Professional Documents
Culture Documents
ON
"A DETAILED STUDY ON KTPS-VII STAGE 1X800MW
OVERVIEW"
A dissertation submitted in partial fulfilment of the requirement of the award of the
Mr B. RAGHUVEER
A.E./BM/KTPS- VII STAGE, PALONCHA
CERTIFICATE
This is to certify that Sri G. RAHUL VARMA (Roll No. : 21MEB0A22) Studying
B. Tech. 2nd-year MECHANICAL ENGINEERING at the NATIONAL
INSTITUTE OF TECHNOLOGY, WARANGAL, completed 30 days STUDY
PROJECT on “A DETAILED STUDY ON KTPS-VII STAGE 1X800MW
OVERVIEW” with a specific view on KTPS - VII Stage at PALONCHA during the
academic year 2022-2023.
CERTIFICATE
THIS IS TO CERTIFY THAT A 15 DAYS STUDY PROJECT ON
"A DETAILED STUDY ON KTPS-VII STAGE 1X800MW
OVERVIEW "
IS CARRIED OUT BY
G. RAHUL VARMA Roll No: 21MEB0A22
Internship by:
G. RAHUL VARMA
ABSTRACT
These days electrical energy plays an important role in every aspect of our day–to–day life. This
electrical energy can be generated from thermal, hydel, Nuclear as well as Gas power plants. To our
surprise, we came to know that 70% of the total electrical energy is generated from THERMAL
POWER PLANTS only.
In thermal plants, every object is having a vital role in electrical power generation. So, the
Thermal plant is to be protected carefully to ensure the availability of electrical energy without
interruption to every load connected to the system. So, precautions must be taken so that the
equipment not only operates as nearly as possible to peak efficiencies but also that it is protected from
accidents.
The object of our project gives an insight into an overall view of Thermal power plants and
power generation transmission and protection schemes of objects in thermal power plants.
CONTENTS
S.No. Chapter Name Pag
e
No.
1. Introduction to TS Generation
1.1 Profile of Kothagudem Thermal Power Station
1.2 Renovation and modernization activities
1.3 Stages of K.T.P.S
1.4 Overview and schematic view of Thermal Power Plant
2. PRINCIPLE OF OPERATION
2.1 Rankine cycle
2.2 Reheat cycle
2.3 Regenerate cycle
2.4 Coal to steam process
2.5 Steam to mechanical power
2.6 Mechanical power to electrical power
2.7 Electrical power to the transmission
3. BOILER
3.1 Introduction
3.2 Principle of combustion
3.3 Pressure paths
3.4 Types of Fans
3.5 Air Heaters
12. CONCLUSION
CHAPTER – 1
z
INTRODUCTION
1.1 INTRODUCTION TO THERMAL POWER PLANT:
Both the historical and the present-day civilizations of mankind are closely
interwoven with energy, and there is no reason to doubt that in the future our
existence will be more and more dependent upon energy. Electrical energy occupies
the top position in the energy hierarchy. It finds innumerable uses in the home,
industry, agriculture, and even in transport. Besides its use for domestic,
commercial and industrial purposes it is required for increasing defence and
agricultural production. In agriculture, it is used for pumping water for irrigation
and for improving the methods of production and numerous other operations.
Electrical energy is a convenient form of energy because it can be generated centrally
in bulk and transmitted economically over long distances and is almost pollution
free at the consumer level. Further, it can be adopted conveniently in the domestic,
industrial and agricultural fields. The process of modernization, increase in
productivity in industry and agriculture and improvement in the quality of life of the
people depend so much upon the supply of electrical energy that the annual per
capita consumption of electrical energy has emerged these days as an accepted
yardstick to measure the prosperity of the nation. Some of the advanced and
developed nations of North America and Europe have a very high annual per capita
consumption of electrical energy; say from 8 to 13 thousand kWh, while in most of
Africa, and America it is too low to be considered. India had an annual per capita
consumption of electrical energy of 15.5 kWh in 1950, 105 kWh in 1975, 131 kWh in
1979, 154 kWh in 1984, 299 kWh in 1993, and 349 kWh in 1997, The annual per
capita consumption of Japan 8,000 kWh, UK 7,200 kWh and USSR 6,000 kWh. The
United States has only 6% of the world's population but accounts for over 30% of the
electrical consumption of the world.
The industrial growth of a nation requires increased consumption of energy,
particularly electrical energy. This has led to an increase in the generation and
transmission facilities to meet the increased demand. In the U.S.A., till the early
seventies, the demand develops every ten years. In developing countries, like India,
the demand doubles every seven years which requires considerable investment in
the electrical power sector.
Coal-based thermal power stations are presently the mainstay of power
development a this is likely to be so in the immediate future also, considering the
present status of the projects and various constraints in the development of hydro
and nuclear power. Besides quantity, the quality of Indian coal has been a major
problem and concern for the power supply industry. With the ash content of coal
being in the range of 30-50%, the beneficiation of coal assumes special significance.
Advantages of thermal power plant:
● Low initial cost
● Since located near the load centre, the cost of transmission and the losses
due to transmission is considerably reduced.
● The construction and commissioning of a thermal power plant takes a lesser
period.
Disadvantages of thermal power plant:
● Fuel is a non-renewable source of energy.
● Efficiency decreases with decreasing load.
● Cost of power generation is high.
● Smoke produced by burning the fuel causes air pollution.
● Life of a thermal power plant is 25 years. The efficiency decreases to less
than 10% after its life period.
1. ABOUT TSGENCO:
Vision:
To be the best-performing power utility in the country, and one of the best utilities
in the world with the use of state-of-the-art technology and smart solutions.
Mission:
To generate adequate, reliable, cost-effective, and eco-friendly power by
spearheading accelerated power development through the proper planning and
implementation of new power projects.
Disadvantages
• It pollutes the atmosphere due to the production of large amounts of smoke
and fumes.
• It is costlier in running cost as compared to the hydroelectric plant.
3. Steam turbine. The dry and superheated steam from the superheater is fed
to the steam turbine through the main valve. The heat energy of steam when passing
over the blades of the turbine is converted into mechanical energy. After giving heat
energy to the turbine, the steam is exhausted to the condenser which condenses the
exhausted steam utilizing cold-water circulation.
5. Feed water. The condensate from the condenser is used as feed water to the
boiler. Some water may be lost in the cycle which is suitably made up from external
sources. The feed water on its way to the boiler is heated by water heaters and
economiser. This helps in raising the overall efficiency of the plant.
Conclusion. All the above factors cannot be favourable in one place. However,
keeping in view the fact that nowadays the supply system is a.c and more importance
is being given to generation than transmission, a site away from the towns may be
selected. In particular, a site by riverside where sufficient water is available, no
pollution of the atmosphere occurs and fuel can be transported economically, may
perhaps be an ideal choice.
(iv) Economiser. It is a device which heats the feed water on its way to the
boiler by deriving heat from the flue gases. This results in raising boiler efficiency,
saving fuel and reducing stresses in the boiler due to the higher temperature of feed
water. An economiser consists of a large number of closely spaced parallel steel tubes
connected by headers of drums. The feed water flows through these tubes and the
flue gases flow outside. A part of the heat of flue gases is transferred to feed water,
thus raising the temperature of the latter.
(v) Air Pre-heater. Superheaters and economisers generally cannot fully extract
the heat from flue gases. Therefore, pre-heaters are employed which recover some of
the heat in the escaping gases. The function of an air pre-heater is to extract heat
from the flue gases and give it to the air being supplied to the furnace for coal
combustion. This raises the furnace temperature and increases the thermal efficiency
of the plant. Depending upon the method of transfer of heat from flue gases to air, air
pre-heaters are divided into the following two classes:
(a) Recuperative type (b) Regenerative type
The recuperative type air heater consists of a group of steel tubes. The flue gases are
passed through the tubes while the air flows externally to the tubes. Thus, the heat of
flue gases is transferred to the air. The regenerative type air pre-heater consists of a
slowly moving drum made of corrugated metal plates. The flue gases flow
continuously on one side of the drum and air on the other side. This action permits
the transference of heat of flue gases to the air being supplied to the furnace for coal
combustion.
3. Prime movers. The prime mover converts steam energy into mechanical
energy. There are two types of steam prime movers viz., steam engines and steam
turbines. A steam turbine has several advantages over a steam engine as a prime
mover viz., high efficiency, simple construction, higher speed, less floor area
requirement and low maintenance cost. Therefore, all modern steam power stations
employ steam turbines as prime movers. Steam turbines are generally classified into
two types according to the action of steam on moving blades viz.
(i) Impulse turbines (ii) Reactions turbines
In an impulse turbine, the steam expands completely in the stationary nozzles (or
fixed blades), the pressure over the moving blades remaining constant. In doing so,
the steam attains a high velocity and impinges against the moving blades. This
results in the impulsive force on the moving blades which sets the rotor rotating. In a
reaction turbine, the steam is partially expanded in the stationary nozzles, the
remaining expansion takes place during its flow over the moving blades. The result is
that the momentum of the steam causes a reaction force on the moving blades which
sets the rotor in motion.
4. Water treatment plant. Boilers require clean and soft water for longer life
and better efficiency. However, the source of boiler feed water is generally a river or
lake which may contain suspended and dissolved impurities, dissolved gases etc.
Therefore, it is very important that water is first purified and softened by chemical
treatment and then delivered to the boiler. The water from the source of supply is
stored in storage tanks. The suspended impurities are removed through
sedimentation, coagulation and filtration. Dissolved gases are removed by aeration
and degasification. The water is then ‘softened’ by removing temporary and
permanent hardness through different chemical processes. The pure and soft water
thus available is fed to the boiler for steam generation.
(i) Alternators. Each alternator is coupled to a steam turbine and converts the
mechanical energy of the turbine into electrical energy. The alternator may be
hydrogen or air-cooled. The necessary excitation is provided employing main and
pilot exciters directly coupled to the alternator shaft.
(iii) Switchgear. It houses such equipment which locates the fault in the system
and isolates the faulty part from the healthy section. It contains circuit breakers,
relays, switches and other control devices.
The fundamental forms of energy with which thermal stations are principally
concerned are heat and work. Heat produces work and this work is further converted into
electrical energy through a medium i.e. electrical generator. For the purse of understanding
thermal plants, the phenomenon of the thermodynamic vapour power cycle's explained here
under.
• Rankine cycle
• Reheat cycle
• Regenerative cycle
2.1 RANKINE CYCLE:
This is the simplest theoretical vapour cycle, which is the basis for the operation of a
steam plant Superheated steam from the boiler is fed into the prime mover (Turbine) and is
expanded there. After which it enters the condenser emerging as condensate. With the help
of a pump, this condensate is again fed into the boiler.
The main purpose of superheating steam and supplying it to the prime movers is to avoid too
much wetness at the end of the expansion. The moisture content of steam would result in
under-blade erosion. The maximum wetness in the final stage of steam that may be tolerated
without any appreciable harm to the turbine blades is about 12%. Also, the use of a
superheater in a boiler helps in reducing the stack temperature by extracting heat from the
flue gases before these are passed out of the chimney.
CHAPTER-3
BOILER
2. BOILER AND ITS AUXILIARIES
• Boiler is a device for generating steam for power, processing or heating purposes. Boilers are
designed to transmit heat from an external combustion source (usually fuel combustion to a
• The heat-generating unit includes a furnace in which the fuel is burned. With the advent of
water-cooled furnace walls, superheaters and economizers, the term ‘steam generator
• Use.
• Pressure.
• Materials.
• Size.
• Tube content.
• Firing.
• Heat source.
• Fuel.
• Fluid.
• Circulations.
• Furnace position.
• Furnace type.
• General shape.
• Trade name.
• Special features.
• Steel boilers
• Shell type
• Nuclear reactors
2.2.1 Furnace:
It has four walls, consisting of water tubes. The two water walls depth-wise, are called front
and rare water walls and the remaining two water walls, width-wise, are called left and right-side
water walls.
