181
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
182
REVIEW EXERCISE
1. The four types of substations are :
a) b)
c) d)
2. The power can be tapped from the incoming power feed from the generation plant
to provide electric power to operate equipment.
a) True b) Fal se
5. Li st four maj or types of subst at ion equi pment /prot ecti ve devi ces.
a) b)
c) d)
6. Enlist the sequential electric power flow when electricity leaves a powe r plant:
183
184
LESSON 3.2
185
186
LESSON 3.2
BUSBARS AND CIRCUIT BREAKERS
LESSON OVERVIEW
DESCRIPTION
This lesson describes the Single and Sectionalized Busbar System, Main and transfer
Bus, Ring and Double Bus concluding with different types of Circuit Breakers and
their applications.
OBJECTIVES
Upon completion of this lesson, the participants should be able to familiarize with:
∑ Busbars
Single and Sectionalized Busbar System, Main and transfer Bus, Ring and Double
Bus, Breaker one and Half breaker Design, Switchgear Identification
∑ Circuit Breakers
Bulk, Air, Gas, Vacuum Circuit Breaker, Breaker Operating mechanism, Breaker
Motion Analyzer
BUSBARS ARRANGEMENT
Different busbar arrangements are used to serve certain requirements for system
operation, protection and to control the power flow, as follows:
1. Single Busbar System
2. Sectionalized Single Busbar
3. Main and Transfer Bus Double Main Bus
4. Ring Bus Design
5. Double Bus and Single Breaker and Half Design
187
188
1- SINGLE BUSBAR
Fig. 3.2-1 shows Single Busbar scheme used
for smaller substations. It is to be noted that if
at any time a busbar fault occurs, all feeders
will be deprived of supply.
189
The multi-sectionalized
busbar is shown in Fig . 3.2-
4. By these means, a
generating plant on any
section can be utilized to
supply the feeders on any
adjacent section. Fig. 3.2-4 Sectionalized Busbar System
190
(a) (b)
Fig. 3.2-7 Double Bus Double Breaker
Both sets of equipment are usually kept in service at all times. Thus, if either should
fail, interruption does not occur to the connected facilities. Fig. 3.2-8 shows an
example of double ma in bus in SEC.
191
Main buses sometimes are arranged in the form of a ring. This provides some of the
reliability of the parallel bus and keeps some of the economy of the radial bus. Instead
of using Circuit Breakers to disconnect each piece of equipment, the breakers are
placed in the RING BUS dividing the rings into sections. Each separate section can
be disconnected and some connected equipment with it without interruption to the
other sections.
192
Fig. 3.2-11 shows an example of Double Bus Single Breaker scheme used in SEC.
193
CIRCUIT BREAKERS
Circuit Breakers are classified according to insulation and air extinguishing medium,
as follows:
1. Bulk Oil Circuit Breakers (BOCB) 4. Gas Circuit Breakers (GCB)
2. Minimum Oil Circuit Breakers (MOCB) 5. Vacuum Circuit Breakers (VCB)
3. Air Circuit Breakers (ACB)
A circuit breaker is a mechanical device for opening or closing a circuit s afely under
all abnormal conditions. Circuit breakers can be operated automatically as well as
manually, but for high voltage and heavy current, they are generally spring or
electromagnetically assisted or remote controlled.
Overload trips, generally with some form of
time lag, are fitted so that the circuit breaker
will trip in the event of a serious overload or
a fault. Circuit Breakers are used to protect
the electrical equipment and circuits against
internal or external short circuit and to
provide flexibility of control and operation.
The control circuit for protection is shown Fig. 3.2-13 Protection Control Circuit
in Fig. 3.2-13.
194
195
Fig. 3.2-17 MOCB type TRI
They are reduced in size and oil. Fig. 3.2-18 (a) and (b) shows comparison between
MOCB and BOCB. In the BOCB the tank is "dead" at earth potential and the
necessary clearances for the system voltage must be obtained in oil between live
contact the tank and between other contacts .
In the MOCB, the tank is a tube of
insulating material held between metal and
caps and as these caps are the terminal
points for the external circuit, the tank, in
normal circumstances, is live at line
voltage. Operating mechanism of MOCB is
mostly spring, the spring either manually
charged or charged by motor. The energy
(a) MOCB (b) BOCB
stored in the springs is utilized for both the Fig. 3.2-18
closing and tripping operation.
196
external aid required for current interruption. As for air-blast CB, a supply of clean,
dry air at the correct pressure and in sufficient volume must be available at all times.
For this, a compressed air arrangement is essential with duplicate compressors for
security, along with air storage facilities and a network of feed pipes.
Fig. 3.2-19 Air Blast Circuit Breaker Fig. 3.2-20 SF6 Circuit Breaker
Recently, SF6 gas is used in insulation and extinguishing medium in Circuit Breakers.
SF6 is a colorless and odorless gas. It has excellent dielectric properties. Under
comparable conditions , its dielectric strength is about 2.5 times that of air. SF6 Circuit
Breaker shown in Fig. 3.2-20 has one arcing chamber per pole of the self -generating,
single-pressure design. During the opening sequence, a piston coupled to the nozzle
contacts, generates the SF6 flow required for arc interruption. The 3-pole drive is of
the oil hydraulic design. All ancillary equipment, including the oil pump and
accumulator associated with the drive, form a modular assembly that is mounted
directly on the circuit breaker, thus eliminating installation of hydraulic piping on site.
197
A vacuum CB is used in high voltage distribution circuits. The contacts are placed in a
sealed container in a vacuum and they are in the form of flat disks with their faces
together, as shown in Fig. 3.2-21 and Fig. 3.2-22. The moving contact is connected to
the outside operating mechanism by means of metal bellows to maintain the vacuum.
Since the contacts are in a vacuum, there are no particles to cause ionization when the
arc is formed as the contacts part. However, some ionization occurs at the contact
surface, owing to vaporized metal at this point, but the arc is extinguished at the first
current zero after the contacts start opening. Thus the duration of the arcing time being
very short, the contacts being in vacuum there is no oxidization and negligible burning
require no maintenance.
Fig. 3.2-21 Vacuum Circuit Breaker Fig. 3.2-22 Vacuum Circuit Breaker
198
199
200
measurement requirements for high-voltage circuit breaker testing. It can measure and
calculate contact paths and the speeds at which breaker contacts operate as well as the
current in operating coils. It can also measure dynamic resistance (DRM), voltage,
pressure, vibration signals and other analog quantities.
After measurement, the MA61 performs the necessary calculations and prints results
on a connected printer (letter-size A4 paper) or via the TM1600’s built-in printer.
Moreover, parts of curves can be easily enlarged for closer study. The MA61
incorporates a battery-backed memory that can store up to ten measurements for
subsequent processing.
Preparation
Set the desired breaker operating sequence on the TM1600. In this case, Close-Open
(CO).
Recording
Enable recording with the READY button. Start the breaker sequence and
measurement simultaneou sly by turning the START switch.
Test Report
The result is printed automatically. This example shows a CLOSEOPEN (C-O)
sequence presented in the report 1 format (85 % of actual size). Only the initial
contact closing time (CLOSE) and final contact separation time (OPEN) are presented
in the report 1 format. Short bounces are not shown .
