Professional Documents
Culture Documents
Rev.
ANRD-INF-MFC-CS-7403-0001
001
Safe Excavation & Trenching Procedure BOC-1962 Ancillary Roads and Infrastructure
Revision History
Revision
Revision Approver Summary of
Number
Date Changes
30-Oct-23 001 Monthir First submission
Holds
Hold Description / Reason for Ref. Section
Ref. Hold
HOLD 1
HOLD 2
HOLD 3
Reference Documents
Ref Document Number Rev Document
. . Title
1 5.0 BOC-1962 Section V - Scope Rev - Scope of Work
of Work 2
CONTENTS
1 PURPOSE ................................................................................................................................5
2 SCOPE .....................................................................................................................................5
3 REFERENCE DOCUMENTS ...................................................................................................5
4 DEFINITIONS & ABBREVIATIONS .........................................................................................5
4.1 Definitions .............................................................................................................................................. 5
4.2 Abbreviations ......................................................................................................................................... 7
5 RESPONSIBILITIES ................................................................................................................8
5.1 CONTRACTOR Construction Manager ................................................................................................ 8
5.2 CONTRACTOR Competent Excavation Person .................................................................................. 8
5.3 CONTRACTOR Department Managers ................................................................................................ 8
5.4 Performing Authority/Subcontractor ................................................................................................... 8
5.5 CONTRACTOR HSE Manager ............................................................................................................... 8
5.6 CONTRACTOR SHE Supervisors ......................................................................................................... 8
6 PROCEDURE ...........................................................................................................................9
6.1 Task Preparation.................................................................................................................................... 9
6.2 Excavation Design Approvals ............................................................................................................ 11
6.3 Soil Classification ................................................................................................................................ 12
6.4 Soil Mechanics ..................................................................................................................................... 12
6.5 Stability and Protection ....................................................................................................................... 14
6.6 Road Closures ..................................................................................................................................... 16
6.7 Initial and Daily Inspection of Excavations ....................................................................................... 16
6.8 Access and Egress .............................................................................................................................. 16
6.9 Crossings ............................................................................................................................................. 17
6.10 Equipment ......................................................................................................................................... 17
6.11 Edge Protection ................................................................................................................................ 17
6.12 Excavation Spoils............................................................................................................................. 18
6.13 Undermining ..................................................................................................................................... 18
6.14 Dewatering ........................................................................................................................................ 18
6.15 Emergency Response ...................................................................................................................... 18
6.16 Vibrations or Superimposed Loads................................................................................................ 18
7 TRAINING ..............................................................................................................................19
8 RECORDS ..............................................................................................................................19
9 LIFE-SAVING RULES ............................................................................................................19
1 PURPOSE
The purpose of this document is to establish essential requirements and controls to ensure that
excavation works carried out within the project site do not cause harm to persons carrying out the
excavation or working within the excavation and do not cause damage to buried services, pipelines,
properties or the environment.
2 SCOPE
This procedure covers all excavations and trenches that will be carried out at the project site.
Excavation works carried out within any existing area (e.g. brown field area where the Client has
care, custody and control) would be regulated and managed in accordance with the relevant Client
requirements, unless, agreed otherwise.
3 REFERENCE DOCUMENTS
4.1 Definitions
The following definitions shall be applied for this project.
Agent Any substance, force, organism or influence that affects the body, a part of
the body, or any of its functions. The effects may be beneficial or harmful.
ALARP ALARP stands for "as low as reasonably practicable", and is a term often
used in the regulation and management of safety-critical and safety-involved
systems. The ALARP principle is that the residual risk shall be reduced as
low as reasonably practicable.
Confined Space An area is a confined space if the space is not intended for continuous human
occupancy or is restricted to only one access way. To be considered a
confined space, such areas would also typically have poor or no ventilation
and there would be a high probability that oxygen levels would be low, and
that dusts, vapors or gases would be present.
Contractor Madar Alfayaa Company.
Employer BOC/KBR
Excavation All work which breaks the ground surface and extends below it except for
designated garden areas where the depth of excavation does not exceed
200mm. This includes digging by both manual and mechanical means.
Greenfield A new Project development requiring new facilities and where no previous
infrastructure exists.
Performing Authority The performing authority is the party which holds the permit of a task that
requires obtaining a ‘Permit to Work’ prior to commencement of the work.
This party is usually the direct Supervisor of the task.
Permit to Work A formal written system used to control certain types of work which are
identified as hazardous.
4.2 Abbreviations
Abbreviations and some terms used in this document are SHE and industry specific. To ensure all
personnel involved in, and responsible for, the implementation and application of the SHE MS have
the same understanding, all abbreviations and specific terms used in this document are defined in
this section.
5 RESPONSIBILITIES
condition.
6 PROCEDURE
CONTRACTOR Civil Department shall provide updated copies of all underground facility drawings
to CONTRACTOR PTW Office in a timely manner for the processing of excavationPTWs.