The furnace front water wall tubes are bent at the top to form the roof of the furnace. The
furnace front and rare water wall tubes are bent at the bottom to form the hopper slope. Furnace
rare water wall tubes are bent at the top into the furnace from the nose portion. These tubes are also
bent back in the furnace to form a slag screen and to permit the furnace gases to pass from the
The function of the steam drum is to separate the water from the steam generated in the
furnace walls and to reduce the dissolved solid contents of the steam to below the prescribed limit
The steam drum is provided with many stub tubes, connected to the boiler tubes, level gauge
connections, safety valve connections, air vent connections, feed water connections, chemical feed
Drum internals is provided inside the drum. The drum metal thermocouples, which are used
when starting the boiler, are attached to the upper and lower parts of near the drum centre and both
ends of the drum shell. The thermo-couples for measuring boiler water temperature in the drums
2.2.3 Economiser:
The purpose of the economizer is to preheat the boiler feed water before it is introduced into
the steam drum by recovering heat from the flue gases leaving the boiler.
Feed water enters the boiler drum through the economizer section, which is located in the
lower gas temperature zone. Steaming in the economizer is undesirable. Therefore, the water
temperature, leaving the economizer is designed below the saturation at the operating pressure
during the normal operating period. The economizer is located under the primary superheater
It is preferable that the oxygen content of the feed water does not exceed 0.007ppm and that
the PH value of the feed water is kept at 8.8-9.0 unsuitable feed water causes the formation of an
excessive quantity of deposit in the economizer. Drain valves, provided on the economizer inlet
headers, should not be used as blow-down valves since they cannot blow down a sufficient amount
370 c.
2.2.4. Air-heater:
Air-heater consists of two types i.e., main air-heater and mills air-heater and mill air-heater.
The mill air heater is used only when the moisture content in coal is large and the main heater outlet
Flue gases flow inside the tubes and air outside of the tubes. Air supplied to the mill air heater
is extracted from the main air-heater outlet hot air duct and after getting heated in the mill air
heater, enters the primary Air fan. Gas used for the mill air heater is extracted from the primary
superheater outlet section and after leaving the mill air heater enters the main air-heater inlet flue.
A shot cleaning equipment is provided to remove soot and ash accumulated inside the tubes
The feed water control equipment is provided to maintain the drum water level at the
specified value. The drum water level is always controlled to maintain a constant value, main steam
flow to feed water flow ratio by adjusting the speed of the feed water pump. Further, the drum water
level is re-adjusted by the real drum water level signal detected from the drum level transmitter.
The heat recovery area is surrounded by the furnace's rear water wall tubes, spaced
tangentially, the superheater tubes connected from the drum to the primary superheater inlet
header and left and right-side water wall tubes the left and right side water wall tubes and
2.2.7 Superheater:
Superheater consists of primary and secondary superheaters. The dry saturated steam
leaving the drum flows down the rear wall tubes of the heat recovery area and enters the primary
superheater inlet header. The steam then leaves both ends of it and passes through the transfer pipe
The steam passes through the spray pipe platen loop tubes hung before the furnace slag
screen and pendant loop tubes to the secondary superheater outlet header.
These platen and subsequent loop tubes are called “secondary superheaters”. Thermocouples
are installed to measure tube metal temperatures. They are installed at the stab tubes of the primary
superheater intermediate header and represent the locations of the tubes near the secondary
superheater inlet and outlet headers. To indicate the steam temperature distribution across the
width of the superheater. It is essential that tubes are arranged in good order, and kept clean on
both external and internal surfaces at all times. Fly ash on slag accumulation results in unequal gas
Soot blowers are provided to clean the external surfaces of tubes. Proper feed water
treatment and control of steam quality and carry-over are essential to assuring the cleanliness of
the internal surfaces of superheater tubes. Overloading, fluctuating loads, high water level, foaming,
high concentration, etc. All contributions to deposits inside the tubes will lead to unit failures.
Periodic checks of steam pressure drop across the superheater under initial load conditions
usually indicate whether solid deposits are present or not within the elements.
The superheater outlet temperature is controlled at 505 c from a steam generator output of
178 tons/h v steam flow by employing two de-super heater spray nozzles one in each connecting
piping between the primary superheater outlet header and the secondary superheater inlet header.
The final steam temperature is controlled at the desired value by varying the quantity of feed water
1) I.D. fans
2) F.D. fans
3) P.A. Fans
5) Coal feeders
Purpose:
The purpose of an I.D. fan is to suck the gasses out of furnaces and through them into the
thermal stack. The boiler is to provide two numbers of induced draft fans. Each I.D fan is provided
with regulating damper control and scoop control for controlling loading on fans, and input/outlet
gates for isolation to facilitate startup/ maintenance of fan. Flue gas interconnection with damper
is provided before E.S.P to maintain balanced flow through both A.P.H/second pass when only one
❖ Shaft seals
❖ Hydraulic coupling
An oil circulation system is provided for cooling and lubrication of fan bearings which consists
of one pair of filters & coolers, one each being stand-by oil drawn by the pump through a suction
strainer. The discharge oil from the pump passes through a duplex filter gets cleaned and passes
through the oil cooler, gets cooled and a sufficient number of valves are provided in the system to
The purpose of F.D. fans is to supply the excess air required for complete combustion. The
boiler is provided with two F.D. fans. Each F.D. fan is provided with blade pitch control for
controlling the loading on fans, and an outlet damper for isolation to facilitate startup/maintenance
of the fan.
• Impeller casing
• Diffuser assembly
• Silencer
Oil for the main bearing assembly and servo motor operation is provided by an oil-circulating
system. The pressure in the system is maintained by a recirculation valve. Oil from the pump is
cooled and filtered after the filter, oil branches into two sections one leading to the servo system
known as the “control oil line” and the other to the main bearing assembly for lubrication termed
as “Lubricating oil line”. The motor is an asynchronous squirrel cage induction motor with a grease
Specifications :
No. of blades 18 18
2.3.3 P. A. FAN:
The primary air fan has got two functions viz., during the coal and transportation into the
furnace. The boiler is provided with two PA fans. Each PA fan is provided with blank pinch control
for controlling the loading on fans, an outlet damper for isolation to the facility ate
* Suction chamber
* Fan housing with guide vanes (stage 1)
* Rotor consists of a shaft, two impellers with adjustable blades the pinch control mechanism
* Main bearing (anti-frictional bearings)
* Outer guide vane housing with guide vanes (stage 2)
* Diffuser
* Silencer
Oil for main bearing assembly and servomotor operation is provided by the circulation
system. The pressure in the system is maintained by a re-circulation valve. Oil from the pump is
filtered. The filter oil branches into two sections, one leading to the servo system known as the
“control oil line” and the other to the main bearing assembly for lubrication termed as
“lubricating oil line” Motor is an asynchronous squirrel cage induction motor with the grease
Description PA FAN
In chain type of feeders, a continuous chain is moving around the sprockets in which a sprocket
is driven by a variable speed DC motor and other sprocket chains chain at different intervals, MS
plates are connected which are called scraper feeders. When the scraper moves it will scrap the coal
and the end of the table or platform the coal into the pulverisers.
The actual fuel bleed thickness carried by the scraper will be more to restrict this, a height
regulating plate is provided so that the height of fuel scraped by the scraper can be controlled.
Specifications:
Capacity: 22 tons/hour
Description:
There are three hundred per cent capacity ball tube mills per unit; they operate at a speed of
15 rpm. The mill drum carrying the balls rotates on the anti-friction bearing. Raw coal is fed to the
drum through the inlet elbow and gets crushed to the powder inside the mill drum. The balls and
the coal are carried to a certain height inside the drum and allowed to fall. Due to the impact of balls
on coal particles and due to attrition, as the particles slide over each other and also over the levers,
the coal gets crushed. The classifier for frothier grinding returns the crushed particles.
Primary air in the case of tube mills has dual functions to perform. It is used for drying as
well as transporting the same mil output and is regulated to have proper pulverized fuel outlet
temperature to avoid excess sweeping of coal from the mill, only part of primary air directly
proportional to the boiler load demand is passed through the mill. Further to ensure and maintain
the sufficient velocity of pulverized fuel and to avoid setting in power factor pipes an additional
quantity of primary air (by-pass air) is fed into the mixing box on the raw coal circuit.
Tube mill output, while responding to boiler load demand, is controlled by regulating primary
airflow. Mill level control electric sensing the decrease in coal level in the mill increases the feeder
speed and vice versa, the mill pressurized and plenum chamber around the rotating ensures
tightness trunnions filled with pressurized seal air.
Specifications:
Exhaust stream from the LP turbine enters into the condenser, condensates into the water by
exchanging its heat energy with the cooling water, Cold water from the river or cooling tower is
circulated through the tubes in the condenser and as the steam from the turbine passes round
CEP extracts the condensate from the condenser and pumps to enter into the ejector which
extracts the non-condensing gases from the condenser and heat exchangers of the turbine. The
pressure and discharge of non-condensing gases depend upon the conditions of working of
condensers and ejectors. This water enters the deaerator through a gland steam condenser, drain
cooler, and LPH1&2 LP heaters 1,2 are used to heat the water. The function of the deaerator is to
remove dissolved non-condensable gases to heat boiler fuel water. The deaerator protects the feed
pumps, piping, boiler & any other piece of equipment used in the boiler from corrosion.
A boiler feed pump is a multistage pump provided for pumping feed water from the deaerator to
the economizer. Generally, two pumps each of 100% of the total capacity are used in the KPTS-VII
station. The pump increases the pressure energy of a fluid with the help of centrifugal action. In
between the deaerator & economizer HP heaters are used to heat the water. By this we can
increase the temperature up to 200°C, then water enters into the economizer. The function of the
economizer is a steam-generating unit is to absorb heat from the flue gases and add this as
sensible heat to the feed water that enters the evaporative circuit of the boilers
STEAM GENERATOR (BOILER)
TYPE
The steam generator is two passes, balanced–draft, once-through sliding pressure
supercritical, single reheat, dry bottom, semi-indoor, welded water wall spiral wound and
vertical construction, tilting tangential firing type.
Safety valves and ERVs are selected for the following conditions
TYPE:
Three–casing condensing turbine with reheat for STP -- Type SST5-6000 HP
TURBINE: Type H70
18 reaction stages including 1 low reaction stage and 17 twisted drum-stages IP
TURBINE: 15 + 15 Stages LP TURBINE: 7 + 7 stages
• Maximum Continuous Rating (MCR): 800 MW
• Maximum capability: 840 MW
• Maximum Overload capability: 918 MW
• Steam pressure: 242 bara
• Steam Temperature: 565 0C
• Exhaust Steam pressure: 0.084 bara
• Maximum turbine cycle Heat Rate: 1810 (with MD-BFP),
STEAM PRESSURES
TEMPERATURES
TURBINE EXTRACTIONS
1 8th Extraction HPT 7TH Stage HP Heater 8 A/B
2 7th Extraction CRH HP Heater 7 A/B
3 6th Extraction IPT 7th Stage HP Heater 6 A/B (through DSH
6A/B)
4 5th Extraction IPT 11th Stage De-aerator, TD BFP
5 4th Extraction IPT Exhaust LP Heater 4
6 3rd Extraction LPT -1&2 2nd Stage LP Heater 3
7 2nd Extraction LPT-2 5&6th Stage LP Heater 1B/2B
8 1st Extraction LPT-1 5&6th Stage LP Heater 1A/2A
ESTIMATED LUBE OIL FLOW REQUIREMENT OF BEARINGS:
VIBRATIONS
Absolute bearing Relative shaft vibration
casing vibration
Alarm setting “warning 9.3 mm/s 165 μm
high” (pk-pk)
Turbine Trip limit 11.8 mm/s 240 μm
“very high” (pk-pk)
A temperature rise of oil in bearings
normal 20 K
A temperature rise of oil in turbine bearings
maximal 25 K
| 27
Vacuum trip
setting
The steam generator is two pass, balanced – draft, once- through, sliding
pressure supercritical, single reheat, dry bottom, semi-indoor, welded
water wall spiral wound and vertical construction, tilting tangential firing
type.
FANS:
• Air is the most desired constituent after fuels for combustion to take place.
There are many types of fans used in modern thermal power plants
depending on type of fuels. The supply of air and withdrawal of the product
of combustion are handled by the fans.
INDUCED DRAUGHT FAN:
An induced draught fan (ID Fan) is provided to maintain a negative pressure in
the furnace by sucking the products of combustion from it with a slight positive pressure
at the discharge end vis-à-vis the bottom of the chimney/stack. This positive pressure,
assisted by the stack effect of the heated chimney (120oC), causes the flue gas to leave the
chimney and mixes it with the surrounding atmosphere. Dampers automatically
controlled, are also a part of the SG plant that maintains the approximate furnace draught
within a safe margin.
