Stages in Construction

SUBSTRUCTURE SUPERSTRUCTURE

1 Site Work GROUND FLOOR


Excavation Raising columns Metalwork
Clearing and Evacuation Curing of Slab
Digging Column Pads and Metal Works Stone Walling above Slab
Concreting Column Pads Shuttering of Column Reinforcements
Laying of foundation Ring Beams Shuttering of Staircase
Concreting Foundation Beams Setting of Stairs DPM
2 Ground Floor Slab Setting of Staircase Reinforcement
Building of Foundation Walling and Retaining Walls Concreting Ground Columns
Filling of Hardcore Concreting Ground Staircase
Filling with Murram Shuttering for Slab
Rolling of Murram Shuttering for Beams
Laying of DPM Shuttering for Slab Floor
Setting of Slab Reinforcement Setting of Slab DPM
Rough Plumbing Installation Setting of Slab Reinforcement
Rough Electrical Installation Rough Plumbing Installation
Concreting Slab Rough Electrical Installation
3 Septic Tank Concreting First Floor Slab
Excavation of Septic Tank Curing First Floor Slab
Filling of Hardcore
Filling with Murram
Rolling of Murram
Laying of DPM
Setting of Septic Floor Slab Reinforcement
Stone Walling above Slab
Shuttering for Slab
Shuttering for Beams
Shuttering for Slab Floor
Setting of Slab DPM
Setting of Slab Reinforcement
Rough Plumbing Installation
Concreting Septic Roof Slab
Curing Septic Roof Slab
FIRST FLOOR INTERIOR FINISHES SECOND FLOOR
Raising columns Metalwork Setting of Window and Door Frames Raising columns Metalwork
Curing of Slab Plaster of Walls Curing of Slab
Stone Walling above Slab Plaster of Floors Stone Walling above Slab
Shuttering of Column Reinforcements Tiling Shuttering of Column Reinforcements
Shuttering of Staircase Plumbing and Fixtures Shuttering of Staircase
Setting of Stairs DPM Painting Setting of Stairs DPM
Setting of Staircase Reinforcement Countertops and Cabinets Installation Setting of Staircase Reinforcement
Concreting First Floor Columns Installation of Doors Concreting Second Floor Columns
Concreting First Floor Staircase Concreting Second Floor Staircase
Shuttering for Slab Shuttering for Slab
Shuttering for Beams Shuttering for Beams
Shuttering for Slab Floor Shuttering for Slab Floor
Setting of Slab DPM Setting of Slab DPM
Setting of Slab Reinforcement Setting of Slab Reinforcement
Rough Plumbing Installation Rough Plumbing Installation
Rough Electrical Installation Rough Electrical Installation
Concreting Second Floor Slab Concreting Third Floor Slab
Curing Second Floor Slab Curing Third Floor Slab
INTERIOR FINISHES THIRD FLOOR INTERIOR FINISHES
Setting of Window and Door Frames Raising columns Metalwork Setting of Window and Door Frames
Plaster of Walls Curing of Slab Plaster of Walls
Plaster of Floors Stone Walling above Slab Plaster of Floors
Tiling Shuttering of Column Reinforcements Tiling
Plumbing and Fixtures Shuttering of Staircase Plumbing and Fixtures
Painting Setting of Stairs DPM Painting
Countertops and Cabinets Installation Setting of Staircase Reinforcement Countertops and Cabinets Installation
Installation of Doors Concreting Third Floor Columns Installation of Doors
Concreting Third Floor Staircase FOURTH FLOOR
Shuttering for Slab Raising columns Metalwork
Shuttering for Beams Curing of Slab
Shuttering for Slab Floor Stone Walling above Slab
Setting of Slab DPM Shuttering of Column Reinforcements
Setting of Slab Reinforcement Setting of Stairs DPM
Rough Plumbing Installation Concreting Third Floor Columns
Rough Electrical Installation
Concreting Fourth Floor Slab
Curing Fourth Floor Slab
LANDSCAPING
Excavation
Rolling Pin Ground
Laying of Galana Tiles Walkway and Driveway
Planting of Vegetation