6.1.2 Worksite Visit
Prior to the application of a PTW for excavation, the Performing Authority, Issuing Authority and
CONTRACTOR competent excavation person shall carry out a field check to determine the presence
of any underground utilities or adjacent existing structures which may have an adverse impact to the
planned excavation works.
All underground utilities shall be located by reference to existing drawings, discussion with the
responsible discipline, and by use of underground electrical cable detector which can detect live and
isolated cables. Underground utilities which are located within the area of the proposed excavation
or within 2m of the proposed excavation or located parallel to the proposed excavation, where there
exists a danger of accidental contact or disturbance, shall be clearly and prominently marked using
flags, pegs, chalks etc. The perimeter of the proposed excavation area shall also be physically
marked at site with distinguishable markings.
In addition, CONTRACTOR competent excavation person shall examine the work area to determine
that no recognizable conditions exist that would expose employees to injury before work is permitted
in or adjacent to excavations.
6.1.3 Confined Space
All excavation and trenches deeper than 1.2 meters shall be classed as a confined space, unless a
confined space risk assessment is carried out to determine otherwise. Entry into confined space
designated excavations and trenches requires, in addition to the excavation permit, a confined space
entry permit. Deep excavations that are confined spaces shall be managed in accordance with the
requirements of the CONTRACTOR Confined Space Entry Procedure.
6.1.4 Trial Excavations
All identified underground utilities identified during the worksite visit shall be subjected to a trial
excavation to physically expose the underground utilities. The depth of the trial excavation is typically
about 1m and dependent on the kind of utilities and information of depth. All trial excavations shall
be carried out using manual hand tools only. When underground utilities are uncovered, adequate
protection and support shall be provided for the existing installation.
6.1.5 Notification
All responsible disciplines owning underground utility lines shall be notified by the Task Supervisor
and advised of the proposed work at least 48 hours prior to the start of the actual excavation works.
Emergency repair works to underground utilities are possible, but every means shall be taken to
mitigate the risks to as low as reasonably practicable (ALARP). Hence, emergency repair works are
exempted from this notification requirement.
• If any shoring components will remain after filling or backfilling (if applicable).
• Sequence and method of shoring installation and removal (if applicable).
All excavation designs shall be submitted to CONTRACTOR Civil Department for their reviewand final
approval before field works may commence.
6.4.2 Sliding
Sliding or sluffing may occur as a result of tension cracks, as illustrated below.
6.4.3 Toppling
In addition to sliding, tension cracks can cause toppling. Toppling occurs when the trench’s vertical
face shears along the tension crack line and topples into the excavation.
6.4.6 Boiling
Boiling is evidenced by an upward flow into the bottom of the cut. A high-water table is one of the
causes of boiling. Boiling produces a ‘quick’ condition in the bottom of the cut and can occur even
when shoring or trench boxes are used.
The dimensions and spacing of the elements of the shoring system area are governed by the depth
of the trench, type of soil encountered and other special conditions of the site, but in no case, provide
less strength than the number of members which the CONTRACTOR competent excavation person
considers to be the minimum required to safely shore the excavation.
6.5.3 Excavation Boxes and Trench Shields
A portable excavation box or trench shield may be used for the protection of employees instead of
shoring, benching or sloping. All excavation boxes and trench shield shall be designed, constructed
and maintained to provide protection equal to or greater than the required shoring, sloping or
benching requirement. The design for custom made excavation boxes or trench shield shall be
reviewed and approved by a qualified CONTRACTOR Civil Engineer before use.
Excavation boxes and trench shield shall be installed in accordance with the manufacturer’s
recommendations and to restrict lateral or other movement of the box or trench shield. Excavation
boxes and trench shields shall be capable of withstanding any sudden application of lateral loads. In
line with OSHA guidelines, excavation boxes or trench shields shall be extended a minimum of 0.45m
(18”) above the excavation. The images 2-4 below are examples of trench shields commonly used.
In excavations or trenches of 1.2 meters in depth or more, a safe means of access/egress shall be
provided which would require no more than 10 meters of lateral travel distance. Ladders used in an
excavation shall rest on the bottom of the excavation on a firm footing and extend at least 1 meter
above the top of the landing point for good handhold.
6.9 Crossings
Surface crossings of trenches or excavations shall be discouraged. However, if trenches or
excavations must be crossed, such crossings are permitted only under the following conditions:
• Vehicles Crossings – Shall be designed by and installed under the supervision of a registered
professional engineer or an engineer of equivalent competency.
• Walkways or bridges provided for pedestrians and utilities over a trench or excavation shall;
o Have a minimum clear width of 1 meter.
o Be fitted with standard guardrails, mid-rails and toe boards and extend a minimum of 1
meter past the surface edge of the trench or excavation.
o Be of sufficient strength for the intended load.
o Have protection for any utilities being taken across it.