START PERMISSIVES for ID FAN-A (similarly IDF-B)
• Flue gas path available
• ID Fan – B in Service
• ID Fan – A lube oil tank level “Adequate >75%”, (low <=60%, Very low <=50%)
• ID Fan – A “OFF” (Switchgear)
• ID Fan – A “Not Tripped”
• ID Fan – A “No Switchgear Disturbance”
• ID Fan – A Switchgear “Available”
• ID Fan – A Cooling/ Sealing air fan outlet pressure “Adequate”
(>75
mbar - Adequate, =<75 mbar - Low, <10 mbar – very Low)
• ID Fan Hydraulic room temperature “Not High” (>=80oC)
• ID Fan – A Bearing room temperature “Not High” (>=80oC)
• ID Fan – A Blade pitch close (<3%)
• ID Fan – A inlet isolation damper “CLOSE”
• ID Fan – A Outlet isolation damper “CLOSE”
• ID Fan – A Motor Bearing DE/NDE vibrations X/Y “OK” (<9 mm/sec)
• ID Fan – A Motor winding temperature “OK” (<110 oC)
• ID Fan – A Motor Bearing DE/NDE temperature “OK” (<90oC)
• ID Fan – A Control Oil pressure “OK” (> 22 Kg/cm2) (C.O Pr. Low < 16.5
Kg/cm2)
• ID Fan – A Lube Oil pressure “OK” (7.5 Kg/cm2)
• ID Fan – A Lube Oil Flow “OK” (> 8.5L/min) (low <6.0 L/min)
• ID Fan – A Bearing temperature “OK” (< 90oC)
• ID Fan – A Vibrations X/Y “OK” (<9mm/sec)
| 36
FORCED DRAUGHT
FAN:
The air is supplied through the forced draught fan (FD Fan) and air ducts. Before
reaching the combustion chamber, air is pre-heated using an air heater in order to
increase the overall efficiency of the Boiler. Furnaces usually have a negative pressure for
various reasons and automatically controlled dampers are part of this system to control
the desired quantity of air which takes care of the differential pressure of the supply air
and the furnace.
Start Permissive for FD Fan – A (Similarly FD Fan – B)
FD FAN TECHNICAL
DATA
Quantity 2 No’s
power 2125 KW
Rated Voltage 11KV
Full load 133.5 Amps
Current
No load 28 Amps
Current
Rated Speed 995 rpm
F.L Efficiency 96.0 %
Flow 350 m3/Sec
Pressure 445 mmWC
Temperature 53 oC
PRIMARY
AIR FAN
The function of the Primary Air Fan (PA Fan)is to transport the fine grains of solid
fuels in the required quantity at the correct temperature with the automatically
controlled dampers, this is done by the proportioning of cold PA with hot PA that is
obtained by heating a portion of the PA using Air Heaters.
Start Permissive for PA Fan – A (Similarly PA Fan – B)
Seal Air
Fans:
A Seal air fan (SA Fan) is used to provide air at slightly higher than PA pressure
to seal all the dust-laden equipment, - namely the mills / pulverizers with associated
dampers, relevant parts of the feeders, and so on.
Scanner Air Fans:
The purpose of the these a scanner air fan (Sc A Fan) is to cool the flame
scanners heads meant for detecting the presence and quality of the flame.
BURNER MANAGEMENT SYSTEM
Boiler Purge Permissive
1. No Boiler Trip Command Exists (2/3 logic)
2. Heavy Oil Recirculation Valve Closed
3. All Elevations all Heavy Oil Nozzle valves Closed
4. All Light Oil Nozzle valves Closed
5. Light Oil Trip valve Closed
6. Heavy Oil Trip valve Closed
7. All Pulverizers OFF
8. All Coal Feeders OFF
9. Nozzle Tilt Horizontal and Air Flow <40%
10. All FSSS System Power Available.
I. All individual Coal Elevations (A,B,C,D,E,F,G&H) power available.
II. All individual Heavy Elevations (AB,CD,EF,GH)) power available.
III. Unit Critical Power Available.
a. 220 V DC power available (2/3 logic)
b. Unit Interrogation power available (2/3 logic)
c. MFT Interrogation power available (2/3 logic)
11. All Elevation Disc.Flame Scanners and Fire ball flame Scanners “No Flame”
a. All Oil Elevations (AB,CD,EF&GH) Disc. Scanners “No Flame”
b. All Elevations (AB,BC,CD,DE,EF,FG,GH&HH) ¾ Fireball Scanners “No
Flame”
12. Both Primary Air Fans “OFF”
13. All Auxiliary Air Dampers are “Modulating”
14. All SOFA (Separated Over Fired Air) Dampers Closed
15. Unit Air Flow is greater than 30% (892 TPH)
16. All Hot Air Gates Closed.
| 42
LOTV / HOTV On
Permissions:
o The Oil Trip Valve is proven “not closed”, any oil (nozzle) valve is “not
closed” and either the following conditions exist, for more than two seconds.
• The oil header pressure is “low”. ( < 2.5 kg/cm2 for both HO & LO)
• For Atomizing header pressure is “low” ( HO: < 4.5 kg/cm2 & LO: <3.5 Kg/cm2).
o A “Master fuel trip” signal is established.
• If all elevations voted, Boiler trips on No flame. For voting in each elevation, the
following are the interlocks.
• For Fuel Elevations: ( A/B/C/D/E / F/G/H):
• Feeder is OFF.
• Both the following conditions:
• Any oil valve not closed in the same elevation.
• Two out of Four guns not proven in the same elevation.
• Both the following conditions:
• Less than 2 out of Four scanners show flame of same elevation.
• Two out of four guns not proven of same elevation. For Auxiliary
• Both the adjacent feeders off ( Ex: for AB: A&B and For HH-Only H Feeder)
• Less than two out of Four scanners show flame of same elevation.
SADC (Secondary Air Damper Control)
Auxiliary Air dampers :
• To maintain wind box air flow distribution.
• Overriding control in the event of high wind box DP.
• Bias capability of elevation dampers.
Up 30% Unit Load, all wind box auxiliary dampers are modulated to maintain wind
box to furnace DP. For above 30% load, BMS will issue close command to elevations of
auxiliary dampers that are not required for elevations of fuel currently in service. These
signals are issued at 10 sec intervals from top of the wind box. This close command sets
corresponding elevation of dampers to a load dependent Out of service damper
position, which ensures minimum damper cooling air flow.
Other BMS command, Position for Oil firing sets the corresponding damper
position to a predetermined position.
AIR PREHEATERS:
An air heater is the last element of the flue gas path where the residual heat
contained in the gas is used for air drying before taking part in the combustion chamber
to improve overall efficiency; this is done by better and spontaneous burning of fuel and
a lower stack outlet temperature. Air Heaters outlet combustion air temperature is higher
compared to a Boiler without them affects fuel saving in the range of 5 to 10%. The
preheated air for the combustion process increases Boiler efficiency practically at all
loads. For larger capacity modern power plants, tubular or regenerative air heaters are
the best suited and are used for higher gas and air pressure as per the recent trend.
START PERMISSIVE
• Air Preheater power supply for Air Motor solenoid valve “available”
• Air Preheater is in “OFF” condition.
• Elec. Motor Switchgear “No Disturbance”
• Air Preheater Support/Guide Bearing Temperature “Not Very High”
• (High Trouble >82 oC, very high >70 oC , High >40 oC, Low <38oC)
• Air Preheater Support / Guide Bearing LOP A/B Switchgear available.
• Plant air Inlet to Air Preheater pressure is “Not Low”
Trip Interlocks
o Air Preheater local Elec. Push Button Operated
o Air Preheater Electrical Disturbance
o Air Preheater Fire Protection
▪ Any Hot end Temperature (out of 14 no’s) > 450oC from 3secs
▪ Any Cold end Temperature (out of 14 no’s) > 450oC from 3secs
Trip Interlocks:
• Air Preheater GB/SB LOP local Elec. Push Button Operated
• Air Preheater GB/SB LOP Electrical
Disturbance AUTO ON:
• LOP on Main Selection & Other LOP in OFF condition & GB/SB
Temperature > 46 OC .
• Pump on Auto Standby & Other Running Pump Run Trip & GB/SB
Temperature > 46 OC.
Start Permissive:
• Boiler Circulation Pump Switchgear available
• BCP Inlet Isolation Valve “Opened”
• BCP Discharge Valve “Opened”
• Minimum Eco. Flow Control Valve at “start up” condition.(28 to 33%)
• BCP Thermal Barrier Return line Flow “Not Low”
• BCP thermal water Return line Flow “Not Low”
• Seperator Storage Tank Level >4mtrs (and)
Circulation Shut OFF valve “Opened”.
▪ (OR)
• Economizer inlet feed water flow > 192 TPH
• BCP Casing /Suction line Abs (Delta) temperature “OK” (>55 OC) ,
▪ ( if Economizer inlet flow is > 192 TPH, Abs Temperature = BCP
Surface Temperature – BCP Suction line Temperature, Otherwise Abs
Temperature = BCP Surface Temperature – water Seperator metal
Temperature average )
• BCP Motor Cavity Temperature “OK” (>4 oC)
• BCP Motor Cavity Temperature not Hi Hi (<66 oC)
Trip Interlocks:
AUTO OPEN: Separator in Auto Wet Mode (OR) MS Flow < 40% (OR) Separator
Storage Tank Level >1 Meter.
PROTECTION OPEN: AUTO CLOSE:
MFT with 2sec time duration. Main Steam Flow > 50%HWL CONTROL
VALVES
HWL CONTROL VALVES
HWL CONTRHOL VALVE-1 EMERGENCY CLOSE:
Water wall soot Blowers : 104 No’s + 26 No’s for future provisions
Long Retractable soot Blowers : 48 No’s + 44 No’s for future provisions
Air Heater soot Blowers : 2 No’s
Furnace Temperature Probes : 2 No’s
Feeders:
The feeders that have variable speeds are provided to feed the raw fuel. For mills, the
speeds varies in proportion to the Boiler demand. The raw feed already available inside the
mills/pulverizers acts as storage for meeting the immediate requirement and then the proper
feeder speed takes care of the situation by bringing storage status back to within acceptable limits.
PULVERISER (MILL) DATA :
Guaranteed Value : 72.4 TPH (90%) and Maximum input coal size : 50 mm
| 52
Start Permissives:
No MFT Exists.
Any of the following condition exists:
● Tilt is horizontal and unit air flow is < 40 %.
● Any feeder is proven for at least 50 secs
All pulveriser discharge valves open.
Pulveriser outlet temperature is not high ( i.e 104 °C or Difference between Set
Point &Process Value <11)
Feeder local control switch in remote.
No pulveriser trip persists .
Lube oil system start permissive:
● Pulveriser LOP C (or) D ON.
● Pulveriser lube oil Return Pr OK.
● Pulveriser LOP-A (or) B ON.
● Pulveriser LO supply temp > 35°C.
● Pulveriser lube oil Supply Pr high.
● Pulveriser Lube oil Flow not low.
● All Thrust bearing temp normal.
● LOP A/B ON & temp < 40 oC & Filter DP > Hi.
Pulveriser cold air gate is in open.
Primary air permit is available (634 mmWcl) .
Bunker isolation valve and manual valves are in open condition.
Seal air header to bowl DP is ok (>203 mmwcl)
On Starting the pulveriser, the following events occurs:
● Run Cold air damper to 5% signal sent to DCS is removed.
● Open Cold air damper to 100 % signal will be sent to DCS
Pulveriser Trip Conditions:
Master Fuel Trip.
Pulveriser – Seal air Bowl DP < 102 mmWcl
(Operating value: 203 mmWC and maximum value is 320 mmWC).
Pulveriser Discharge Valves Not Open.
Loss of Ignition Energy in 180 Sec on start of pulveriser.
Emergency Push Button Operated.
Master Trip from Switchgear.
Loss of PA Header Pressure Very Low 507 mmWC.
Loss of PA Header pressure Low 634 mmWC with 5 sec delay.
Trip from Pulveriser Lobe Oil System.
● Lube Oil Supply Temperature Low <29oC.
