SKEMA JARINGAN D.I.

ENO KECAMATAN SEKO KABUPATEN LUWU UTARA

BE.1Ka.1Ki
BE.4Kc.1 Ka 15,00 Ha 34,73 lt/dt
60,00 Ha 139 lt/dt
BE.1Ka.1Ki
BE.3Kc.1 Ka BE.3f. Ka BE.3c.Ka 9,00 Ha 20,82 lt/dt
BE.4Ka.1 Ki 15,00 Ha 34,71 lt/dt 28,00 Ha 64,82 lt/dt 15,00 Ha 34,72 lt/dt
26,00 Ha 60,20 lt/dt BE.2.Ka
BE.3g. Ka BE.3e. Ka BE.3b.Ka 18,00 Ha 41,67 lt/dt

L=208m
35,00 Ha 81,01 lt/dt 15,00 Ha 34,73 lt/dt 21,00 Ha 48,60 lt/dt
L=231

BE.4Te.1 Ki
8,00 Ha 18,52 lt/dt 1850,00 875,00 985,00 575,00 450,00 448,00 215,00 508,00 594,00
BE. 4 BE.3Kc.1 Ka BE.3g. Ka BE.3f. Ka BE.3e. Ka BE.3c.Ka BE. 3b BE.2 BE. 1
6500,00 4650,00 3775,00 2790,00 2215,00 1765,00 1317,00 1102,00 594,00
BENDUNG D.I. ENO

Bangunan Utama (BU)


A = 265,00 Ha
Q = 0,613 M³/Dtk
L = 6.500,00 Meter

KETERANGAN GAMBAR

Bangunan Bagi Lining

Bangunan Sadap Talang

Bangunan Bagi Sadap Jembatan