The document evaluates two firms for a conditions project. Firm 1 offers a one year guarantee while Firm 2 claims work will last 10-15 years verbally. Firm 1 requires 50% advance and 50% on invoice, while Firm 2 requires 30% with order and balances after milestones. Firm 1 provides resources like fuel and housing, while Firm 2 expects the client to provide electricity, water, and housing. Financially, Firm 2 submitted the lowest bid of Rs. 970,000 plus Rs. 174,600 GST for a total of Rs. 1,144,600.
The document evaluates two firms for a conditions project. Firm 1 offers a one year guarantee while Firm 2 claims work will last 10-15 years verbally. Firm 1 requires 50% advance and 50% on invoice, while Firm 2 requires 30% with order and balances after milestones. Firm 1 provides resources like fuel and housing, while Firm 2 expects the client to provide electricity, water, and housing. Financially, Firm 2 submitted the lowest bid of Rs. 970,000 plus Rs. 174,600 GST for a total of Rs. 1,144,600.
The document evaluates two firms for a conditions project. Firm 1 offers a one year guarantee while Firm 2 claims work will last 10-15 years verbally. Firm 1 requires 50% advance and 50% on invoice, while Firm 2 requires 30% with order and balances after milestones. Firm 1 provides resources like fuel and housing, while Firm 2 expects the client to provide electricity, water, and housing. Financially, Firm 2 submitted the lowest bid of Rs. 970,000 plus Rs. 174,600 GST for a total of Rs. 1,144,600.
1 Guarantee One Year No guarantee offered but work shall last 10 to 15 years as per telephonic talk
2 Payment Condition 50% advance, 50% 30% along with
against proforma order, 50% at the invoice time of stacking of material and balance after completion of work immediately
3 Our Scope Firewood & Electricity, water,
Kerosene, firewood & staying Accomodation for facility to their workers, Unloading staff/workers shall & Shifting goods at be provided By us at site site. Scaffolding to be provided if required.
Financial Bid Evaluation
Sr. Description Firm 1 Firm 2
1 Over all fee of the work including 992,000 970,000 transportation 2 GST 178,560 174,600 Gross Total 1,170,560 1,144,600 Lowest L2 L1
Note: 1. We can operate fork lift with 1 ton load over this surface as claimed by both firms. 2. All rates net of discounts offered, if any.