● Any Lube Oil Pump ON and Flow to Planetary Gearbox is very low for 5
sec.(i.e <175 LPM)
● Any Lube Oil Pump ON and Pressure Not Adequate (i.e <0.8 Bar)
● Lube Oil Filter DP High (>2.0 Bar).
● Lube Oil Tank Level Low (i.e <460 mm from Tank Top).
● Lube Oil Tank Temperature Low (<29oC).
● Lube Oil Supply Temperature High after cooler (>65oC).
● Gear box Bearing Temperature High (>85oC).
● Motor Bearing Temperature High (105oC).
● Motor Winding Temperature High (130oC)
● When both LOPs are not ON for more than 2 secs.
● LOP ON and Lube Oil Pressure is <0.5 bar after cooler is very low
with a time delay of 15 sec
Loss of Primary Air exists when any of the following conditions exist:
The primary air duct to furnace differential pressure is low for more than five
sec. ( 634 mmwcl).
The primary air duct to furnace differential pressure is low low. (
507 mmwcl).
Both primary air fans are Not ON and any pulverizer is O.
PULVERISER LUBE OIL SYSTEM:
FEED
WATER SYSTEM:
After de-aeration in the de-aerator, the condensate is taken to the (3x50%) capacity
boiler feed pumps. Two of the boiler feed pumps are turbine driven and one electric motor
driven through variable speed hydraulic coupling. Individual recirculation control loops
are envisaged for the pumps to maintain required minimum flow. A common feed water
outlet from BFPs is taken to the parallel banks of HP heaters nos. 6A & its de-superheater,
7A & 8A and 6B & its de- superheater, 7B & 8B. Each of the HP heater banks are provided
with inlet and outlet motorized isolating valves. Two 50% flow bypass lines are provided
in parallel to heaters banks to serve isolation of one bank or both the heater banks. Each
bypass line will have 50% capacity spring loaded bypass valve.
Feed water to the boiler shall be regulated during low load operation by regulating
30% low capacity control valve and during higher load operation, flow shall be regulated
by controlling the speed of the BFPs.
The attemperation water for boiler reheat steam temperature control is drawn from
feed pump inter stage tap off. The attemperation water for HP bypass station is drawn
from the main feed water line upstream of the HP heaters. The attemperation water for
boiler main steam temperature control is drawn from boiler feed pump discharge line
after HP Heaters.
During normal operation HP heater no. 8A / 8B drains are cascaded to HP heater-
7A / 7B and HP heater no. 7A / 7B drains together with drains from HP heater-8A / 8B
are cascaded to HP heater-6A / 6B respectively. HP heater-6A / 6B drains are cascaded to
deaerator. Under high level conditions heater drains are directly led to the condenser via
flash tank-A.
The outlet of the De-aerator its connected to the Boiler feed pump (BFP) Suction
and from there to reach the Boiler proper. It impels the feed water with requisite pressure
that dictates the working or operating point of steam generation. BFPs are always supplied
in a redundant configuration to avoid interruption of operation. Normally, one motor-
driven BFP is kept for startup and emergency situations and two Turbine-driven BFPs are
kept for operating up to a full load.
During normal operation boiler feed pump turbines are fed with steam drawn from
IP turbine intermediate stage, beyond approx. 30% load. During start-up, steam for BFP
turbine is supplied from cold reheat line as well as external supply source i.e. auxiliary
steam header. BFP turbines exhausts are connected to condenser through motorized
butterfly valves.
| 57
Low
(2sec ) Suction Flow – (maximum
▪ < 10 value of
Kg/cm — 2 actual
Very Low Speed
(10sec )) function
and
• MD BFP Trip Conditions: 650T/H
r) OR
• BFP Suction Flow – Speed X 0.8 = < 0 TPH Suction Flow measured fault & BFP ON
& BFP ON for time delay 5 sec.
• BFP Suction Flow < x TPH Recirculation Valve Opened
• ( Low : <330 TPH, High : >1050 TPH)
• BFP Lube Oil Header Pressure very Low
Recirculation Valve Protection
• (very Low : < 0.8 Kg/cm2, Low : < 1.0 Open:
Kg/cm2, High : < 3.0 Kg/cm2)
Suction Flow <330 T/Hr OR BFP
• BFP Working Oil Temperature at upstream OFF
of coolers Very High.
• BFP Journal Bearing Temperature DE/NDE Recirculation Valve AUTO Closed:
“ very High”
• BFP Trust Bearing Temperature DE / NDE Suction Flow – (maximum value
“Very High” of comparison of 640 T/Hr to
• BFP Motor Winding Temperature “ Very actual Speed function) =>50
High” T/Hr after 1.5
• De-aerator Level “Very Low” (-950mm) sec OR
• BFP Motor Journal Bearing Temperature Suc
“Very High” tion Flow is >1050 T/Hr
• BFP Hydraulic Coupling Bearing ● DP across BFP / Booster Pump
Temperature “Very High” Strainer
• Booster Pump Journal Bearing High : > 1500mmWC , Very
Temperature DE/NDE “Very High” High : >2000 mmWC.
• Booster Pump Trust Bearing Temperature
● DP across HC Filter : High >0.6
DE / NDE “Very High”
Kg/cm2
• BFP Suction Pressure : < 10 Kg/cm2 & BFP
ON.
● BFP/BP Mechanical seal cooler SW
Inlet Temperature : High > 80oC.
• BFP Pump / Motor Bearing Vibration “Very
High” ● BFP/BP Mechanical seal cooler SW
• Separator Level “Very High” (>14 meters) Outlet Temperature : High > 70oC.
● BFP/BP Mechanical seal cooler CW
Inlet Temperature : High > 50oC.
: BHEL , HYDERABAD
Type
: NK 63/71-3
Machine No.
: T-1131 to T-1132
Type of Governing
: EHTC
No of Drive Turbines
: Dual
Operating Speed range
: 4995 rpm
Trip Speed
: 5494 rpm
No of Stages 11
Steam source
:
D
u
r
i
n
g
n
o
r
m
a
Design & lOperating Conditions
Steam
o condition at Drive Turbine inlet at full
loadp(TMCR/800 MW /0% makeup)
e Pressure
r : 11.86 Kg/cm2(a)
a Temperature
t : 363.3oC
Drive
i Turbine operating Speed
o
: 4770 rpm 1. Main Oil Pump 2500 S
Shaft power at full / BFP
Design case 2. Auxiliary Oil Pump 2500 S
3. Emergency Oil Pump 425 C
: 12489/15790 KW Steam
consumption for two Drive
Turbines
: 61.367/59.481
Exhaust Steam Pressure at
TDBFP Outlet
: 0.1038/0.0836 Kg/cm2(a)
Maximum allowable
temperature at exhaust
: 85oC
Turbine inlet parameters at low load
operationt
Pressure
: 11.9 Kg/cm2(a)
Temperature
: 375.3oC
Lube oil and Control system
Total Oil System Capacity
: 16700 litres
Oil Tank Capacity
Trip Oil Pressure “Not Very Low” & any one the following exists
1. Start up sequence ON
2. TD BFP-A Exhaust steam block Closed &
TD BFP-A Gland Steam leakage to GSC valve Closed
3. TD BFP-A Gland steam Control valve kept in manual & minimum
through EHTC
OR
Kept Gland Steam Pressure & Temperature Adequate
4. CRH Steam to BFPDT-A Block valve Closed
OR
kept CRH Steam Pressure (>15 ata) & Temperature (>287oC) &
Superheat (>50oC)
5. TD BFP-A Aux. Steam CV warm up valve Closed
OR
CRH Steam to TD BFP-A Block valve Opened
6. IP Extraction Steam to TDBFP-A Block valve Closed
OR
TD BFP-B Working & Extraction Steam Pressure (>8.0 ata) & IP
Extraction Steam to TDBFP-A Block valve Opened
7. IP Extraction to TDBFP-A &B line drain valve Opened
OR
TD BFP-B Working & Extraction Steam Pressure (>8.0 ata) & IP
Extraction Steam to TDBFP-A Block valve Opened
8. Drain valve upstream of TDBFP-A Emergency Stop valve (ESV)
Opened &
Drain valve downstream of TDBFP-A aux Control valve Opened &
CRH Steam to BFPDT-A drain valve U/S of Isolation valve Opened
9. Gland Seal Steam Header drain valve Opened & Aux Steam to
TDBFP-A Drain valve before Block valve Opened
10. TDBFP-A Aux. CV warm up valve Opened & TDBFP-A Vent valve
upstream of ESV Opened
11. TDBFP-A Casing drain valve Opened (both) & TDBFP-A Casing cross
drain valve Opened & maintained Condenser Pressure <0.6
Kg/cm2(a)
12. Maintain Aux Steam Header Pressure >12.0 ata & TDBFP-A Gland
Steam Header drain valve Opened & maintain TDBFP-A speed > 30rpm
& Aux Steam temperature at TDBFP-A inlet on Gland Steam line >
300oC
13. Put the Gland Steam Control valve in Auto & maintain Gland Steam
Header Pressure >700 mmWC & Temperature >330oC
14. TDBFP-A Gland Steam Inlet Header drain valve Closed & TDBFP-A
Gland Steam Header drain valve Closed
15. Maintain any one of the following
Aux. Steam to TDBFP-A&B Pressure, temp.& Superheat OR
CRH Steam to TDBFP-A&B Pressure, temp.& Superheat OR
IP Extraction Steam to TDBFP-A&B Pressure, temp.& Superheat
16. CRH Steam to TDBFP-A Block valve Opened
17. Aux. Steam to TDBFP-A Block valve Opened
18. IP Extraction Steam to TDBFP-A Block valve Opened
19. CRH Steam to TDBFP-A Block valve Opened
OR
Aux. Steam to TDBFP-A Block valve Opened
OR
IP Extraction Steam to TDBFP-A Block valve Opened
20. Maintain TDBFP-A Lube Oil Header Pressure not Low and
De-aerator level adequate & TDBFP-A Suction valve Opened &
TDBFP-A Pump barrel top/bottom diff. temp < 40oC
21. TDBFP-A Recirculation valve Opened
22. TDBFP-A Discharge valve & Discharge bypass valve Closed
23. TDBFP-A Trip Condition present & TDBFP-A Remote engage
solenoid permissive available (energize)
24. Maintain remote engagement oil pressure > 5.0 Kg/cm2
25. TDBFP-A Remote engagement De-energized
26. Maintain any one of the following
Aux. Steam to TDBFP-A&B Pressure, temp.& Superheat OR
CRH Steam to TDBFP-A&B Pressure, temp.& Superheat
OR
IP Extraction Steam to TDBFP-A&B Pressure, temp.& Superheat
27. TDBFP-A Main Control valve Closed to <2% &
TDBFP-A Aux. Control valve Closed to <2% & maintain remote
engage Oil pressure > 5.0 Kg/cm2
28. Maintain TDBFP-A Gland Steam Pressure adequate & Condenser
pressure < 0.6 Kg/cm2(a)
29. TDBFP-A Exhaust Block valve Opened & Gland Steam leakage to
GSV valve Opened
30. TDBFP-A ESV 1&2 Opened & maintain trip oil pressure after SV-
2220 >4.0 Kg/cm2
31. Maintain any one of the following
Aux. Steam to TDBFP-A&B Block valve Opened & Aux. Steam to
TDBFP-A&B Pressure, temp.& Superheat
OR
CRH Steam to TDBFP-A&B Block valve Opened & CRH Steam to
TDBFP-A&B Pressure, temp.& Superheat
OR
IP Extraction Steam to TDBFP-A&B Block valve Opened &
IP Extraction Steam to TDBFP-A&B Pressure, temp.& Superheat
32. Open main Control valve > 2% OR Aux Control valve >2% and
maintain Speed > 1500rpm
33. TDBFP-A Discharge pressure Not < 40 Kg/cm2 & TDBFP-A
Turbine and GB LSS axial Displacement Not High & TDBFP-A ,
GB,BP Vibrations are not High & TDBFP-A Turbine, BFP, BP.GB
Bearing temp are not High & TDBFP-A and BP Thrust Bearing
metal temp are not High
34. TDBFP-A Discharge isolation bypass valve Opened
35. TDBFP-A Discharge valve Opened
36. TDBFP-A Discharge isolation bypass valve Closed
(FW Control release)
37. TDBFP-A FW Control kept in Auto and make TDBFP-A suction
flow >30% and TDBFP-A 100% casing temp > 140oC
38. TDBFP-A all the drain valves Closed
39. TDBFP-A Suction flow > 850 T/Hr OR
TDBFP-A variable speed set point for RCV Closed &
TDBFP-A Speed pick up No fault
40. TDBFP-A Recirculation valve Closed
41. Maintain all the critical parameters of TDBFP-A are within the
limits
42. TDBFP-A Startup sequence completed
TD BFP SGC SHUT DOWN SEQUENCE PROCEDURE:
Turbine Exhaust. High vacuum is maintained to extract steam and then cool it vis-à-vis
condensation through exchange of heat with the cooling water from a separate source.
