Professional Documents
Culture Documents
Doc Ref
HCSB-MLNG-000-
JOB METHOD No
CVS-JMS-0001
STATEMENT
Page No 1 of 8
CLIENT : MLNG
CONTRACT NO : RFP-000000059466
A 09/11/23 IFR
Hadoumi Norma Ibrahim
Prepared Reviewed Approved Review Endorsed Approved
Rev Date Description
HCSB MLNG
MCHE-EXE-
Doc Ref
HCSB-MLNG-000-
JOB METHOD No
CVS-JMS-0001
STATEMENT
Page No 2 of 8
TABLE OF CONTENTS
2. SCOPE OF WORK 3
4. MAN POWER 4
9. PERMIT TO WORK 8
MCHE-EXE-
Doc Ref
HCSB-MLNG-000-
JOB METHOD No
CVS-JMS-0001
STATEMENT
Page No 3 of 8
1. INTRODUCTION
Based on scope of work, the MCHE Module 5 need to be decontamination, dismantling,
demolish and manage the scrap as per project direction. The MCHE currently located at
MLNG Car Park to be specific at Lot 39 Old MCHE Storage area.
2. SCOPE OF WORK
4. MANPOWER
No Position No of Pax
1 Construction Supt. 1
2 Site Safety Supervisor 1
3 Lifting Supervisor 1
4 Site Supervisor 1
5 Radiation Protection Officer 2
6 Work Leader (Dismantling & Demolition) 1
7 Work Leader (Cleaning) 1
8 Welder 2
9 Fitter 4
10 General Workers (Dismantling & Demolition) 13
11 General Workers (Cleaning) 5
12 Decontamination Technician 4
13 Rigger 4
14 Scaffolding Inspector 1
15 Scaffolders 6
TOTAL 47 PAX
a) All workers entering the worksite must be properly briefed on the rules and regulations
on the safety of working in the hazardous area.
b) Toolbox meeting shall be conducted prior to the start of any workday to ensure worker
are aware of the activity being carried out and safety requirement to execute the work.
c) HCSB to ensure that all PPE requirement are being adhered to.
d) The worksite must be clearly marked with suitable signboard to prevent any unauthorized
entry.
e) All personnel must observe strictly to the MLNG Safety regulation and occupational
safety, health and environment plan.
f) Precaution to be taken for lifting over live plant, field weld shall be strictly adhered to
PTW, JHA and relevant PTS.
a) Temporary laydown area shall be included perimeter hoarding, temporary bund wall,
temporary laydown cutting area, temporary covered TENORM decontamination area,
temporary scrap management area and workers shade with toilet and eye wash area.
b) The security personnel shall be provided at site gate to control the entry and exit of
personnel.
c) Lighting shall be provided during night hour.
8. WORK PROCEDURE
e) The concrete surfaces were levelled and finished with steel/wood trowels before
initial set took place.
f) Water shall be used to cure the concrete after 24 hours and formwork shall be
removed.
8.8. Housekeeping
a) Clean up the job site.
b) Prevent development of safety hazards.
c) All equipment and tools used must be removed after use.
d) Store tools, equipment, and unused materials properly at the end of working day.
9. PERMIT TO WORK
a) MLNG e-PTW system will be diligently adhered to appropriate e-PTW forms will be
submitted to MLNG for approval prior to commencement of work ad copy shall be made
accessible and visible at work site.
b) JMS/JHA will be review and approved by MLNG prior to start work.
c) Approved PTW and related document will be displayed at site where it can be easily seen
and checked.
d) E-PTW shall be returned to receiving authority (RA)/ Area Authority Representative (AAR)
at the end of the day on daily basis for revalidation.
e) After completing the job and finishing 7 days duration, e-PTW form will be signed off by
Receiving Authority/ Area Authority Representative and submitted to MLNG filed for
further reference.
f) Work Leader shall be fully responsible to handle copy of e-PTW and for monitoring
activities to comply with JHA requirements.