CRCC 90-Day Look-Ahead for High Risk Activities - Rev 25

Contract Number: TAAPF 4800000241 Start Date: 29 January 2023 to 30 April 2023 Project: Spine Tunnel Access, Adit and Portal-C028 -Access Tunnel , Adit and Portal Formation

The construction management team and Foremen must evaluate the


Select most relevant Life Critical Requirement Planned Start Date Duration
# Activity Description Hazards Mitigation Physical Mitigation Documentation Area Contruction Managers activity and list any requirements prior to commencing works e.g. revise
(drop down list) (dd/mm/yy) (no. days)
RAMS, resource requirements, specific trainings for work crew etc.

ADIT 1, 2, 3, 4, 5 and 6

Area Managers:
● Operator and Jumbo drilling machine must be 3rd party certified each 6 months.
● Familiarization Training for Jumbo Rig Operators.
Li Bai (West)
● Serious injury to operatives in basket and working above the jumbo rig. Wan Chaojie (East)
● Wear appropraite PPE . ● Approved RAMS
● Equipment failure, operator failure,
● Must be provided manual handling training. ● Implementation of Pre-task briefing cards.
● Personnal contact/impact with machinery Adit Captains
● Only inspected hand tools should be used. ● Drilling safe work procedure must be in place ● TBT must be conducted
● Slip, trip and falls
● Provision of communcation system. ● ● Must be implement jumbo dilling machine daily inspection checklist A1: Wu Zhanping ● Exclusion zone must implimented and barricades provided
1 Drilling ● Risk of falling from height
Unauthorized people shall not be allowed in the barricaded area, MEPI and exclusion zones. ● Flood management must be in place
Barricades (Hard and Soft)
● Provsion of Appropriate Plugs, Sockets and Panels.
29 January 2023 90
● Vibration.
A2: Li Hailong
● Exclusion zones used so No personal will be allowed to go near to the jumbo drilling machine during drilling. ● Any mainatenance to be performed under LOTO system procedure A3: Sun HaoYan ● CRCC 12 life critical requirements
● Water flood
● Equipment and plants must be inspected by the user before use. ● Training record A4: Martin Hao
● Noise
● All operators must have received tool box talks on the job. A5: Yan Jindan
● Electric shock from hardwiring Jumbo into electrical source. .
● Must be provide dewatering pump to remove flood water and drilling water
● Compatible Panels and Plugs to be maintained and checked. LOTO procedure must be adhered to at all times.

● Risk of falling objects


● Equipment failure, operator failure,
● Unauthorized people shall not be allowed in the barricaded Restricted Zone.
● People in contact with machinery (MEPI)
● Must use tools with tools landyard, exclusion zones whilst drilling or below installations
● Slips, trips and Falls
● Operator and Jumbo drilling machine must be 3rd party certified ● Safe System of works for installation of Rockbolts, Spiles and Dowels. ● Competant crew should do this job, Swellex pump training,
● Risk of falling from height Li Bai (West)
2 Rockbolt Installation
● Noise
● No personal will be allowed to go near to the jumbo drilling machine during operation. ● safe work procedure training on operation of the jumbo drill, Swellex Barricades (Hard and Soft) ● Only use inspected and proper hand tools 29 January 2023 90
● Equipment and plant must be inspected by the user before use. pump and grout pump.
Wan Chaojie (East) ● Proper communcation system must be implemented
● Vibration
● Exclusion and Restricted Zone to be in place.
● Manual handling.
● Pressurised sytems (Swellex Pump)
● Electric Shock from Jumbo

● Wear appropraite PPE (N.B. PPE should be last resort)


● Grounting machine must be inspected by competent person
● Pressurized systems: Safety whip checks must be installed with pressure pipes, bleeder valves, etc.
● Health impacts from chemical reaction (skin issues, etc.),
● Only skilled/ competent person do this job ●PPE to be used at all times: dust mask, glasses, gloves, etc.
● Electric shock ●Provison of approved RAMS
● All cables and hoses must be installed properly Li Bai (West) ●Swellex and Grouting machine must be operate by competent person
3 Grouting ● High pressure systems ●Implementation of Pre task briefing cards. Defeating Safety Devices 29 January 2023 90
● Grouting machine area should be barricaded and need to be post safety signs Wan Chaojie (East) ●Implementation of exclusion zones
● Dust inhalation ● ●Provison of information, instruction, training and supervision
● Must be provide SDS sheet and need to communicate with relevant crew
Slips, Trips and Falls
● Must be provide cutoff switch for grounting machine, Pressurised system checeked as bled (empty of pressure) after each
use.

