TBM-1 (SHAKTI) Progress Beyond RTB Chainage 48180
A1 Shield Chainage 50307.25 Total excavtion by TBM-1 (in RM) 2128.40
Face Chainage 50308.40 in terms of Rings 1252 Inverts installed 1240
TBM-2 (SHIV) Progress Beyond RTB Chainage 878
A2 Shield Chainage 2094.05 Total excavtion by TBM-2 (in RM) 1217.20
Face Chainage 2095.20 in terms of Rings 716 Inverts installed 704
243
Conveyor belts: Commisioning Date Remarks
B TBM-1 (SHAKTI) 22.04.2023
09 rolls of 1m width belts, 500m each available at Portal 1 store for both TBMs
TBM-2 (SHIV) 08.06.2023

MSVs: Commisioning Date Remarks


MSV-1 17.01.2023
C MSV-2 15.01.2023
MSV-1 to 4 operational at site
MSV-3 20.04.2023
MSV-4 24.04.2023

Casting of Ring segments/Invert segment (Availability of parts for initial start-up of casting activities)
S.No. Item Scope Available Remarks
In % Date
Availability of Mould Sets 12 12 100%
1 Available 100% i.e. 12 sets recived
INVERT 12 12 100%
Total Required Total rings casted Total rings installed in tunnel Stock Available
D 2 Supply of gaskets Gasket for 2216 ring along with 13.1 ton adhesive is available
12,224 Rings 3253 1968
at site.

Segment rings casted FTW FTM Cumulative Available 3253 Ring casted & 2984 Invert Casted.
3 Factory-1 36 27 2144
Tentative target- 3496 rings by Aug 2023
Factory-2 41 29 1109 3253
(490 Rings for Aug 2023)
Invert 82 53 2984

Page 1 of 2
#Actionable points on TBM Commissioning and Excavation Dated: 18.08.2023

Availability of spares - Target


Remarks
S.No. % Date
E 1 As per desired list of items 100% Jan-23-W-4
These are through SLA with HK.
2 Disc Cutters (Total No. reqd:) TBM 1
1 set Received at Site
3 Disc Cutters (Total No. reqd:) TBM 2

Stacking of aggregates/raw materials vis-à-vis Total required


S.No. Material Required Available (Tons) Remarks
1 Aggregates 21920
2 Cement (at Portal 1) 750
F 3 Grout- 1 component (BENTONITE) 92
4 Grout- 2 component (SODIUM SILICATE) 100
5 Microfine cement 9.75
6 Collidal Silica 4.30
7 PU grout 1.6

G Availability of TBM consumable as per OEM List. Target Date = Dec-22 (Available for initial drive), remaining will be delivered at site as per consumption.