Walkways or bridges constructed with scaffolding materials shall fully comply with the requirements
specified in the Scaffold Procedure.
6.10 Equipment
All excavation equipment shall be inspected and approved for use on site in accordance with the
project’s Plant & Equipment Inspection and Maintenance Procedure.
Any employee working near operating equipment shall take such measures to ensure that they will
not be crushed by such equipment and its moving parts. Employees shall be kept away from the
working slew radius of a mechanical excavator (line of fire) except the nominated banksman who
shall be visible to and in contact with the machine operator. The banksman, who shall wear a high
visibility vest, shall monitor all mechanical excavations and enforce the necessary safety
requirements around the excavation.
All heavy equipment shall be kept a minimum of two (2) meters away from the edge of an excavation.
Wheel chocks shall be placed on any wheeled vehicle parked or working near to an excavation.
protected against collapse by a shoring system designed and approved by a registered professional
engineer or an engineer of equivalent competency.
6.13 Undermining
No excavation works shall take place below the level of an adjacent foundation, retaining wall,
scaffold base/supports, structure or existing structure.
Undermined sidewalks shall be supported to safely carry all anticipated loads. If the stability of
adjoining buildings or walls is compromised by excavations, either shoring, bracing, underpinning or
some other method affording equivalent protection for employees shall be provided as necessary to
ensure their safety. All such systems shall be inspected daily or more often, as conditions warrant,
by CONTRACTOR competent excavation person. He shall also ensure that the protective measures
are effectively maintained.
6.14 Dewatering
Employees shall not work in excavations where there is accumulation of water. The necessary
controls vary with each situation, but shall include water removal (dewatering) to control the level of
accumulating water (e.g. by pumping) and may include support shields or shoring systems to protect
from cave-ins.
If water is controlled or prevented from accumulating using water removal equipment, the water
removal equipment and its operations shall be monitored by an attendant to verify proper operation.
Water shall be properly discharged at a safe location from the excavation to prevent re-entry. Refer
to CONTRACTOR Environmental Management Plan.
If excavation work interrupts the natural drainage of surface water, then diversion ditches, dikes or
other suitable means shall be used to prevent surface water from entering the excavation and to
provide adequate drainage of the area adjacent to the excavation. Excavations that have been
subject to runoff shall be inspected and verified safe by an excavation competent person before
works may resume.
7 TRAINING
All employees who will be engaged in excavation works shall be instructed by a competent person
from CONTRACTOR on the safe methods of excavation and working within an excavation asper the
contents of this procedure.
8 RECORDS
All documentation relevant to this procedure shall be kept in the CONTRACTOR SHE Department
for reference throughout the duration of the project. Such documents may include, but are not limited
to the following:
• Underground facility drawings.
• Excavation design approvals.
• SWMS/JSA for excavation works.
• Excavation PTW and confined space PTW for excavation.
• Initial and daily excavation inspection records.
• Excavation training records.
• Manufacturer data sheet for excavation boxes & trench shields.
9 LIFE-SAVING RULES
The Life Saving Rules (LSR), of which there are nine (9), are associated with high risk work activities
at site and are designed to help save life if followed. LSR are zero tolerance rules and the violation
of these rules will result in serious consequences, including removal from the project. All LSR relevant
to this procedure shall be strictly adhered to on the Project. The below describes the LSR and the
components of which they consist:
1. Bypassing safety controls:
• Obtain authorization before overriding or disabling safety controls, deviating from procedures,
or crossing any established barrier;
• Understand and use safety critical equipment and procedures which apply to the task.
2. Confined space:
• Obtain authorization before entering a confined space;
• Confirm that energy sources are isolated;
• Confirm that the atmosphere has been tested and will be monitored;
• Check and use breathing apparatus as required.;
• Confirm entry attendant is in place and standing by;
• Confirm rescue plan is in place.
3. Follow safe driving rules:
• Always wear a seat belt;
• Do not exceed the speed limit and reduce speed for uneven road conditions;
• Do not use or operate mobile phones or devices while driving;
10 ATTACHMENTS
Attachment 1 – Sloping, Benching and Shoring Guide
Attachment 2 – Initial/Daily Inspection Checklist
Stable Rock Natural solid mineral matter that can be excavated with vertical sides such as
sandstone.
Type B Less cohesive soil, such as mix of sand, rocks and clay
Type C Less cohesive soil. Examples are gravel, sand, muddy of freely seeping soils,
submerged rock that is not stable, or a layered system. Previously disturbed soil is
Type C soil.
Soil Type Maximum allowable slopes (H:V) for excavations less than 6m deep
Note: Numbers shown in parentheses next to maximum allowable slopes are angles expressed in degrees
from the horizontal. Angles have been rounded off.
Excavation Location
Excavations are safe if all the above questions can be answered “Yes” or “N/A.” “No” answers require
rectification of the deficiency prior to allowing people to enter the excavation.