Preparation of MA61
201
The following additional settings are needed when you include motion recording in
breaker analysis. These settings are menudriven via the built-in display on the MA61.
1. Select test interval (50 ms to 1 s).
2. Calibrate the input(s) connected to the position transducer(s) , as follows:
a) Close the breaker.
b) Record closed positio n via menu option.
c) Open the breaker.
d) Record the open position.
e) Estimate or measure breaker stroke. Enter the value via the menu.
f) Enter speed calculation parameters.
3. Enter the current range and the scale factor for the current shunt for current to be
measured.
4. Enter range and scale factor for other transducers , if used.
Recording
Press the READY button to prepare the TM 1600 for measurement.
Travel measurement, time measurement and the breaker sequence all start
simultaneously when you turn the START knob. The inputs now record the input
voltages obtained from the connected transducers.
Test report
The motion recording report includes both curves and a table. The table presents
calculated breaker parameters such as closing speed, opening speed, overtravel and
penetration.
The diagram shows one or more time/amplitude curves and the calculated breaker
parameters. The time axis scale factor can be changed to provide you with a quick
overview of an enlarged view part of diagram.
The position of the curve in the diagram and the amplitude scale factor can also be
changed to make best use of the available space. The damping and speed variations at
closing and opening times can be studied on the speed curve obtained from each of the
motion-monitoring c hannels.
202
203
204
SUMMARY
∑ Bus-Bars may be in the shape of tubes, bars, pairs or cable.
∑ The bus duct is a sheet metal pipe that supports and protects the heavy, hollow,
square/round copper/aluminum bus.
∑ The bus support insulators and the surrounding duct jacket provide electrical safety
and protection, not only for the bus but also for the plant personnel and equipment.
∑ Circuit breakers (CBs) protect the e lectrical equipment and circuit against internal
or external short-circuits.
∑ The most common five design specifications of Circuit Breakers are:
Voltage Rating, Insulation withstanding voltage, Current rating, Interrupt ratings
and Operating time in Hz.
∑ The oil as an insulator in an OCB and its excellent cooling properties gives greater
current carrying capability in smaller packages.
∑ SF6 gas used in GCBs for insulation and extinguishing medium is a colorless,
odorless, non-toxic, inert and odorless gas having excellent dielectric properties
(2.5 times that of air) under comparable conditions .
GLOSSARY
T-Bus: Transfer Bus. NEMA: National Electrical Manufacturers'
Association.
ACB: Air Circuit Breakers. AIEE: American Institute of Electrical
Engineers.
BOCB: Bulk Oil Circuit Breaker. kVA: kilo-Volt-Amperes.
MOCB: Minimum Oil Circuit Breaker. MVA: Mega-Volt-Amperes.
GCB: Gas Circuit Breakers.
2.5 FORMULAS
E
I= Where: I = Current E = Applied voltage Z = Circuit resistance
Z
205
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
206
REVIEW EXERCISE
1. Bus-Bars are normally made of _____________ or _______________.
2. An isolated phase bus duct carries each phase of the three-phase generator output
in separate duct.
a) True b) False
3. The high capacity bus ducts often utilize _____________ cooling, where filtered
air is drawn through the duct to increase heat transfer.
4. The British Standards specify that the temperature rise, when carrying normal
rated current at rated frequency, shall not exceed __________°C.
a) 59 b) 75
c) 125 d) 55
7. OCBs suppress the sparks of high voltage better than pneumatically operated Air
Circuit Breakers.
a) True b) False
8. All tanks in BOCB are mounted directly to the floor without insulators and
grounded at 0V potential.
a) True b) False
207
______________________________ ______________________________
11. A ____________ is used in high voltage distribution circuits where the contacts
are placed in a sealed container in a vacuum in the form of flat disks with their faces
together.
208
UNIT-4
DISTRIBUTION SUBSTATIONS
209
210
UNIT-4
DISTRIBUTION SUBSTATIONS
UNIT OVERVIEW
OVERVIEW
This unit consists of two lessons as follows:
Lesson 4.1 deals with Distribution Substation Types , Components and Voltage Levels
followed by two tasks. This lesson familiarize the participants with distribution
substation equipment, EOS, SF 6 Ring Main Unit (RMU), Lucy switchgear, earth fault
indicators and single line diagrams.
Task 4.1-1: Demonstrate Distribution Network in Outside Yard
Task 4.1-2: Identify secondary and customers distribution equipment
Lesson 4.2 discusses Meter Types and their Classifications and overviews the
operation and maintenance of different types of meters used in power transmission
and distribution systems.
OBJECTIVES
Upon completion of this unit the participants should be able to fa miliarize with:
∑ Distribution substation Types
Room Type Substations, Unit Substation, Lucy RMU and EOS
∑ Components of Distribution network
MV Components, Ring Main Unit (RMU), Earth Fault Indicator (EFI), Substation
Room, Air Switches, Circuit Breakers, Distribution Panel, Overhead Line
Patrolling, Overhead Line Equipment
∑ Inspection and Maintenance of Components of Distribution network
∑ Meter Types and their Classifications
211
212
LESSON 4.1
213
214
LESSON 4.1
DISTRIBUTION SUBSTATION TYPES,
COMPONENTS AND VOLTAGE LEVELS
LESSON OVERVIEW
DESCRIPTION
This lesson familiarize the participants with distribution substation equipment, EOS,
SF6 Ring Main Unit (RMU), Lucy switchgear, earth fault indicators and single line
diagrams.
OBJECTIVES
∑ Trace the single line diagram for unit substation with RMU.
∑ State purposes of RMU and EOS and identify the parts of Lucy switchgear.
∑ State the applications , uses and range of SF6 Ring Main Unit (RMU).
215
216
INTRODUCTION
The distribution system is fed through grid stations. They are of a large capacity and
supply power to a large area through many primary feeders. Each primary feeder is
supplying several distribution substations .The primary and secondary distribution is a
part of the system through which the power finally reaches the industries and
residential consumers . Distribution Substations are those substations, which are
located nearest to the load. The outgoing feeders supply the distribution substation
with 13.8 kV, or 34.5 kV from Grid Station, and reducing the AC power to a level
suitable for distribut ion (220V, 110V).
DISTRIBUTION SUBSTATIONS
There are five types of substations used for primary distribution as follows:
217
2) PLATFORM MOUNTED
TRANSFORMER
3) UNIT SUBSTATION
Unit substations in Fig. 4.1-3 consist of a 13.8 kV/LV distribution transformer with an
integral LV distribution panel.
Unit substations are used to supply LV
network in residential and commercial
areas. The advantage of unit substations is
its compact size, which makes it easier to
obtain sites for installation and easier to
find an area for the LV network with
short LV feeders.
Fig. 4.1-3 Distribution Unit Substation
218
4) PACKAGE SUBSTATION
Package substation Fig. 4.1-5 used in
SEC where the Ring Main Unit
(RMU), transformer and secondary
voltage distribution cabinet form one
unit.
The main equipment installed in a room -type substation is the transformer, Ring Main
Unit, LV panel, and HV/LV cables. Transformer at room type is a ground-mounted,
500/1000 kVA. RMU is a ground-mounted with two 400 Amps ring switches. LV
distribution panel is fitted with a 1600 Amps isolator for incoming circuit and eight
outgoing 400 Amps each.