The water boxes of the condenser have been designed for smooth entry and
uniform distribution of cooling water to all the tubes. The front water boxes are hinge type
and have been provided with necessary hinged manholes for easy access to the interior for
inspection. Each water box has been provided with a vent and drain connection. The
circulating water connections of adequate size have been provided with water boxes.
Safety guards have been provided at CW inlet and outlet connections to protect the
operating personnel from falling-in, during inspection or maintenance.
Hot Well
The hot well (of adequate capacity) is divided longitudinally for detecting
contamination of the condensate in each condenser half. Suitable manholes are provided
in each of the hot well sections for easy access and inspection. The provision of drainage
of condensate has been provided at the bottom of the hot well to drain it completely if
required.
The condensate produced in the condenser and the drains entering through flash
vessels collect in the condenser hot well from where they pass to the condensate pumps.
CONDENSER DATA:
DESCRIPTION UNIT CONDENSER-1 CONDENSER-2
Design C.W Temperature oC 33.0 37.72
C.W Temperature raise oC 4.72 4.66
Condenser back Pressure mmHg (a) 56.93 72.96
C.W Flow Quantity TPH 84200
C.W side Pressure Drop MLC 2.86 2.86
No. of Tubes No. 29755 29755
Tube OD X Thickness mm X mm 25.4X0.7112/25.4X0.889 (top 2)
Vacuum pumps:
Start permissions:
Vacuum Pump Seal Water Flow Not Low ( Flow Switch)
Gland Steam Header Pressure Not Low (> 0.1 Bar)
Vacuum Pump MCC Available
Vacuum Pump at NO LEPBO
Vacuum Pump recirculation water Temperature NOT Hi (< 65 oC)
Vacuum Pump Separator Tank Level Not Low
Recirculation Pump ON
Vacuum Pump NO Electrical Disturbutor
CONDENSATE EXTRACTION PUMPS
The Condensate Extraction Pumps (CEP) are connected to the Condenser Hot well to
take out the condensate and deliver it to the rest of the water circuit of the whole cycle.
3x50% condensate extraction pumps (CEP) are provided; normally two pumps are
working while the third pump is on standby. Any one of the pump can be selected as a
working pump with the help of a switch. One pump will be in operation up to 50% load.
In case of high-pressure drop (0.125 kg/cm2) alarm in the suction strainer, the
working pump is to be tripped & isolated remote manually after bringing standby pump
in to service.
CEP MOTOR Technical Data:
Make : BHEL , BHOPAL
Type of Motor/Enclosure : SCIM / TETV
Rated Continuous Output (KW) : 1450 KW
Rated Speed (rpm)/ Slip (%) : 1492 / 0.53
Rated Voltage : 3300 V
Full Load Current (apms) : 302.0
No load Current (apms) : 61.5
No Load losses (KW) 31
Full Load Efficiency (%) : 95.5
Noise Level : 85 dB (A)
Vibration Level (Rigid Mounting) : 37 µ (displacement) /2.3 mm/s
De-aerator:
A de-aerator provides mechanical-type and chemical type for removal of the
dissolved gases (CO2 and O2), which is highly desirable for safe boiler operation. The
same is accomplished prior to dose chemical oxygen scavengers (Hydrazine) by heating
feed water with steam. This process reduces the concentration of oxygen and carbon
dioxide from FW. Being most economical, it can reduce the oxygen content up to 0.005
mg/liter. Steam is preferred for de- aeration because steam is essentially free from O2 and
CO2. Readily available steam adds the heat required to complete the process.
Data sheet for De-aerator
Description Steam Condensate Feed water
entering entering leaving
Pressure ( ata) 11.85 --- 11.80
Quantity (TPH) 107.250 1724.427 2313.765
Enthalpy (Kcal/Kg) 760.3 149.3 189.0
No of spray valves / trays 144 / 792
Design pressure (ATG) 14 & FV
Design temperature (Dea heater /tank) 395 / 260 oC
Operating Pressure / Temperature 11.8 Ata /186.3 oC
LP Bypass
System:
LP bypass pressure control valves are provided to maintain reheat steam pressure at desired set
point during start-up, shutdown, load rejection, normal unit operation or turbine trip condition.
The LPBP Protection System is a redundant digital system in which all the individual
safety circuits for bypass protection are built in. If any of the individual protections is
relayed, the LPBP trip is released, thereby closing the single stem control valves. For each
LPBP station, tripping criteria’s are separately determined.
Each LPBP control valve is provided with 2 trip solenoid valves (TSV). The TSVs
are connected in 1v2 hydraulic circuit. The LPBP protection system keeps the TSVs
energized under normal operating conditions. Trip signal coming from any of the
individual protection circuits, act through the protection system, to de- energize the
TSVs.
TRIPPING CRITERIA:
•The LPBP 1 trips automatically under any of the following conditions. The
initiating signal in each case actuates both the trip channels separately.
• Condenser 1 vacuum protection: The protection acts if absolute pressure
in the condenser 1 rises above 0.6 Kg/cm2 (abs).
• Condenser 1 temperature high: The protection acts if the condenser 1 wall
temperature rises above 90 °c. Three thermocouples are provided in condenser
wall and the trip signal is initiated in 2-out-of-3- logic.
• Water Injection flow protection 1: For the water injection flow protection,
the permissible LPBP 1 flow is specified through a set point derived as specified.
An adjustable margin mwp (10 to 50%) is added to this calculated WI flow .
Then final output value is compared continuously with water injection flow
measured by each Flow Transmitter at W.I. valve upstream. If the differential
flow exceeds the set limit a trip signal is formed in each channel. Initial value of
mwp is kept as 10 %.
LPBP 2 TRIPPING CRITERIA:
• The LPBP 2 trips automatically under any of the following conditions. The
initiating signal in each case actuates both the trip channels separately.
• Condenser 2 vacuum protection: The protection acts if absolute pressure
in the condenser 2 rises above 0.6 Kg/cm2 (abs). The trip signal is initiated by
three pressure transmitters in 2-out-of-3-logic (MAG10CP012,13,14).
• Condenser 2 temperature high: The protection acts if the condenser 2 wall
temperature (MAN52CT001,02,03) rises above 90 °c. Three thermocouples are
provided in condenser wall and the trip signal is initiated in 2-out-of-3- logic.
Water Injection flow protection 2: For the water injection flow protection, the
permissible LPBP 2 flow is specified through a set point derived as specified. An
adjustable margin mwp (10 to 50%) is added to this calculated WI flow . Then final
output value is compared continuously with water injection flow measured by each
Flow Transmitter at W.I. valve upstream. If the differential flow exceeds the set
limit a trip signal is formed in each channel. Initial value of mwp is kept as 10 %.
Difference of the LPBP 2 flow and water injection flow is continuously compared
with a limit signal in each of the channels. If the differential flow exceeds the set
limit a trip signal is formed in each channel.
Condenser level protection: The protection acts if the condenser hot well level
rises above admissible level. 2 hot well level trip signals are received from station
C&I and processed in 1 v2 to affect the trip. The trip signal is initiated from station
C&I by three level transmitters in 2 out of 3 logic.
HPSU Header Pressure Low: In case both the CF pumps are working and
header pressure falls below 120 Kg/cm2 , LPBP trip is initiated.
HPSU Emergency off : HPSU provides control fluid at high pressure for
operating the control Valve . In case of control fluid temp exceeds the admissible ,
oil level fall below pre determined value , or Emergency off push button imitated.
HPSU emergency off signal is generated if any of above parameter reaches an
impermissible level , LPBP trip is initiated.
MANUAL TRIP : Pushbutton/Control button is provided on the HPSU skid for
each bypass system for individual tripping of bypass system 1 & 2.
BYPASS TRIP SYSTEM : If the following trip criteria coming any of the
individual protection system responded then SR flip flop is set and along with water
injection protection responded and passed thru OR gate for related LPBP TSVs ,
tag nos. MAN52AA013, 14 and MAN55AA013,14 to get de-energized.
o Condenser hot well level Protection
o LPBP condenser press protection
o LPBP condenser temperature protection
o HPSU emergency off
o HPSU header press too low
o LPBP trip switch Operated.
The SR flip flop reset when LPBP reset sw operated from OWS or position set point
of LPBP is < -40% derived from controller output. <- 40 % is used for resetting
bypass trip corresponds to lift set point of LPBP controller operating in negative
direction. Controller o/p range is -100 to 105%.
| 87
Unit Start-up up to
synchronization
Load Pressure SP
840 57
800 54.6
640 44
320 23.6
240 17.4
0 12
At Boiler Super Heater outlet pressure of approx. 5.5 Kg/cm2, ensuring the Main
Steam Stop valves (Boiler side) open position, put both the HP & LP bypass valves
including Master control in auto with Logic Set Point selection
Note:
Maximum value of the logic Sp to HPBP PCV = 255 Kg/cm2
Maximum value of the logic Sp to LPBP PCV = 57 Kg/cm2
HP Bypass quick open conditions:
when boiler in service and on any of the following conditions
a. Turbine tripped
b. GT CB (both breakers) opened
c. Turbine Load Shedding Relay (LSR) Operated
d. Emergency fast Open from Desk / HMI
e. RH Protection Acted
f. HPBP pressure control deviation > 8 Kg/cm2
Station:
Auxiliary steam system is designed to provide steam for the turbine auxiliaries &
boiler auxiliaries during start-up, low loads and normal running of unit.
The system comprises of:
● A "High capacity PRDS", Controlled by ASV-22, with tapping off steam from
main steam line to meet auxiliary steam requirements during unit start-up,
low loads & intermittent requirements,
● A "Low Capacity PRV", Controlled by ASV-26, with steam tapped from CRH
line to meet auxiliary steam requirements during normal running.
● Spray water required for de-superheating will be tapped off from
condensate extraction pump discharge. Spray water for HCPRDS is
controlled through the control valve CDV-138.
● CDV-141, a 100% bypass motorized regulating valve for HCPRDS spray
control.
The HCPRDS will reduce the pressure and temperature of the steam tapped off
from main steam line to 16 kg/cm2 (abs) & 290o C. The LC-PRV shall reduce the pressure
of steam tapped from CRH line to 16 kg/cm2 (abs) and temperature in the range of 280o
C to 310o C, depending upon the CRH parameters at corresponding load.
Motorized bypass regulating globe valve (ASV-29) has been provided for low
capacity PRV which can be operated remote manually in case of mal- operation of main
control valve.
The change-over from Low capacity PRV to High capacity PRDS & vice- versa is
automatic with manual override facility. During high capacity PRDS operation, low
capacity PRV remains in operation also.
The low & high capacity PRDS can be operated independently either in auto or
remote manually from the unit control desk. However, manual operation overrides the
auto operation.
The CW system shall be closed circuit re-circulating type with Natural Draught
Cooling Tower. The CW system will deliver cooling water to Condenser. Cooling water
shall be supplied to Condenser through CW pumps installed in CW pump House. The hot
water return from Condenser & ACW system shall be led together to Cooling Tower for
cooling. The cooled water from cooling tower shall be returned to CW sump by gravity for
recirculation in the closed cycle CW system. Make up water shall be added in the CW
forebay of CW system.
Pump Details:
● 5 x 25% capacity CW pumps viz. 4 working and 1 standby.
