SETTING OUT
DEFINITION
▪ Is a process of marking of a building position, size and
shape in terrain.

June 2022 3
DEFINITION...
▪ This task is usually undertaken once the site has been
cleared of any debris or obstructions and any reduced
level excavation work is finished.
▪ It is usually the responsibility of the contractor to set out
the building(s) using the information provided by the
designer or architect.

June 2022 4
MATERIALS &TOOLS NEEDED
I. Wooden Peg
II. String for string lines
III. Timber for ledger
IV. Measuring tapes
V. Hammers
VI. Nails/nails
VII. Marking equipment
VIII. Calculators
IX. Water level
X. T- square
June 2022 5
STAGES IN SETTING OUT
I. Determining the reference point/Base line
▪ Baselines may be described as a straight line
whose terminal are fixed in relation to some other
detail. Baselines are found in a variety of forms.

June 2022 6
II. Location of building from a Baseline
▪ The first line of the building is set out from the baseline
of boundary pegs and the remainder of the building is
then set out from this tertiary baseline.

Step 1 Step 2

June 2022 7
▪ Turn into rectangle if possible

June 2022 8
III. ERECTING PROFILE BOARDS
▪ Profile Board is a board which is erected 0.9-1.2 m away
from the out side perimeter of the building.
▪ Are used as temporary guides to ensure the accurate
setting out and construction of the building.

June 2022 9
Types of profiles
1. Corner profiles: made of at least 3 pegs well driven in
to the ground on which two boards are nailed. These are
placed in each corner.

June 2022 10
2. Partition wall profile:- made of two pegs well driven
in to the ground to which a board is nailed and placed
where partition wall are situated.

June 2022 11
3. Continuous Profiles:- are made of many pegs well
driven in to the ground on which strong boards are
nailed. This is placed around the building.
▪ Mostly applied when the building is complex & for
architectural beauty.

June 2022 12
ERECTING PROFILE BOARDS…..
• Approximately Locate two corners of the building
which are parallel to the boundary/base line and
erect the two profile boards behind them.
• The boards must be set Parallel to the building lines
and a reasonable distance from them to allow access
for plant.
• level horizontal profiles, from the highest point of the
site first using a builder’s level.
• Should all be set to the same level if possible and
relative to FFL (Finished Floor Level)

June 2022 13
IV. LOCATING THE BUILDING CORNERS
▪ A string line is fastened between the two ledges of the profile
boards.
▪ The first and second corners of a the building is located along the
string lines and using the offset given from the boundary line.
▪ The other two corners will be located using 3-4-5 method.

June 2022 14
V. ERECTING THE OTHER PROFILE BOARDS
• The other profiles are located using the previously
located corner points and leveled to the highest ledger
using Automatic leveler or tube leveler.
• Finally internal and external boundaries of walls and
footings ate nailed on all ledges and strings are fastened
between them

June 2022 15
June 2022 16
June 2022 17
ANY
QUESTIONS??