219
LUCY EOS
All oil switches include fully interlocked earthing and testing facilities for the ring
cables, while the fuse switches have earthing facilities for the tee-off cables or
transformer connection only.
Fig. 4.1-7 incorporates two oil switches for isolation
of the ring main circuit and an oil fuse switch for
controlling the tee-off feeder. Each of the two
switches is a single break, 3-position type On/OFF
and Earth.
220
2
is more than that of electric oil at a pressure of 3 kg/cm . This gas is now being very
widely used in electrical equipment such as HV Circuit Breakers. This gas liquefies at
certain low temperatures, the liqu efication temperature increasing with pressure.
Several types of SF6-RMU are filled with SF6 gas. SF6 substations are compact and
are favored for use inside crowded cities. The following properties of SF 6 gas mak es
it unique for application in electrical equipment.
1-Physical Properties
Colorless odorless, non -toxic gas, non-inflammable, inert gas
State: SF6 is a gas at normal temperature and pressure .
Density: SF6 is a heavy gas, with a density five times that o f air at 20∞C and standard
atmospheric pressure .
221
∑ At pressure about 3 kg/cm2 , the dielectric strength of SF 6 gas is more than that
of dielectric oil. This property permits smaller clearances and small size of
equipment for the same kV.
222
DISTRIBUTION TRANSFORMERS
The transformer is one of the most efficient electrical equipment ever built. Its
purpose is to increase or decrease voltage or current. Briefly, the transformer changes
electric energy to magnetic energy and then back to electric ener gy, by the process of
mutual induction.
In addition to accessory equipment such as fans, pumps, tap changer, counter and
mechanism, there are various gauges to be read and logged, such as temperature,
pressure and oil level gauges. Some transformers also have a breathing system that
must also be inspected during PM checks. Transformers are usually designed for
average required voltage conditions. However, most transformers obtain some
flexibility of operation by having several tap positions available.
This may be done to make up for the voltage drop in the supply or to accommodate a
specified characteristic of the connected load. The winding taps usually are brought
under oil to a rotary dial switch located inside the transformer tank. The rotary switch
changes the taps and is rotated manually by means of a crank or handwheel usually
located at the side of transformer enclosure. Most transformers have a nameplate
nearby indicating the voltage obtained at each tap position. Some positive means
(Lock or bolt) is used to assure that the tap changer cannot be moved accidentally.
Fig. 4.1-9 shows no load tap changer and Fig. 4.1-10 shows internal wiring of
transformer with tap changer.
223
LV PANEL
Fig. 4.1-12 shows LV panel including the outgoing secondary from LV panel to Mini -
pillars. The LV panel is connected to a nearby distribution transformer.
Fig. 4.1-13 shows a single line diagram of a LV panel. Grounding facilities are
provided in the panel.
Incoming
Fuse
Transformer
Distribution cabinet
Busbar
Outgoing
224
MINI-PILLARS
Mini-pillars are installed outdoor to receive incoming cables from the LV panels. The
Mini-pillars are capable of accepting up to two 4×300 mm 2 Al cables and five 4×70
mm2 Al cables, Fig. 4.1-14(a-b).
The first point is taken care by the Protection System by initiating tripping action of
the Circuit Breaker (CB). The second point is taken care by the EFIs, when operated
giving indication of flow of an earth fault current through the cable on which they are
225
226
FLAG INDICATION
Fault indication is by a moving flag visible through a transparent plastic window.
Partially dropped flag indicates a flow of fault current , Fig. 4.1-16. The flag will drop
completely when the fault is isolated. When supply is restored, the indicator will reset,
automatically. Type 'A' Reset Indicators
are provided with a hand reset option. It
is operated by means of a push-button
located in the EFI case. Type 'B'
indicators are provided with automatic Fig. 4.1-16 Positions of Flag
reset.
227
Rated Voltage: 12 kV
Rated Current – Busbars: 2500 A
Rated Current - Circuit Breaker: 2500A
228
229
ARCING COLUMN
The interrupter is a single pressure type that consists of cylinder and a piston as
shown in Fig. 4.1-23. The arcing column is shown in Fig. 4.1-24. The arcing chamber
of each pole unit consists of a cylindrical arcing tank and two bushings , comprising a
pressurized chamber as a whole.
230
Manual (DMM-01-01) provides general guidelines for the inspection and maintenance
of substation equipment on distribution feeders rated 34.5 kV or below consist of any
of the following:
1. Ground mounted substations, indoor and outdoor, with RMUs.
2. Ground mounted package substations with MV air break switchgear
3. Ground mounted compact substations with MV switchgear.
4. Pole mounted substations with transformer on a platform and controlled by an
RMU or Cutout Fuses.
231
232
INSPECTION OF MINI-PILLAR
Routine inspection of each Mini -pillar in service should be carried out as follows:
∑ Costal/High Humidity Areas
Metal enclosure once every four (4) years
Fiber enclosure once every six (6) years
∑ Other Areas
Metal enclosure once every five (5) years
Fiber enclosure once every six (6) years
233
The scheduling of the overhead line maintenance is based on the information recorded
on the patrol sheet. Likewise the materials, equipments and tools required to effect the
necessary repairs should be evident from the patrol sheet.
TYPES OF PATROLLING
Two types of periodic patrolling are carried out on the overhead distribution line
system, as follows:
Safety Patrol
This patrol is carried out to ensure safety to the public by the visual detection of
possible hazards. The patrol in open country, desert village and suburban area will be
conducted from a vehicle. In congested area, it will be sometime necessary to carry
out the patrol on foot.
Detailed Patrol
This patrol is carried out on foot along the route of a lin e in conjunction with planned
maintenance. The purpose of this patrol is to detect network defects and interference
prior to the start of planned maintenance on that section of line . Items to be covered in
this patrol are detailed in Fig. 4.1-25.
234
235
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
236
REVIEW EXERCISE
1. A padlocked A) The operation of any one fuse operating on a trip bar gives triple
hinged flap pole tripping of the switch fuse.
2. Interlock lever B) Restricts access to the operating shafts of the switches.
3. Striker pin fuses C) prevents the switch being operated through from ON to EARTH
4. Room substation. D) Supply LV network in residential and commercial areas.
5. Platform mounted E) The high tension is supplied to the transformer either by overhead
transformers lines or by underground cables from an RMU.
6. Dedicated s/s F) High tension is supplied to the transformer by U/G cable
7. Unit substations G) Installed outdoor to receive incoming cables from the LV panels
and outgoing cables for service connections.
8. Pad mounted H) Installed in consumer’s building, used for schools, apartment
transformer buildings, commercial buildings, industrial buildings and
compounds.
9. Mini-pillars I) For one customer.
1. (SF6) is an inert, light gas having bad dielectric and arc extinguishing properties.
2. Same SF6 gas is recirculated in the circuit, hence the big requirement of SF 6 gas.
3. The maintenance required for RMU switch is minimum.
4. The life of metallic parts and contacts are longer in SF6 gas.
5. SF6 is a gas at low temperature and pressure.
6. Moisture has low effect to the properties of SF 6 gas.
7. The SF6 is a chemical inactive gas.
237
238
TASK 4.1-1
IDENTIFY PRIMARY DISTRIBUTION EQUIPMENT
PROCEDURE
1. Study the following steps of the performance sheet , carefully.
2. Go to outside distribution equipment yard.
3. Identify and state the purpose of a distribution transfor mer.
4. Identify and state the purpose of distribution substation with pole mounted
transformers.