● Pump rated Capacity : 22500TPH
● Pump Total Head : 26.85 MWC
● Temperature raise across Condenser : 9.4oC
● Pump rated Speed : 420 rpm
● No. of Stages/type of Impeller : One / Semi-Open
Motor Details:
● Rated Capacity : 2500 KW
● Rated Voltage : 11 KV
● Full Load Current : 164 Amp
● No Load Current : 60 Amp
● Full Load Efficiency : 95.50
● Vibration Level (Vel/Disp) : 2.3 mm/sec /37 microns
Trip interlocks:
CWP-A ON for 5sec and Discharge valve not Opened for 5sec
CWP-A Winding Temperature Very High
CWP-A Pump /Motor Bearing Temperature Very High
CWP-A Motor Bearing Vibration Very High
CWP-A Sump Level Very Low
CWP-A Standby AUTO Startup:
✔ CWP-A Standby Selected &
✔ any One of CWP is in ON position with 60 sec on time delay & CWPs
Discharge Header Pressure Low
(OR)
Any One of CWP Tripped
Auxiliary Cooling water (ACW)
Pumps:
ACW system takes suction from ACW sumps located in CW pump house and cooling
water shall be supplied to Plate Heat Exchangers and vacuum pump heat exchangers
by ACW Pumps. Self-Cleaning Strainers shall also be installed on the common
discharge line of ACW Pumps. The hot water return from ACW system shall join the
CW hot water return header downstream of Condenser.
Trip Interlocks:
o ACWP-A ON & ACWP-A Discharge valve Open Not more than 10%
o ACWP-A Motor Winding Temperature Very High
o ACWP-A Pump /Motor Bearing Temperature Very High
o ACWP-A Motor Bearing Vibration Very High
o ACWP-A Sump Level Very Low
SYSTEM
The CCW system takes care of the cooling water requirements of all the auxiliary
equipment such as Turbine & Generator auxiliaries (TG DMCW) and steam Generator
Auxiliary (SG DMCW) i.e Turbine Lube Oil /Control Oil Coolers, H2 and Seal Oil
Coolers, stator Winding water coolers ,BFP auxiliaries, CEP Bearings , all sample
coolers , Air Compressor auxiliaries, all Boiler auxiliaries coolers , etc.
The primary part of this CCW system is actually that utilizes DM Water as cooling
medium
The components of this system are:
● Redundant ACW pumps
● Plate –type Heat Exchangers
● Overhead expansion tank
TG DMCW PUMP
The extraction steam for the LP heater-4 is supplied steam from IP turbine exhaust.
Steam for the LP heaters nos. 1, 2 & 3 are extracted from various stages of the LP turbines.
During normal operation LPH-4 drain is cascaded to LPH-3. LPH-3 drain is fed
back into the main condensate cycle by 2x100% drip pumps after LPH-3. LPH-2A/2B
drains are led to drain cooler-2 and then drain cooler-1 and finally to condenser via flash
tank-B. Under high level conditions LPH-4 /LPH-3 and LPH- 2A/2B drains are directly
led to condenser via flash tank-B. No level is maintained in LPH-1A/1B. Its drain is
connected through a siphon to condenser via drain cooler-1 and flash tank-B.
Description Unit LP Heater-3 LP Heater-4
Steam entering Pressure ATA 2.71 5.12
Drain Entering Pressure ATA ~ 5.4 --
Condensate entering Pressure ATA 15.8 14.8
Condensate Leaving Pressure ATA ~ 14.8 ~ 13.8
Drain leaving Pressure ATA ~ 2.5 ~ 5.4
Steam entering Temperature oC 190.4 255.2
Drain Entering Temperature oC 131.7 NA
Condensate entering Temperature oC 80.0 127.0
Condensate Leaving Temperature oC 126.6 149.2
Drain leaving Temperature oC 129.6 131.7
Steam entering Quantity T/Hr 130.048 67.942
Drain Entering Quantity T/Hr 67.942 ---
Condensate entering Quantity T/Hr 1526.438 1724.427
Condensate Leaving Quantity T/Hr 1526.438 1724.427
Drain leaving Quantity T/Hr 197.989 67.942
No of tube passes/tubes provided No 2 / 1145 2/ 1145
Condensate velocity m/sec 1.65 1.87
Design tube Pressure ATG 47 & FV 47 & FV
Design Temperature (shell / Tube) oC 210/152 275/173
While the unit is heating up, check the Boiler expansion movements frequently &
Expansion movements should be recorded for comparison with future Startups.
Take 2nd set of ID & FD fans into service.
Maintain Storage Separator Tank (SST) Water level at normal set point via auto
Feed water flow control and check the Water concentrations and constituents as
frequently as necessary to maintain proper Boiler Water conditions. Sample
connections are located on the SST.
Chlorides λ Cation λ
pH Fe(ppb) Si(ppb)
(ppb) µS/cm µS/cm
<5 9.0 – 9.2 <5 <10 <10 <0.3
• Confirm the Steam conditions, pressure, temperature, and Steam purity, at the
Turbine are correct for Turbine roll.
• Wait for criteria full filling and Check the TSI parameters (expansions ,axial
shift, Bearing vibrations and shaft vibrations)
• After fulfilling the criteria, reset the turbine trip by reducing the TSLLDE
(starting device) to zero and observe the oil pressures. Check that the turbine
trip gear reset.
• Ensure the Hydrogen pressure in Generator casing is more than 4.7 Kg/cm2 (at
Full load condition the H2 pressure shall be maintained at 5kg/cm2)
and H2 purity is more than 96%. Charge all hydrogen coolers on DMCW side.
Check the primary water system and maintain the conductivities.
Open the STOP valves by increasing Starting Device about 35to36% and observe
the STOP valves opening. Check the TSI parameters. Observe the speed. Increase
the starting device up to 85% and above. Also observe the speeder Gear Position is
at 100%.
Set the speed ref. set point to 500 rpm and confirm the ramp. Observe the speed
raising and TSI parameters. Kept the turbine under soaking condition. Up to
fulfilling of next criteria’s and observe the differential expansion of HPT and IPT.
After getting rated speed criteria’s, observe the MS Pressure & HRH Pressure of
rated values. Raise the speed ref. to 2200 rpm and kept in to Hot Soaking.
Raise the speed ref. to 3000 rpm and observe TSI parameters at critical speeds.
Soak the turbine speed at 3000 rpm till IP shaft mean temperature with respect hot
reheat temperature as per the rolling X-curves is satisfied.
Close the Generator field breaker from AVR console.
Raise the AVR set point to build the Generator Voltage to about 27KV.
Match the auto and manual set point of the AVR and Transfer the AVR to auto
mode.
Ensure that load controller is on with load gradient kept at 40MW (5% of full
load) / Minute.
Check load reference set point more then40MW and less then55MW depending
up on main steam pressure.
Adjust the Voltage, so that in coming and running Voltages values are same.
Adjust the turbine speed so that synchronoscope is slowly rotating in clockwise
direction showing in coming frequency is slightly higher than gird.
Switch ON Auto synchronizer after two minutes Generator breaker closed.
Immediately raise the load with help of speed reference up to 40MW.
Close HP/LP Bypass valves.
Slowly change speed control mode to load control mode.
Close all the drains which were opened during rolling.
Check the generator slot core, exciter air and hydrogen cold
gas temperatures.
Check that pressure limiter valve slowly increase also ensure that load reference
set point is higher than the actual load valve.
Slowly increase Boiler firing with help mills and increase the load depending up
on main steam pressure
Raise the HP bypass pressure set point to about full load pressure plus 6 Kg bias
and temperature set point to about 340 oC to avoid HP bypass opening on auto.
| 106
WARM START-UP
Assuming that the unit has been down for a short period of time (less
than approximately 48 hours), the unit can be re-started in a similar
sequence to Cold Start-up procedure as outlined below:
1. Boiler separator metal temperature > (100 OC). and
2. Boiler pressure < (50 kg/cm2)
Warm start-up is carried out following the same procedure as for cold
start-ups. Refer to the section on cold start-up for details.
| 107
HOT STARTUP:
Assuming the unit has been down for a comparatively short period of time (< 8
Hours) following a normal unit shutdown and considerable steam pressure has been
maintained, use the following procedures to restart the unit:
Hot Startup conditions:
● Boiler Separator metal temperature >316oC
● Main steam pressure > 84 Kg/cm2
● Turbine requirements are met
Preparations & Lighting off:
Make a general inspection of the steam generator and check the points outlined in
the Preparations for Lighting Off for Cold Start Ups.
The BRP should still be in service.
lf the air heaters and fans were shut down at reduced temperature, start the air
heaters and fans. Increase the secondary air flow more than 890TPH.
Check all purge permissive are satisfied.
Purge the Boiler, after 9min. Boiler MFR gates reset. The first cause of Unit
Tripping gates reset.
Ensure de-aerator pressure is maintained at 3.5kg/cm² and Auxiliary steam
pressure is maintained at 16kg/cm².
Establish condenser vacuum 0.90kg/cm²
Open LDO Trip valve and HFO Trip valve after complete the Boiler purging.
Keep the wind box, CCOFA and SOFA dampers are in auto.
Light up the Boiler with ‘CD’ and ‘EF’ elevation oil guns.
Ensure that minimum stable fire is established in the Boiler.
Open wide all superheater drains to allow complete draining of superheater
headers and/or elements. After draining, close all drains except the superheater
back pass lower header drains and the start-up drains (main steam line vents and
drains). Keep the back pass header drains open until only steam is discharged. Keep
the start-up drains open. Reheater drains and vents are open and also Open the
following Turbine side drain valves. (As per requirement)
i. MS strainer drains to SDFT (MSV-109 & 110)
ii. CRH pot drain to SDFT (CRHV101)
iii. HRH strainer drains to SDFT (HRH-105&106)
iv. LP Bypass line drains (HRHV109&110)
v. LP Bypass warm up line drains (HRHV109&110)
vi. Open all drains of Turbine system except Mal-22 (HPT casing drain).
Mal-11,12,26,31,27,32,47,51,54,52,81,55,65.
Charging steam lines and commence warm up.
Set the HP and LP bypass control set-point to the existing pressure in auto
mode.
For hot start-ups, the fuel startup sequence should follow this table (A
elevation is the bottom elevation):
Seq. Elevation Notes
step
1 C warm up
2 D warm
up
3 C Coal If C Coal not available, Start D
Coal
4 D Coal If D Coal not available, Start E
Coal
5 E Coal
6 B Coal
7 A Coal
8 F Coal
9 G Coal
10 H Coal
Set warm-up (HFO Oil) flow control to auto and increase fuel flow set point to 5%
of BMCR firing rate, After a 5 minute stabilization period, progressively increase
firing rate to 10% BMCR. Increase separator pressure / temperature at the
desired rate.
When steam pressure at HP bypass begins to increase, the HP bypass valve is
released to "pressure ramp" mode. The valves will then control the boiler pressure
ramp-up to the required startup pressure [minimum 84 kg/cm2] or to existing
pressure if greater than 84 kg/cm2.
As the HP bypass opens, the Reheater will be pressurized as steam is passed
through the reheat vents and drains. Set the LP bypass station to minimum set
point in auto mode. The LP bypass will open in response to increasing reheat
pressure. Progressively throttle the reheat vents and drains to transfer flow and
pressure control to the LP bypass station. (Ensure LP Bypass system is functioning
on auto adjust the fixed set point to 12 kg/cm2)
HP Bypass valves can further be opened to assist in increasing steam parameters
(up to rolling parameters) if required mill can be taken into service.
Increase the firing rate, as prescribed, to raise the pressure and steam production.
The rate of pressure rise should follow the prescribed start-up curves.
When boiler pressure reaches the required startup pressure (minimum 84 kg/cm2)
(or existing pressure), the HP bypass valve is released to “pressure control” mode,
and maintains a constant pressure during turbine rolling, synchronization, and
initial loading.
When steam is admitted to roll the turbine, there should be a minimum steam-to-
turbine metal temperature differential. This can be achieved by raising boiler load
while on HP/LP bypass.
| 109
Turbine Rolling and
Synchronization:
• Confirm the steam conditions, pressure, temperature, and steam purity, at the
turbine are correct for turbine roll.
• Turbine can be rolled to rated speed either by ATRS rolling or manual rolling
through Electro Hydraulic Turbine Controller (EHTC).
● Raise the AVR set point to build the Generator Voltage to about 27KV.
● Match the auto and manual set point of the AVR and Transfer the AVR to auto
mode.
● Ensure that load controller is on with load gradient kept at 40MW (5% of full
load) / Minute.
● Check load reference set point more then40MW and less then55MW
depending up on main steam pressure.
● Adjust the Voltage, so that in coming and running Voltages values are same.
