RENCANA ANGGARAN BIAYA PERENCAAN

No Uraian Pekerjaan Volume Satuan Harga Satuan Total Harga Keterangan

A. Operasional
1 Sewa Mobil 10 Hari 300,000.00 3,000,000.00
2 Sewa Rumah 25 Hari 150,000.00 3,750,000.00
Sub Total A 6,750,000.00

B. Peralatan
1 Komputer 2 Buah 2,000,000.00 4,000,000.00
2 Printer 1 Buah 1,000,000.00 1,000,000.00
Sub Total B 5,000,000.00

C. Tenaga Ahli
1 Project engineer 1 ha 7,000,000.00 7,000,000.00
2 Project arsitek 1 ha 7,000,000.00 7,000,000.00
3 Drafter 1 org 3,000,000.00 3,000,000.00
Sub Total C 17,000,000.00

Total Harga 28,750,000.00