5. Identify and state the purpose of a distribution substation with platform
mounted transformers.
6. Identify and state the purpose of a distribution substation with pad mounted
transformer.
7. Identify and state the purpose of an indoor (consumer's type) primary
distribution substation. Go inside and point to Circuit Breaker and instruments
on switchgear.
8. Identify and state the purpose of a primary distribution overhead line.
9. Identify and state the purpose of a primary distribution underground cable
feeding an overhead line.
10. Identify and state purpose of a cable term .
239
TASK 4.1-2
IDENTIFY SECONDARY AND CUSTOMERS DISTRIBUTION
EQUIPMENT
PROCEDURE
1. Identify and state the pur pose of a secondary distribution transformer.
2. Identify and state the purpose of a LV panel.
3. Identify and state the purpose of metering instruments inside the LV panel.
4. Identify and state the purpose of incoming and outgoing cables for the LV panel.
5. Identify and state the purpose of a Mini -pillar.
6. Identify and state the purpose of incoming and outgoing cables for the Mini-
pillar.
7. Identify and state the purpose of a consumer's panel with KWH meters.
8. Identify and state the purpose of a consumer's panel with KWH meters and
Current Transformers.
240
LESSON 4.2
241
242
LESSON 4.2
METER TYPES AND CLASSIFICATIONS
LESSON OVERVIEW
DESCRIPTION
This lesson overviews the operation and maintenance of different types of meters used
in power transmission and distribution systems.
OBJECTIVES
Upon completion of this lesson, the participants should be able to familiar ize with:
∑ Meter Types
∑ Meter Connections
∑ Meter Installation
∑ Whole Current (WC) Meter, Current and Voltage Transformer (CT & PT) Meter
243
244
INTRODUCTION
Electrical power is measured by Wattmeter. The electrical power is the rate at which
electrical energy is used and its unit of
measurement is the Watt while the unit of
measuring electrical energy is Watt-hour.
The instrument used to measure the electrical
energy is Watt-hour meter, which measures
the total electrical energy during specific
Fig. 4.2-1 Kilo-Watt-Hour Meter
time as kilo-Watt-hour meter. ( Fig. 4.2-1)
245
246
It is common to have a condition where VARs are equal to the Watts. This is one
reason why overload occurs to feeders. Many substations have installed capacitors to
compensate for this condition.
WATT-HOUR METERS
The WH meter is an instrument that is used t o measure electrical energy. The (KWH)
meter is an instrument that is used to measure electric energy sold by SEC. Its function
is to provide an accurate record of the electric energy. KWH meters measure the
amount of electric energy passing through variou s parts of the generating, transmission
and distribution systems .
Some KWH meters are
equipped with demand
registers and named Watt-
hour demand meters. The
demand meters indicate or
record the peak demand or
the maximum demand at
given time period. Fig. Fig. 4.2-6 Maximum Demand KWH Meters
4.2-6 shows example of
maximum demand KWH
meters.
247
DEMAND LOAD: It is the load demanded by the customer averaged over a suitable
and specified interval of time.
CLASSIFICATION OF METERS ACCORDING TO TYPE
METER TYPES
∑ WHOLE CURRENT (WC)
METERS
Used for low voltage
customer load not exceeding
150 Amps.
∑ CURRENT TRANSFORMER
(CT) METERS
Used for customer load
exceeding 150 Amps.
248
249
Table 4.2-1 shows the Dimension of CTs, bus bar and cable size.
250
251
252
253
METERS IN INSETS
∑ As per standard one to four meters can be installed on the front wall of the
consumer.
∑ For the installation of 4 to 16 meters, the consumer shall provide a wall in an
inset to install the meters.
∑ Meters in the inset shall be installed in meter boxes as per prototype depending
on the number of meters in the plan , (Fig. 4.2-15, 16, 17, 18, 19).
∑ A space of 10 mm shall be provided between two adjacent meter boxes .
∑ A clearance of 200 mm shall be maintained between the meter boxes and the
border of the assigned area on the right, left and th e top of the installation.
∑ Clearance between the bottom of any meter box and the ground level shall be
800mm.
254
255
256
SAFETY PRECAUTIONS
∑ Ensure that approved personal protective equipment is used.
∑ Ensure that required work clearances (work permit and hold tags) have been
obtained.
257
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
258
REVIEW EXERCISE
1-Complete the following
Classify the meters according to type of current to be measured:
a) --------------------------------- (WC) METERS
Used for low voltage customer load not exceeding 150 Amps.
b) ------------------------------------- (CT) METERS
Used for customer load exceeding 150 Amps.
c) --------------------------------------------------------------- (CT&PT) METERS
d) Used for customer load from medium voltage 13.8 kV and above.
259
260
UNIT-5
ELECTRICAL DIAGRAMS,
SWITCHING ACTIVITIES,
LINEMAN AND CABLEMAN
261
262
UNIT-5
ELECTRICAL DIAGRAMS, SWITCHING ACTIVITIES,
LINEMAN AND CABLEMAN
UNIT OVERVIEW
DESCRIPTION
This unit consists of four lessons:
Lesson 5.1 familiarizes the participants with different types of Electrical Drawings
used for maintenance and troubleshooting of electrical power systems. This lesson
describes the layout and single line electrical diagrams.
Lesson 5.2 familiarizes the participants with Switching Activities of electrical
systems. The switching activities include switching to transfer load, switching to
energize isolated circuits, switching apparatus with remote operation facilities as well
as hold tags and lockout, grounding and safety procedures.
Lesson 5.3 for Lineman and Cableman Activities, discusses how the lineman in SEC
maintains and constructs OH Distribution and Transmission lines and be
knowledgeable of materials, work procedures and safety precautions necessary to
perform his job. The cableman's duties include the quality of joint and termination
while using manufacturer instructions for installation , making precise measurements
and cleaning joints by properly applying heat to shrinkable materials.
In Lesson 5.4 for Cable Splicing Activities, mainly Cable Receiving, Safety Aspects,
Work Procedures, Work Site Preparation, Direct Burial of Cable in the Ground and
Trenches, Cable Preparation, Joint and Termination, Pre-Commissioning Tests,
Ground Testing by Megger, Continuity Tests and Phase Rotation Tests are discussed.
263
OBJECTIVES
Upon completion of this unit the participants should be able to familiarize with :
∑ Layout and single line electrical diagrams.
∑ Block diagrams.
∑ Schematic diagrams.
∑ Switching to transfer load.
∑ Switching to energize isolated circuits.
∑ Switching apparatus with remote operation facilities.
∑ Hold tag and lockout procedures.
∑ Grounding and safety procedures.
∑ Transmission and Distribution Lineman Duties .
Hazards, Materials, Equipment and Tools Identification, Work Procedures and
Safety Precautions
∑ Transmission and Distribution Cableman Duties .