● Adjust the turbine speed so that synchronoscope is slowly rotating in
clockwise direction showing in coming frequency is slightly higher than gird.
● Switch ON Auto synchronizer after two minutes Generator breaker closed.
● Immediately raise the load with help of speed reference up to 40MW.
● Close HP/LP Bypass valves.
● Slowly change speed control mode to load control mode.
● Close all the drains which were opened during rolling.
● Check the generator slot core, exciter air and hydrogen cold gas
temperatures.
● Check that pressure limiter valve slowly increase also ensure that load
reference set point is higher than the actual load valve.
● Slowly increase Boiler firing with help mills and increase the load
depending up on main steam pressure.
Loading of Machine:
I. Charge the LP heaters at 7% load.
II. Raise the Unit load @ as per the ramp rate given, by cut in mills one by one.
III. Take 2nd PA fan into service and parallel with the 1st PA fan.
IV. Charge the HP heaters at 15% load.
V. Charge the De-aerator with IP extraction steam at 20% load.
VI. Raise the load 45% and observe change in evaporator temperatures from wet to
dry mode.
VII. Parallel 1st TDBFP with MDBFP at 45% load and raise the load further.
VIII. Parallel 2nd TDBFP-B with TDBFP-A at 70% load and Unload & stop
MDBFP-C.
IX. Raise the load to full load 800 MW and stabilize the parameters.
EMERGENCY PROCEDURES
1. Reheater Protection:
Stopping or significantly reducing steam flow through the reheater when the
entering flue gas temperature is above 1100 oF (593 oC) can cause overheating and damage
to the reheater tubing.
To prevent this condition, the following measures are taken with the automatic
reheat protection interlocks:
Turbine Valve Closure due to Grid Disconnection:
lf a loss of load should cause the turbine valves to close due to grid
disconnection, the turbine will be rundown to house load and the boiler should be
rundown to match the HP bypass capacity (60% BMCR or 65% TMCR at full
pressure).
Initially the SG is runback to 65% TMCR at a target rate of 50% per minute
at constant MS pressure = 242 bara. Simultaneously, the ST is runback to house
load. The bypass quick-opens and the balance of SG flow (65% TMCR less ST house
load) is transferred to the bypass.
SG Load is held at650/o TMCR for a stabilization period.
After stabilization, ST load is maintained at house load, while the balance of
SG flow is controlled by the bypass.
lf the HP bypass is not proven open within a short time delay, then all fuel
should be tripped automatically and instantaneously.
When a master fuel trip is caused by turbine control valve closure, an
immediate restart is feasible in most instances. lf an immediate turbine restart is
not possible and the turbine is tripped, the reheater drains should be opened.
Turbine Trip:
lf a loss of load occurs in which the turbine is tripped, then boiler should be
rundown to match the capacity of the HP bypass (60% BMCR or 65% TMCR at full
pressure).
Initially the SG is runback to 65% TMCR at a target rate of 50% per minute
at constant pressure MS pressure = 242 bara. The bypass quick- opens and the total
SG flow is transferred to the bypass.
SG is held at this condition for a stabilization period.
After stabilization, if desired the SG load and pressure can be reduced at a
controlled rate of<3% per minute within SG temperature gradient limitations and
within the bypass capacity limitation.
lf the HP bypass is not proven open within a short time delay, all fuel should
be tripped automatically and instantaneously.
The superheater and reheater safety valves will protect against
overpressure. The reheater drains to the condenser should be opened to evacuate
the steam in the reheater in the event of a unit trip.
Post-Trip Procedures:
The furnace must be purged immediately following a master fuel trip.
Empty any pulverizer containing coal as soon as possible.
To permit firing during start-up, the initiating fuel trip circuits associated
with the turbine must be disarmed before opening the turbine valves. They must
then be rearmed at a suitable point in the start-up sequence, such as when
synchronizing the turbine.
CAUTION:
Operators should be alert to detect the symptoms of water carry- over from
the boiler and introduction of water into the turbine, such as:
a. A sudden, unexplained drop in steam temperature in either the main
steam or hot reheat line.
b. Vibration in the steam piping resulting from water hammer.
c. Abnormal vibration and differential expansion readings from the
turbine supervisory instrumentation.
Operators must be prepared to take necessary steps to prevent turbine
damage upon detecting the introduction of water.
Turbine Protection upon Loss of Load:
Extreme care must be taken following a trip of the turbine and boiler to
prevent water from entering the turbine during a unit restart. Condensation may
cause water to collect in the main steam line(s) and cold reheat lines. Water may
be introduced into the superheater due to overflow from the separator (inadvertent
high water level). Water may be introduced into the superheater and/or reheater
through the de- superheaters due to open or leaking spray water control valves.
Inadvertent introduction of water into the steam lines must be prevented.
The lines must be drained prior to opening the turbine stop valves. When a master
fuel trip occurs automatically through normal interlocks, or is initiated manually
by an operator, all fuel shall be tripped instantaneously. If coal is being fired, the
pulverisers shall be tripped immediately. The master fuel trip will automatically
trip the feeders and close the hot air gates and close the cold air shutoff gates on
pulverisers that were in service at the time of the trip.lf warm-up fuel was being
fired, the fuel trip valves and individual nozzle shutoff valves should be closed
immediately.
The following steps should be taken immediately following an emergency fuel trip:
✔ If unit airflow is in excess of 30%, maintain unit airflow at the pre-trip value for at
least 1 minute and then gradually reduce the airflow to the purge rate (30% airflow)
and complete a unit post trip purge.
✔ If the master fuel trip was caused by a low airflow trip or if unit airflow less than
30% at the time of the trip, the unit airflow shall be maintained at the existing rate
for a 5 minute period and then gradually increased to the purge rate (30% airflow)
to complete a unit post trip purge.
✔ Procedure after Master Fuel Trip when all lD and FD Fans are off:
The ID and FD fans discharge dampers shall be opened to allow natural
ventilation of the unit. Opening of fan(s) dampers shall be timed or controlled to
avoid excessive furnace pressure excursions during fan(s) coast-down. The fans
discharge dampers shall remain open for a period of at least 15 minutes.
During this 15-minute period, the lD and FD fans shall not be started.
At the end of the 15-minute period, the lD/FD fans may be started in
accordance with ID/FD fan(s) start-up procedures.
If the unit will not be re-started for an extended time, a flow of air through
the unit shall be maintained.
✔ If warm-up fuel was in service when the fuel trip occurred, make sure the warm-up
header trip valve and individual nozzle shutoff valves are closed.
✔ If all auxiliaries are lost during a fuel trip, The cooling flow must be maintained for
the Boiler Circulating Pump.
✔ If pulverisers are in service when the fuel trip occurs, all operating pulverisers will
be automatically inverted. The pulverisers must remain under inverting until they
can be cleared of coal or cooled to ambient. After a boiler trip at a high pressure, a
controlled pressure reduction is carried out to the highest pressure with which a
restart is possible (to approximately 180 bar) to obtain reliable SST level indication.
✔ The BRP should be placed back in service and recirculation established to maintain
uniform temperatures throughout the boiler circulation system and to enable a
restart of the boiler. The boiler must be refilled to re- establish normal SST level for
BRP restart and the minimum recirculation flow must be re-established as a
prerequisite for re-firing. This process will naturally cause pressure to decay,
concurrent with the controlled pressure reduction.
✔ Check that the startup system is ready for operation and the drain transfer system
is ready for operation. Place the BFPMD in service, stabilize de- aerator conditions,
and establish feed water flow of 10% BMCR to the boiler to refill to normal SST
level. Follow the same procedure for boiler filling as outlined previously. When SST
level is stable with HWL-1 at stable opening and all BRP start permissive are
satisfied, start the BRP. Zero the feed water flow as SST level recovers and attains
the operational set point. lf restart of the BRP is delayed, excessive HWL action will
result in draining of water at pressure, oscillatory dump-feed action, with further
reduction in boiler pressure and extension of startup time.
✔ The pre-firing furnace purge can be initiated once all purge permissive are met.
✔ If the boiler can be immediately restarted, then raise load to >20 % on auxiliary
fuel utilizing the HP/LP bypass and successively clear the pulverisers using the
steam transport system as described below while the SG is operated on bypass
at>20% BMCR firing auxiliary fuel.
pulveriser clearing procedure instructions:
a. Close the pulveriser discharge gates on all other idle pulverisers containing
coal during each steam transport procedure. This prevents hot furnace gases
from being carried back into the
pulverisers in the event of a furnace pressure rise when a pulverizer is
started.
b. Start the lower elevation of warm-up fuel and establish the ignition energy
required to start a pulverizer.
c. lf RH flow has not been establish via the HP bypass or via turbine
synchronization, then reduce furnace exit gas temperature to 900- 950 deg
F (482-510oC) by adjusting warm-up fuel flow. before transport steam flow
is initiated.
d. Clear pulverizer A by following the pulverizer transport procedure located
in the steam inerting supplier's instructions.
e. Shut down pulverizer A.
f. Clear pulverizer B as per the same procedure.
g. Continue with normal unit start up sequence until both pulverisers are in
service and the turbine is synchronized.
h. When boiler load is approximately 20%, the remaining pulverisers may be
cleared one at a time using the steam transport procedure and returned to
normal service or shut down in a normal fashion if not required for load
regulation.
i. If the pulveriser will be retained in service, when the pulveriser has
completed the clearing process, open the hot air shutoff gate, bring the
pulveriser up to normal operating temperature and start the associated
feeder.
j. If the pulverizer will not be retained in service, stop it after completely
clearing the coal. The pulverizer discharge gates should remain open to
allow a flow of cooling air through the empty pulverizer.
✔ lf, due to load conditions and/or requirements to the Burner Management System,
it is impossible to establish ignition permissives to allow steam transport, inerting
steam shall be maintained until each pulverizer can be cleared of coal using steam
transport or cooled to ambient.
✔ lf the boiler cannot be re-started and the auxiliary steam source cannot be
continued indefinitely, then the pulverizers must be switched to an alternate steam
inerting source or to an alternate inerting medium until they can be cooled to
ambient and manually emptied.
| 120
lf all feed water pumps are tripped at any time, cooling of all boiler circuits will be
lost. All fuel must be automatically tripped with a maximum 20 second time delay.
Low Airflow:
lf airflow drops below 25% at any time, combustion conditions could become
dangerously unstable. All fuel shall be automatically tripped immediately.
Furnace Pressure High/Low:
lf furnace pressure exceeds the high-high or low-low set point at any
time, all fuel shall be automatically tripped immediately. A warning alarm is
generated at high and low set points.
Separator Storage Tank Level High:
lf the SST level exceeds the high-high level set point, then all fuel shall
be tripped immediately. A warning alarm is generated at high set point, at
which time the operator should check operation of the HWL valves, SST level
control, or the balance of feed water and firing rate (possible that firing rate
is too low for feed water flow).
Airheater Gas Outlet Temperature High:
lf the gas temperature leaving the airheater exceeds the high set point,
load must be automatically reduced to reduce the gas temperature. This is to
protect downstream equipment from over-temperature. The cause for the
excessive gas temperature should be investigated and corrected.
Both FD Fans Off or Both lD Fans Off:
lf at any time both FD or both ID fans are off while firing the boiler,
then all fuel shall be automatically tripped immediately.
Load Run-Backs:
Upon loss of the following equipment, load must be automatically reduced to a level
that can be supported by the remaining equipment. The load reduction is typically at a
target rate of 50% per minute (except for individual pulverizer trips). The reduction of fuel
input is accomplished by the equal decrease of coal feeder speed or by trippingthe of the
pulverizer(s) (for loss of PA fan or BFP).
One out of two FD fans.
One out of two LD fans.
One out of two PA Fans.
One out of two feed water pumps.
Any pulverizer(s) (depending on boiler load and number of pulverizers in service).
One out of two air heaters. Turbine
trip (as described above).
Disconnection from the electrical grid without turbine trip (as described above).
