PROJECT:
Page 1 of 7
1 Introduction :
The design note below describes the details of calculations involved in design of Temporary Steel Bridge
to enable construction of Pier and launching of girders for Bridge near Pilibhit, Uttarakhand.
2.0 Scope :
Temporary steel Bridge shal be designed for the calculated crane load and the girder load.
Code of Practice.
Input Data
10.00 T/m2
0.400 m
Page 2 of 7
Properties of the section
SAFE
SAFE
4.00 t/m
2.00 m
B
A
Page 3 of 7
Bending moment, Shear force calculation
ISMB 300
SAFE
SAFE
Page 4 of 7
SAFE
20.00 t/m
2.00 m
B
A
ISMB 350
Page 5 of 7
4.3.2 Check for Bending stress
SAFE
SAFE
SAFE
SAFE
Page 6 of 7
4.7.2 Check for tension capacity
IS-800-2007
CL 10.3.5 Design tensile strength, Tdb = 0.9xFubxAn/γmb = 13.0 T
Factored tensile strength = 0.0 T
SAFE