Cable Receiving, Safety Aspects and Work Procedures, Work Site Preparation,
Direct Burial of Cable in the Ground and Trenches Cable Preparation, Joint and
Termination
∑ Cable Splicing
∑ Pre-Commissioning Tests
Ground Testing by Megger, Continuity Tests, Phase Rotation Tests
264
LESSON 5.1
ELECTRICAL DIAGRAMS
265
266
LESSON 5.1
ELECTRICAL DIAGRAMS
LESSON OVERVIEW
DESCRIPTION
This lesson describes the layout and single line electrical diagrams, including Block
diagrams and Schematic diagrams.
OBJECTIVES
267
268
INTRODUCTION
Before we read and correctly interpret the electrical diagrams, we will define the
different types of the electrical diagrams as follows:
∑ Block diagrams represent all electrical network equipment as blocks to show
power flow.
∑ Single line or one line diagrams are shown by single lines and graphic symbols.
∑ Schematic diagrams are the basic reference for control circuits and electricians
use them to understand the operation of control circuits. Schematic diagrams are
made of standard symbols, function numbers and lines.
BLOCK DIAGRAMS
Block Diagrams represent all electrical equipment as rectangular functional blocks
with text interconnected by arrowed lines, the arrows indicating the signal flow.
They do not use standard symbols or abbreviations. The purpose of the block
diagrams is to:
∑ Show the flow of power through a system/equipment in one or more stages
of functional blocks.
∑ Understand the system operation.
As the system equipment gets complicated, its drawing gets simpler. This is because
it will be drawn as stage-by-stage block diagram. In troubleshooting, the electrician
will just measure and compare the output of each stage. Any faults may exist where
it deviates from normal.
269
270
As shown in Fig. 5.1-2, single line diagrams can also be used to show how meters
(Ammeters/Voltmeters) or protective devices (fuses) are connected to the system.
Along with identifying the components of the system, single line diagrams usually
include additional information, such as:
1. The major components, switching devices and connecting circuits in a sys tem.
2. Ratings of the major components (Ring Switches, 400 A).
3. Voltage level at various points in the circuit (13.8-231/133 kV).
4. Control functions provided in the circuit.
5. The path or power flow in a plant or a system.
6. The specifications and types of each equipment used (voltage level, CB
rating, transformer capacity, vector group etc)
271
control circuitry. It doesn't show the control of power equipment. These diagrams
are usually done for substations. Fig. 5.1-4(a) shows three line diagrams for a LV
distribution cabinet. It shows the details of:
∑ Voltmeter and Ammeter connections .
∑ Protective devices (fuses).
∑ Instrument Transformers (CTs) .
SCHEMATIC DIAGRAMS
Schematic diagram in Fig. 5.1-5, also called "Elementary Diagrams", like the other
electrical diagrams, are made of symbols and lines.
272
A schematic diagram (often called schematic) shows all the components in a circuit
and how each component is electrically connected, but not necessarily in their
proper physical locations. It also shows how the circuit is designed to operate. Fig.
5.1-5 is the "power circuit" of a "motor control circuit", identifying the components
in the circuits as follows:
1. Motor 2. Circuit breakers 3. Starter contactors (Magnetic starter)
4. Fuses 5. Overload protection 6. Magnetic protection (short circuits)
The dotted line at the circuit breaker indicates that the 3 breaking mechanism are
ganged and they move together.
∑ The symbols represent the power source, components and the devices of the
circuits.
∑ The function numbers and abbreviations represent type of switch, relay or device.
∑ The lines represent the conductors connecting the devices.
Schematics are usually designed to be read from left to right and from top to bottom.
They typically use standard electrical diagram symbols and device function
numbers. The position of the contacts and switches are shown as they would be in
the de-energized state.
The electrician should determine the following conditions from the catalog or from
the notes on the drawing :
∑ The initial conditions at which the diagram is drawn.
∑ The normal conditions at which the system will operate.
∑ The stop/trip con ditions.
EXAMPLE 5.1-1
In the single line diagram for electrical network in Fig. 5.1-6:
∑ Unit 1 feeds bus bar A ∑ Unit 2 feeds bus bar B
∑ Unit 3 feeds bus bar C ∑ Unit 4 feeds bus bar D
∑ Bus Tie 1 disconnected ∑ Bus Tie 2 disconnected
∑ Bus coupler 1 connected ∑ Bus coupler 2 connected
273
SOLUTION
a) The electrical network is divided into two sections (left and right) because bus tie
1 & 2 are disconnected .
Left Section U1 + U2 = 60 + 60 = 120 MW
F1 + F2 + F3 = 40 +50 + 50 = 140 MW
The generated MW from U1 and U2 is not enough (20 MW lost) to feed
the feeders F1, F2 and F3
Transformer T1 will receive 20 MW from 230 kV network to balance the
network.
Right Section U3 + U4 = 60 + 60 = 120 MW
F4 + F5 + F6 = 50 + 50+ 10 = 110 MW
The generated MW from U3 and U4 is more than required (10 MW
more) for feeders F1, F2 and F3.
Transformer T2 will send 10 MW from 69 kV network to 230 kV
network to balance the network.
274
b) If Bus Tie 1 is connec ted, all the network connected together (no sections) and the
transformers T1 and T2 will divide their loads together .
U1 + U2 + U3 +U4 = 60 + 60 + 60 + 60 = 240 MW
F1 + F2 + F3 + F4 + F5 + F6 = 40 +50 + 50 + 50 + 50 +10 = 250 MW
The generated MW from U1, U2, U3 and U4 is not enough (10 MW lost) to feed
the feeders F1, F2, F3, F4, F5 and F6.
So, Transformers T1& T2 will divide their load and receive 5 MW for each from
230 kV network to balance the network.
SUMMARY
∑ Block diagrams represent all electrical network equipment as blocks to show
power flow.
∑ Single line or one line diagrams are shown by single lines and graphic symbols.
∑ Schematic diagrams are the basic reference for control circuits and electricians
use them to understand the operation of control circuits.
∑ Schematic diagrams are made of standard symbols, function numbers,
abbreviations and lines.
GLOSSARY
UPS: Uninterruptible Power Supply LV: Low Voltage
275
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
276
REVIEW EXERCISE
1. The block diagrams with symbols facilitate troubleshooting be measuring input
and output signals.
a) True b) False
Fig. 5.1-7
277
278
TASK 5.1-1
ISOLATING POWER TRANSFORMER (T-703) 230 /69 kV
OBJECTIVES
1. Practice and follow switching procedures.
2. Practice and follow grounding procedures.
3. Write switching rep orts.
SAFETY PRECAUTIONS
1. Wear required safety equipment .
2. Follow the trainer's directions.
PROCEDURE
1. Study steps of the performance sheet.
2. Receive from your instructor single line diagram for transformer in Fig. 5.1-8
& 5.1-9.
3. Check transformer (T-703) that must be isolated for repair .
4. Check transformers (T-701), (T-702) in normal service.
5. 69 kV oil CB A 524 (refer to the single line diagram attached) must be opened
and tagged.
6. 230 kV SF6 (A703) for transformer (T-703) must be opened and tagged .
7. Disconnect switch (D707) must be in open position and tagged .
8. Disconnect switch (D708) must be in open position and tagged .
9. Disconnect switch (809) must be in open position and tagged.
10. PT on 230 kV side, secondary coil must be opened and tagged.
11. Disconnect (D548) must be in open position .
279
280
NOTE
Now transformer (T -703 ) is isolated and ready for repair .