Run-Back Initiator Target Load Run-Back Rate
One PA Fan ON 50% 50% per minute
One FD Fan ON 50% 50% per minute
One ID Fan ON 50% 50% per minute
One Air Heater ON 50% 50% per minute
One TDBFP ON and One 75o/o or capacity of TDBFP + 50% per minute
MDNFP MDBFP
One TDBFP ON 50% or TDBFP capacity 50% per minute
One MDBFP ON 30% or MDBFP capacity 50% per minute
Main Turbine Trop 60% (within HP Bypass capacity) 50% per minute
100 596
90 596
70 596
60 596
| 128
2. PA/Furn. Pr DP
set point Vs Coal
Feeder Speed
X Y
0 635
25 635
100 945
6. OOS WB
Damper
position
Vs Load
X Y
0 0
25 0
50 0
60 10
70 15
80 16.5
90 17.5
100 18
110 18
10. SAFA
Demand
Vs main
WB Tilt
X Y
0 33.3
25 33.3
33.3 33.3
50 50
66.7 66.7
75 66.7
100 66.7
The combustion control system computes the amount of fuel and air required for the
furnace depending upon the load demand on the Boiler, which in turn is generated by the
CMC Loop. The CMC loop also generates Load signals for Turbine EHG- Electro hydro
Governor.
The unit load demand signal is based on the electrical load requirement from the Load
dispatch centre (LDC) or as decided by the Operator.
As the Electrical load on the generator Changes, the mechanical load on the coupled
turbine also changes. The turbine copes with these load changes by increasing or
decreasing the steam mass passing through it by modulating the steam inlet control
valves. The turbine inlet valves are closed to reduce the steam flow thru the turbine and
vice versa.
As the turbine inlet valves tend to close the instantaneous effect on the Boiler is an
increase in steam pressure at the Boiler outlet. The fuel input to the steam generator is
required to be reduced to adjust to the reduced requirement of steam. The dynamic
response of the steam generator to change in the steam quantity required is quite sluggish
due to the inherently slow chain of fuel preparation and fuel firing equipment. So till the
effect of reduction in firing rate takes place the Boiler will tend to produce an excessive
quantity of steam and its discharge pressure will tend to increase, since flow through the
Turbine is decreasing. This extra pressure is killed across the turbine inlet steam control
valve.
This will lead to the opening of the steam inlet valve to let more steam flow thru the
turbine. The boiler is not able to produce this extra steam, therefore the Steam pressure
at the Boiler outlet tends to fall. This sudden reduction of steam pressure in the steam
generator prompts an insanity expulsion of steam mass due to an increase in the specific
volume of the steam within the confines of the system. This provides a temporary load
increase even before the increase in fuel handling and the fuel firing system provides more
fuel to the Boiler. To provide more steam on a sustained basis, more fuel is to be fired into
the furnace.
A turbine can give the required load capability at varying steam pressure at its input
provided it gets the requisite steam mass having the required energy or enthalpy. The
steam can be delivered by Boiler at constant pressure or variable pressure. The important
point is to produce the steam at an optimum cost of fuel and at the same time with a quick
response of the boiler and turbine to the varying load conditions of the electrical grid to
which the turbine and generator are connected.
In the Sliding Pressure control mode of operation, the Combustion control system
operates in the manner that Boiler steam pressure varies in proportion to the steam
pressure required at the turbine inlet throttling valves
If the boiler main steam pressure is controlled in a manner that it follows the pressure
required at each turbine load, then this is called the “Pure sliding pressure” mode of
operation However when we speak of sliding Pressure, we often speak of “Modified
sliding Pressure operation” Mode of Operation. In the modified sliding Pressure
operation, the range of pressure control at the boiler outlet is limited. It lies between Pure
and constant pressure mode.
A unit operating at constant boiler steam pressure will have significant load reserve at any
reduced load due to significant capacity available at the Turbine input
throttling valve, but leads to lots of energy wastage as a throttling loss. A pure sliding
operation can not offer a dynamic load response. Therefore modified sliding pressure
mode is used for control.
To handle the rapid and continuous load ramping ( which is of great interest due to high
fuel cost), turbine temperature transients are minimized by operating in sliding pressure
mode
CMC control station provides flexibility to the operator to control the Boiler and
turbine in Manual or Coordinated mode depending upon the physical condition of the
Boiler and turbine auxiliaries and operational requirements of unit startup and
shutdown.
In manual mode, the Boiler input demand is manually generated by the operator. Main
Steam pressure is controlled by operating the steam turbine in by-pass mode during the
start-up.
In Coordinated Control Mode, the target load is dictated either by AUTOMATIC LOAD
DISPATCH SYSTEM (ADS) or set manually if ADS is not functional.
The target load signal is processed for minimum/maximum load limits which are
manually adjustable, and corrected for grid frequency variation before feeding to the
Ramp circuit for the generation of Unit load demand. DEFEAT SWITCH is provided to
the operator for introducing the frequency deviation. The Ramp circuit is provided with ‘
down directional blocking to regulate unit load demand during process disturbance.
TURBINE STRESS EVALUATOR ‘HOLD’ signal is interfaced for holding the rate of
integration and load changed rate limits to control load demand variation. In case of Unit
disturbance Run down / Run back conditions are generated and the unit load demand is
automatically reduced to the low limit as permitted by the Process.
The Unit load demand is fed to Boiler Master to generate Boiler demand i.e. Air & Fuel
requirement and to Turbine Control to set Turbine demand i.e. MW.
The Control System envisages the following modes of operation which are selectable
manually:
| 132
COORDINATED
MODE
In this mode both Boiler Master and Turbine Control are put in ‘Auto’ and unit load
demand is fed to both Boiler and Turbine to compute their load demands. The turbine
bypass valves act as pressure relief valves and are generally fully closed.
In this mode, the turbine takes the load and the boiler follows. It is adopted when turbine
control is Manual. The turbine sets the MW load and the boiler controls throttle pressure
as a follower.
In this mode, the boiler takes the lead and the turbine follows. The boiler input demand
is manually generated by the operator and the turbine governor system controls the main
steam pressure. It is automatically selected during the Run down / Runback situation.
MW is controlled by the boiler while throttle pressure is maintained by the turbine.
MANUAL MODE
In this mode, both the boiler master and turbine controller are switched over
to manual and the unit is controlled manually.
‘Run down’ is switched ON automatically when the Process error i.e. Feed water, Airflow
etc. becomes excessive and the control element goes to maximum position making the
process uncontrollable. Under the situation, Unit load demand is reduced to a value as
Permitted by the process to get over the blockage.
Similarly, ‘Run back’ is initiated automatically in the event of tripping of unit auxiliaries
ie. BFP, IDF etc. to match unit demand with reduced unit capacity.
‘Up/Down directional blockings’ are introduced whenever process error i.e. Feed water,
Airflow etc. becomes high or the associated control element goes to maximum position to
hold the unit load demand till such time the process
recovers. Under the generator circuit breaker OPEN and turbine trip, the unit is run under
house load operation.
Fixed or Variable Pressure modes of operation can be selected from the Pressure setter.
With Fixed Pressure operation, the set point can be fixed manually while with invariable
Pressure Operation, the steam flow signal representing the load index is programmed
through a function generator to generate Variable Pressure set point. The actual pressure
is measured by 3-redundant transmitters and the median value is taken as the Process
value. The pressure error is given to Boiler Master / Turbine Control as required by the
operation mode mentioned above.
• Coordinated Mode / Boiler follow mode / Turbine follow mode selection station
• Master control auto-manual station to select the load demand signal from the load
dispatch centre or to be set by the operator in a Coordinated mode of operation
• Boiler Master Auto-manual
setter
Steam Turbine Control functions include automatic startup and speed control,
synchronization, load control, frequency control and valve testing. The system
includes means to …
Override the normal valve position signal to prevent the valve from exceeding a limit
Speed Control
The system accelerates the turbine from the turning gear to synchronous speed. An
automatic time v/s speed program is provided to assure a safe and fast startup. In
addition, a rotor stress calculation program may be employed to ensure the turbine will
start up in the minimum time with minimum stress. The operator can adjust the speed
reference and acceleration through any workstation.
Depending upon the turbine design, the unit is synchronized. The speed is trimmed by the
system until speed and phase angle are matched with the line. Note that the median of
three-speed signals is used in the system.
Valve Management
The system provides individual control of all the steam admission valves (main throttle or
stop valves, control or governor valves and the intercept valves). Each valve has a different
purpose depending upon the mode of control. Sequential control of these valves during
startup, automatic load control and shutdown is performed automatically by the system.
Switching control modes is automatic and bump-less.
During startup, when controlling speed, the throttle valve (typically a bypass valve
built into one of the stop valves) controls the steam flow. Under these conditions the
control/governor valves are wide open, thus allowing steam admission to the entire
nozzle block. Depending upon the turbine design, transfer to sequential control
(control valves/governor valves) takes place before or after synchronization. At the
transfer point, the governor valves are closed in sequence and the throttle/stop bypass
valve continues to control steam flow. When the throttle bypass valve reaches its full
open limit, control is transferred to the control (governor) valves that then open in
sequence to increase speed or load. All throttle/stop valves are opened to their limit at
a controlled rate.
When reducing load, the reverse transfer occurs automatically at a preset load point. On
a rapid loss of load, the transfer will take place after the reheater has been unloaded.
Load Control
Load control is used after synchronization takes place and above a preset low load limit.
The system allows the operator to set the load reference in MW and the rate of change or
loading rate in MW per minute. The system will automatically control the governor valves
to increase the load in a linear fashion which duplicates the load demand curve as
established by the operator or the Automatic Dispatch System (ADS).
Note that the system employs the Unit Constraint Coordinator, which permits the
operator to set the loading rate at a level higher than most other systems.
Automation employs a unique approach that uses turbine first-stage pressure (P1), gross
generation (MW) and system frequency in a cascade control loop. This control loop
provides optimum performance, with or without a coordinated control system (CCS). It
makes maximum use of boiler-stored energy and linearizes the governor valves.
Frequency Correction
There are two elements to frequency control – the “natural” element provided by the
turbine control (governor) and the planned element provided by the Energy Management
System (EMS). The turbine control provides for natural frequency correction capability.
Frequency control capability is necessary for area-wide frequency control as well as
system-wide control. Without frequency correction, the network would not be stable.
Frequency correction is the change in steady state speed expressed in per cent of rated
speed when the power output of the turbine is gradually reduced from rated power to
zero power output. It can also be stated as the per cent speed (frequency) change that
results from a full opening or closing of the governor valves. Thus the greater the value of
per cent regulation, the less will be the sensitivity.
Per cent, correction is adjustable up to 10% with a nominal setting of 7%. Frequency
correction is used even when the unit is in coordinated control mode.
There are circumstances when it is necessary to control pressure with the governor’s
valves. This is normally referred to as turbine follow mode. In this mode, the valves
respond to the throttle pressure error by closing the valves to increase pressure and vice
versa.
Turbine follow mode is normally used when in an emergency condition and it is important
to immediately balance the boiler with the turbine.
If Turbine Base mode is available with the boiler control this can be initiated after boiler
turbine stability has been restored.
Turbine follow mode is automatically initiated when the throttle pressure drops below a
dangerously low limit. This is done to protect the turbine from water induction.
The turbine control system positions the steam admission valves by sending demand
signals to servomotors (servos) mounted on or near the hydraulic valve actuators.
Hydraulic fluid is controlled by the spring-loaded pistons of the servos. An I/O module,
called a “valve positioner”, provides an analogue output to the servo. Since most servos
have two coils, dual outputs are provided.
The “valve-positioner” also has the means to receive two valve position feedback signals
from LVDTs mounted on the valve. The positioning algorithm uses the greater of the two
signals. Since the LVDTs are nonlinear and vary with temperature, means are provided to
calibrate the LVDT periodically.
The Constraint Coordinator also monitors, in real time, the availability of plant
auxiliaries, such as fans, pumps, coal pulverizers, etc. It automatically adjusts the
maximum and minimum limits for load changes based on this availability.
The fundamental forms of energy with which thermal stations are principally
concerned are heat and work. Heat produces work and this work is further
converted into electrical energy by the Generator.
A thermal power plant uses a dual (vapour liquid) phase cycle. It's a closed
cycle to enable the working fluid (water) to be used again and again. The cycle used
is "The Rankine Cycle' which is the simplest theoretical vapour cycle and has an
efficiency of 29%.
Superheating the steam reduces the wetness of the steam at the final stage and
the efficiency of the cycle.
Reheating the steam after it has partially expanded, improves the thermal cycle
efficiency by 4 to 5%. Regenerative feed water heating by using Low pressure and
High-pressure heaters also improves the thermal cycle efficiency by 6 to 7%.