Conditions Evaluation

Sr. Description Firm 1 Firm 2


1 Guarantee One Year No guarantee
offered but work
shall last 10 to 15
years as per
telephonic talk

2 Payment Condition 50% advance, 50% 30% along with


against proforma order, 50% at the
invoice time of stacking of
material and balance
after completion of
work immediately

3 Our Scope Firewood & Electricity, water,


Kerosene, firewood & staying
Accomodation for facility to their
workers, Unloading staff/workers shall
& Shifting goods at be provided By us at
site site. Scaffolding to
be provided if
required.

Financial Bid Evaluation

Sr. Description Firm 1 Firm 2


1 Over all fee of the work including
992,000 970,000
transportation
2 GST 178,560 174,600
Gross Total 1,170,560 1,144,600
Lowest L2 L1

Note: 1. We can operate fork lift with 1 ton load over this surface as claimed by both firms.
2. All rates net of discounts offered, if any.