281
282
LESSON 5.2
SWITCHING ACTIVITIES
283
284
LESSON 5.2
SWITCHING ACTIVITIES
LESSON OVERVIEW
DESCRIPTION
This lesson explains the switching activities including switching to transfer load,
switching to energize isolated circuits, switching apparatus with remote operation
facilities as well as hold tag and lockout , grounding and safety procedures.
OBJECTIVES
Upon completion of this lesson, the parti cipants should be familiar ized with:
∑ Switching to transfer load.
∑ Switching to energize isolated circuits.
∑ Switching apparatus with remote operation facilities.
∑ Hold tag and lockout procedures.
∑ Grounding and safety procedures.
285
286
INTRODUCTION
Switching activities are the responsibility of the network operator with coordination
of the power dispatcher to isolate or energize a piece of electric equipment safely
whenever maintenance or repair is required or completed after fault removal.
SWITCHING PROCEDURE
a. All transmitted switching orders used in conn ection with switching at a station
shall be written in an approved form, as shown in Table 5.2-1.
b. When issuing switching orders, the power dispatcher shall state in detail and in
proper sequence the switching to be performed and shall require the person
taking the order to repeat the order word for word.
c. Network Operator shall not execute more than steps of a switching operation
than has been ordered by the dispatcher.
d. All switching shall be performed by an authorized person and in detail and
seque nce as ordered by the issuing dispatcher.
e. If for any reason the Network Operator is delayed in executing a switching
order, he shall not perform the order but contact power dispatch control
center, which issued the order for instructions.
287
The order in which a switching program is carried out to isolate circuits, line or
equipment should be , as shown in Table 5.2-2:
288
6. Adjust the voltage at the original locations and set the tap changers to
automatic that was previously set to t he manual mode.
7. Check the load at both sources to confirm that the original forecast of load
transfer is correct.
289
The purpose of Lockouts and Hold Tags is to make sure that the controller
remains open while work is being done on any system and to protect the
personnel workin g on the portion of the system being protected by the controller.
GROUNDING
A ground system consists of grounding conductors connected together at all times
to ground electrode contacts. The electrode makes contact with the earth and
consists of buried conductors and ground wells with certain specifications. The
grounding systems serve four main functions:
1. To safeguard a person from electric shock under fault conditions; all surfaces
remain at safe condition contacting the ground.
2. To safeguard electri cal equipment
by grounding power systems.3.
To provide a path to ground from
lightning arresters that may operate
under conditions of direct lightning
strike, surges induced by lightning
or switching surges.
4. To reduce the possibility of static
discharge and hence fire risk for
grounding performed by earthing
switches and connected at definite
Fig. 5.2-1 Earthing Switches connected
points on the circuit, as shown in at definite Points on Circuit
Fig. 5.2 -1.
When high-voltage equipment is to be discharged and grounded, it is done by a
special ground switch or approved device to make ground connection. Where this is
not possible, the high -voltage equipment may be discharged by a working ground lead
applied by an approved device.
No high-voltage ground switch will be closed to the transmission or distribution
system unless it is part of an approved switching operation and is approved by the
Power Dispatcher or after the switching program has been approved by the Network
Foreman/Supervisor.
290
EXAMPLE 5.2-1
In the single line diagram for electrical network in Fig. 5.2-2
∑ Unit 1 feeds bus bar A ∑ Unit 2 feeds bus bar B
∑ Unit 3 feeds bus bar C ∑ Unit 4 feeds bus bar D
∑ Bus Tie 1 disconnected ∑ Bus Tie 2 disconnected
∑ Bus coupler 1 connected ∑ Bus coupler 2 connected
a) What is the load of transformers T 1 and T2?
b) What is the load of transformers T 1 and T2 if Bus Tie 1 is connected ?
c) If Bus Tie 1 is connected and the feeder F 6 disconnected , what is the load of T 1
and T2?
d) If Bus Tie 1 is connected and the unit 1 is tripped, what is the load of T 1 and
T2?
291
SOLUTION
a) The electrical network is divided into two sections ( left and right) because bus tie
1 & 2 are disconnected .
U1 + U2 = 60 + 60 = 120 MW
Left section F1 + F2 + F3 = 40 +50 + 50 = 140 MW
The generated MW from U 1 and U2 is not enough (20 MW lost)
to feed the feeders F 1, F2 and F3
Transformer T 1 will receive 20 MW from 230 kV network to
balance the network.
U3 + U4 = 60 + 60 = 120 MW
Right section F4 + F5 + F6 = 50 + 50+ 10 = 110 MW
The generated MW from U 3 and U4 is more than required (10
MW more) for feeders F1, F2 and F3
Transformer T 2 will send 10 MW from 69 kV network to 230 kV
network to balance the network.
b) If bus tie 1 is connected to all network connected together (no sections) and the
transformers T1 and T2 will divide their loads together :
U1 + U2 + U3 +U4 = 60 + 60 + 60 + 60 = 240 MW
F1 + F2 + F3 + F4 + F5 + F6 = 40 +50 + 50 + 50 + 50 +10 = 250 MW
The generated MW from U1, U2, U3 and U4 is not enough (10 MW lost) to feed
the feeders F1, F2, F3, F4, F5 and F6.
So, Transformers T1& T2 will divide their load and receive 5 MW for each from
230 kV network to balance the network.
292
SUMMARY
∑ Switching activities are the responsibility of the network operator with
coordination of the power dispatcher.
∑ When issuing switching orders, the power dispatcher shall state in detail and in
proper sequence the switching to be performed and shall require the person
taking the order to repeat the order word for word.
∑ Network Operator shall not execute more than steps of a switching operation
than has been ordered by the dispatcher.
∑ A ground system consists of grounding conduc tors connected together at all
times to ground electrode contacts.
∑ No high-voltage ground switch will be closed to the transmission or distribution
system unless it is part of an approved switching operation and is approved by the
Power Dispatcher or after the switching program has been approved by the
Network Foreman/Supervisor .
GLOSSARY
kV: Kilo-Volt kW: Kilo-Watt
T: Transformer
293
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
294
REVIEW EXERCISE
1. Switching purpose is to ________ or __________ a piece of electric equipment
safely whenever ______________ or __________ is required or completed after
fault removal.
3. List the five orderly steps in which a switching program is carried out to
isolate circuits, line or equipment.
4. The purpose of Lockouts and Hold Tags is to make sure that the controller
remains open while work is being done on any system and to protect the
personnel working on the portion of the system being protected by the
controller.
a) True b) False
295
296
TASK 5.2-1
ENERGIZING POWER TRANSFORMER (T-703) 230 /69 kV
OBJECTIVES
1. Practice and follow switching procedures.
2. Practice and follow grounding procedures.
3. Write switching reports.
SAFETY PRECAUTIONS
∑ Wear required safety equipment
∑ Follow the trainer's directions.
PROCEDURE
1. Study steps of the performance sheet.
2. Receive from your instructor single line diagram for transformer, Fig. 5.2-4 and
5.2-5.
3. Ground switch (K711) for transformer (T 703 ) must be opened and tag
removed.
4. Ground switch (K528) for transformer (T 703 ) must be opened and tag
removed.
