% de avance Agosto Septiembre Octubre Noviembre Diciembre Enero Febrero Marzo
Project Activities Start Date Ending Date Duration Responsable
8.06% 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 1 2 3 4 5 6 7 8 9 11 11 12 13
STARTUP STAGE
OC 95708 8/26/2023 8/26/2023 0 AJEMAYA 100%
Contract Confirmation 9/11/2023 9/18/2023 7 AJEMAYA 100%
Down Payment- 50% 8/26/2023 9/5/2023 10 AJEMAYA 100%
Machine Layout Confirmation 8/31/2023 9/25/2023 25 AJEMAYA / FILLEX 100%
Pipeline Layout Confirmation 10/13/2023 11/18/2023 36 AJEMAYA / FILLEX 70%
Utility List Final (machine consumption specifications) 8/28/2023 11/18/2023 82 FILLEX 85%
Can and Lid Sample 9/22/2023 10/23/2023 31 AJEMAYA 100%
Label Dimension and Design 11/30/2023 45260 AJEMAYA 0%