5. PT (on 69kV side ) secondary coil must be closed and tag removed .
6. PT (on 230 kV side ) secondary coil must be closed and tag removed .
7. OCB (A524 ) must be checked open .
8. Disconnect (D548) must be opened .
9. Disconnect (D547 ) must be closed and tag removed.
10. GCB (A703 ) and Disconnect (D707 ) must be checked open .
11. Disconnect (D709 ) and Disconnect (D707) must be checked open .
297
298
299
300
LESSON 5.3
301
302
LESSON 5.3
LINEMAN AND CABLEMAN ACTIVITIES
LESSON OVERVIEW
DESCRIPTION
In this lesson, Lineman Craft Pole and Tower (Materials, Equipment and Tools),
Work Safety Precautions and Procedures, OH Distribution Lines (13.8 kV and 34.5
kV) OH, Transmission Lines (69 kV, 115 kV, 230 kV and 380 kV), Steel Towers and
Hazards of Lineman Craft and Safety Equipment and Hot Sticks are discussed.
OBJECTIVES
303
304
INTRODUCTION
A lineman in SEC maintains and constructs OH Distribution and Transmission lines.
His duties require him to work on poles and towers as well as on ground surfaces.
Beside pole and tower climbing skills, the lineman must be knowledgeab le of rigging
and lifting techniques, materials, work procedures and safety precautions necessary
for performing a job. A lineman uses specialized tools and equipment in his daily
activities and follows specific procedures to handle SEC standard tools and materials.
Switchyards are the places where a transmission line terminates into buses as
outgoing or incoming lines or equipment bushing. The following figures show
examples of poles and transmission tower structures, as shown in Fig. 5.3-1 and Fig.
5.3-2.
305
306
307
308
Fig. 5.3-4 Rigging and Lifting Fig. 5.3-5 Rigging and Lifting
309
310
Hot sticks, as shown in Fig. 5.3-9, are used for checking voltage by a MV buzzer
tester and to install temporary ground. It is an important safety aspect to install
temporary ground first to a buried ground rod, then to the line and when removing
temporary ground, a reversed sequence of de-installation is followed.
311
LINE EQUIPMENT
Besides conductors, insulators, guy wires (to support poles against conductor
tension) hardware bolts, nuts, brackets, poles and tower structures, OH distribution
poles can be used for mounting Pole Mounted Transformers (PMT), current and
potential transformers, CTs and PTs, voltage regulator, capacitors, disconnects and
air load breaks, OH Transmission line insulators, lightning arrestors, buses,
bushings in switchyards etc. The Fig. 5.3-10 shows CTs and PTs mounted on an
MV metering pole as examples of this equipment.
312
Fig. 5.3-11 shows a Pole Mounted Transformers (PMT) , which are used to supply LV
network in OH line areas. In this type of substation, the high tension is supplied to the
transformers by overhead lines. Fig. 5.3-12 shows Platform Mounted Transformers.
Here the high tension is supplied to the transformer either by overhead lines or by
underground cables through a pad mounted Ring Main Unit (RMU).
313
Fig. 5.3-11 PMT Fig. 5.3-12 RMU
The primary purpose for each class is to isolate equipment for maintenance.
AIR SWITCHES
All air switches are either air break or disconnect devices and are helpful in opening
unloaded circuits. All air switches are mounted on insulators that are parts of the
switch. The higher the rated voltage, taller is the stack of insulators. Either class of air
switches is often installed on both sides of a transformer or other substation
equipment, primarily to isolate the equipment for maintenance. Any of these switches
can be used as single phase modules or set up as GANG OPERATED three-phase
units, as shown in Fig. 5.3-13.
314
Although air switches can often be hot stick operated, they are frequently opened and
closed by an operating rod mounted on the structure. These switches are usually pole
mounted, but are also frequently mounted on steel or wooden substation structures
called racks.
Air switches provide positive, visible air gap isolation of equipment and line sections
for safe examination, maintenance and repair. In the closed position, air switches must
provide adequate capacity to handle all normal and abnormal curre nts, which flow in
the system. Most air switches are installed only for local manual operation.
Some switches open and close by vertical action but others operate by rotation in a
horizontal plane. The way and procedure of operation of air switches is a very
important part of the operation, maintenance and switching of substation equipment.
An air-break switch can open a circuit when only light current is flowing. The
airbrake switch will break the ARC in air by drawing the arc out until it is quenched ,
as shown in Fig. 5.3-14 .
315
Fig. 5.3-14 Arc Chute for Arc Quencher Fig. 5.3-15 Arching Horns
The air-break switch has no arc quencher, such as arc chambers or arc chutes to
extinguish the arc but works only by stretching and breaking the arc in the air, usi ng
the arc horn, as shown in Fig. 5.3-15. These switches will open a circuit when only
line charging current is flowing but should not be used when a circuit is under
overload or short circuit conditions. The air-break switch has both the SWITCH
BLADE and the stationary contact assembly equipped with ARCING HORNS. The
switch sets on insulator stacks, which set on a firm base, all of which are part of the
switch.
316
317
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
318
REVIEW EXERCISE
Complete The Following :
1. The following indicate s hazard source that can be eliminated simply by adherence
to proper safety on the job.
Following correct procedure of receiving _______________ line.
2. A lineman before starting any work must check for presence of voltage on a
_______________ line (induction effect from nearby parallel lines ) and install
temporary ground before starting any work directly on _______________ line for
equipment
319
320
LESSON 5.4
321
322
LESSON 5.4
CABLE SPLICING ACTIVITIES
LESSON OVERVIEW
DESCRIPTION
In this lesson, Cable Splicing Activities, mainly Cable Receiving, Safety Aspects,
Work Procedures, Work Site Preparation, Direct Burial of Cable in the Ground and
Trenches, Cable Preparation, Joint and Termination, Pre-Commissioning Tests,
Ground Testing by Megger, Continuity Tests and Phase Rotation Tests are discussed.
OBJECTIVES
323
324
INTRODUCTION
A distribution cableman joints and terminates 15, 34.5, 69 kV cables to equipment.
Also, the cableman must be capable of performing pre-commissioning tests,
meggering, continuity and phase rotation tests. Official receiving of a dead and spiked
cable from the network operation crew is a safety aspect for the cableman crew, which
must be performed with the highest sense of responsibility. A responsible cableman
must be able to :
1. Follow safe procedures as per SECstandards in carrying out maintenance and
repair job duties.
2. Read joint material kit manufacturer 's instructions for installation.
3. Make precise measurements.
4. Clean joint and prop erly apply heat to shrinkable materials.
Cableman tools, materials, safety aspects and work procedures as well as the
importance of high quality workmanship are required in making MV U/G cable joints
and terminations.
325
3. MV U/G CABLES
The standard MV U/G Cables are 3*300 mm2 and 3*70 mm2 consisting of:
a) Conductor, Aluminum
b) Conductor S heath, semiconductor to control electric stresses on insulation and
to prevent insulation ionization.
c) Insulation
d) Insulation sheath, semiconductor to control and evenly distribute electric
potential stresses inside the cable.
e) Protection screen copper ground s the outer surface of insulation.
f) Bedding to keep circular shape of the cable.
g) Armour to provide mechanical protection of the cable.
h) Outer jacket, PVC, to protect the internal constituent of the cable from
humidity, dust and acids.
326
327
5. CABLE INSTALLATION
MV U/G cables are installed by direct burial in the ground and in trenches, the depth
of the cable trench depending on the operating voltage of the cable. The following
Fig. 5.4-5 shows an LV U/Gcable trench with the required backfill layers and warning
tape.
The dimensions of U/G MV cable trenches are different than LV U/G cable trench
(depth and width), as shown in Fig. 5.4-6. The places for making splices (Splice Pit)
should be made with larger dimensions to enable a cableman to perform the joint on
MV cables. It is installed in the trench by pulling it over rollers placed in the trenc h to
prevent the outer jacket from being torn off .
Fig. 5.4-6
LV U/GCable Trench
328
The following Fig. 5.4-7 shows the operation of pulling MV cable in the trench (left
side) and the pull eye that clamps the cable end for pulling with straight and corner
rollers.
6. CABLEMAN TOOLS
The cableman tools can be classified into the following categories:
1) Common Hand Tools: Hammer, Screw Drivers, Saw, Scale
2) Specialized Hand Tools: Electrician's Knife, Scorning Knife, Semi -Con Removal
Tools, Compression Tool and Dies, Soldering Tools, Heat Shrinking Tools
Besides the hand tools, the cableman journey truck contains the tent, the first aid box
and a water cooler.
329
In SEC, however, the standard cable joint and terminati on material kits are Raychem
heat shrinkable for performing MV cable joints and termination. These material kits
consist of electric stress control insulation and outer tubes that shrink with applying
moderate heat flames onto the tube. Beside these tubes, the material kit includes
copper braid to join the ground screen for the two cables to be jointed with
semiconductor paint and masking tape to cover the connector between the two cables '
conductors. These connectors are not supplied as a part of the material kit.
330
TERMINATION
1. Cable Receiving
2. Work Site Preparation
3. Cable Preparation
4. Core Preparation
5. Soldering Copper Wire to Ground Screen
6. Inserting Stress Control Tube
7. Heat Shrinking Stress Tube ( Black)
8. Inserting Oversheath tube
9. Heat Shrinking Oversheath Tube ( Red)
10. Inserting Outbreak Tube
11. Heat Shrinking Gut break Tube ( Red)
12. Connector Compression
13. Install Outskirt Bells to Outdoor Termination
331
332
The following pre-commissioning test procedure is recommended for the New Plant:
a) Perform continuity, phase identification and insulation resistance test of cable
section ‘FB’ before terminating to the new RMU at ‘B’ as follows:
333
6. Repeat the same procedure for the other two phases ‘Phase Y’ and Phase ‘B’.
334
Fig. 5.4-9
b) Undertake continuity, phase identification and insulation resistance test of cable
section ’GD’ before terminating to the new RMU at ’D’. The procedure is
repeated as per 8-3 (a) above for the cable Section ‘GD’ .
c) Cable sections ‘FB’ and ‘GD’ are then terminated to the new RMU at points ‘B’
and ‘D’ with reference to the identified phase designation or markings of the cable
and matching terminals of the RMU, respectively. It is essential that a consistent
marking system is used.
d) Carry out pre-commissioning test for the ground mounted transformer .
335
e) Based on the scheduled shutdown program, Operation Unit should carry out the
necessary switching procedures to isolate the existing cable section ‘AE’ and
applied grounds at points ‘A’ and ’E’ as per SEC standard practice.
f) Cable identification and spiking of cable section ‘AE’ at site ‘F/G’ and splicing to
the new cable sections.
Connection points ‘F’ and ‘G’ are coincident, as referred to Fig. 5.4-9(a), the
procedure is as follows:
∑ The cable section ‘AE’ must be identified, tagged and spiked at the work location
‘F/G’ prior to cutting the cable and proceeding with the required work.
∑ Before cutting single core cables, both sides of each core of the cable from the
point to be cut must be designated and tagged for proper identification.
∑ After cutting the cable section ‘AE’ at site ‘F/G’, the new cables are spliced
maintaining the same known and identified phase connections for both the loop -
in and loop -out cables.
∑ Connection points ‘F’ a nd ‘G’ are non -coincident at two distinct locations along
the circuit cable.
336
∑ After cutting cable section ‘AE’ at site ‘F’ and ‘G’ must
be checked for
consistency of phase identities as outlined in section 8.1.
∑ The new loop -in and loop -out cable section of the new S/S are then spliced
maintaining the same known and identified phase designations at points ‘F’
and ‘G’.
8.4 PRE-COMMISSIONING TEST PROCEDURE FOR COMPLETED
PLANT (NETWORK)
It is necessary that proper phasing should be consistently maintained for all
connections on the completed installation. The following pre-commissioning phase
test methods are recommended. It can be used for identification of phases on a
completed installation.
337
5. If the phasing test results obtained are consistent with the established phase
identification at point ‘A’ and ‘E’, then phase matching is correct and acceptable.
If not, Construction Work Unit should remake terminations at ‘B’ and/or ‘D’ as
dictated by the phasing results.
The above procedure is repeated to confirm the corrected phasing.
TEST PROCEDURE
1. Open and ground switches ‘A’, ‘B’, ‘D’, ‘E’ and fused switch ‘C’.
2. Insert the appropriate test probes for the RMU at ‘B’ and ‘D’.
3. Remove grounds at switches ‘B’ and ‘D’; switching the RMU to ‘OFF’ position.
4. Remove all applied grounds (if any, except C) and close
switches ‘A’ and ‘E’.
5. Using a suitably rated phasing voltmeter, identify and confirm matching phases
across the RMU test probes at ‘B’ and ‘D’. Matched phases will indicate a zero
reading.
6. Open and ground switches ‘A’ and ‘E’ and also ground s witches ‘B’ and ‘D’.
7. Place tag to matching phases ‘R’, ‘Y’ and ‘B’ at points ‘B’ and ‘D’.
8. Remove the test probes at ‘B’ and ‘D’ and replace the relevant covers and
padlocks.
TEST RESULTS
∑ If the tagged phases R, Y and B at switch ‘B’ are electrically direct ly opposite the
phase R, Y and B at switch ‘D’, then phase matching is correct and acceptable.
The completed installation is ready for commissioning.
∑ If the tagged phases are found not correctly positioned, it is necessary that
Construction Work Unit should remake the terminations at ‘B’ and/or ‘D’ to
provide proper phase matching.
338
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
____________________________________________________________________ _
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
339
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
340
REVIEW EXERCISE
1. Complete the following:
i) Upon completion of the Megger or MV DC test on any phase of the cable
or equipment, the phase terminals must be_________ prior to
disconnecting the test leads and proceeding to test on the other phases.
ii) Due to the absorption effect associated with MV testing, which can cause
dangerous voltage to remain on the cable conductor long after the test has
been completed, it is necessary that the conductor should be adequately
_________ for a considerable time for at l east 4 times as long as the
duration of the test voltage application .
3. MV U/G cables are installed by direct burial in the ground and in trenches with the
depth of the cable trench depending on the operating voltage of the cable.
What are the dimensions of U/G MV LV U/Gcable trenches for one cable as per
SEC standard?
4. Considering the time limitation for the scheduled shutdown to the distribution
network, Construction Work Unit should complete the preliminary cable
preparations and pre-commissioning tests required for the new cable sections,
switchgear and transformer prior to the shutdown and their connection to the
existing network. List these pre-commissioning tests?
341
ENGINEERS' COURSE
342