● Pretask card shall be obtained before starting the job


● Toolbox Talk shall be conducted before starting the job
● Collision of pedestrian with vehicle/ heavy equipment (MEPI)
● Exclusion and Restricted Zones shall be provided with proper signage ● Approved TMP
● Failure of equipment
● Operator shall follow the approved TMP/MEPI, Segregate the pedestrian route ● Approved RAMS
● Untrained Operator ● Need to implement excavation premit sysytem (RESS)
● Operator shall be trained and have valid documents ● Equipment all has valid documents
● Vibration, Noise. Li Bai (West) ● Provison of proper supervsion
4 Breaker Excavation
● Collapse of soil/rock (FoG Fall of Ground)
● Operator shall inspect their equipment prior to start the work on daily basis according to checklist ● Operators have valid documents Excavation & Trenching
● Make sure proper Exclusion and Restricted Zones.
29 January 2023 90
● Dust supression by water spray. ● Equipment Daily Inspection Checklist
Wan Chaojie (East)
● Excavated Material
● Rock cutting and excavation angle shall be maintained to control the face ● Excavation mapped and checked for SRG and RESS.
● Falling Material
● Excavated material shall be kept at close distance from the excavation to use as backfill contingency. ● Approved RESS must be provided
● Dust
● Look out on slope above, if applicable.
● SRG to determine the RESS controls.

● Operator & Shotcrete machine must be 3rd party certified


● Interface between people and shotcrete machine relocating and boom movement (MEPI).
● All activities have to be monitored by a competent supervisor
● Failure of equipment
● Must be wear appropriate PPE
● High pressure systems
● Exclusion and Restricted Zones . Never go under the unsupported ground
● Dust inhalation and Irritation and/or alkali burns to the skin
● Equipment and plant must be inspected by the user before use. ● Daily TBT shall be conducted along with Pre-Task ● TBT must be conducted
● Equipment or operator failure
● Hearing protection, air-fed helmets and eye wash stations must be provided . ● Must be provided SDS and need to communicate with relevant crew Li Bai (West) ● Conduct pre-task card
5 Shotcreting ● Incorrect manual handling/lifting of material
● Must be provided cover all and ERP for shotcrete crew. ● Approved RAMS
Barricades (Hard and Soft)
● Provison of appropriate PPE
29 January 2023 90
● Slip, trip and falls
Wan Chaojie (East)
● Competent supervision shall be provided ● Impelmentation of telehander daily checklist ● Adequate supervsion must be in placed
● Vibration, noise and dust
● Shortcrete testing required for early age strength, panel strength is best safety indicator
● Dehydration, heat stress,
● Exclusion zone to remain in place until panel strengths confirmed.
● Shotcrete fall out
● Telehandler and operator must be 3rd party approved
● Loading and unloading Chemicals for shotcrete
● Load must be secure during shifting from one place to other place by telehandler

● Unplanned Explosion
● Equipment shall be thoroughly inspected
● Flyrock/Air Overpressure.
● Third party inspection of machine shall be done and inspection tag to be displayed
● Failure of machine
● Exclusion (200m) and Restricted Zone (200m) to be in place: Shotfirer in total control all of the time
● Unauthorized Operator
● Shotfirer and authorised persons only to do post-blast inspection
● Unsupported ground ● Toolbox Talk shall be conducted before starting the job
● Ensure man-lift always placed on firm and levelled ground
● Toppling of Machine, ● Approved TMP ● Must be implemented blasting before & after checklist
● Every person will evacuate the tunnel after charging
● Struck by swing radius ● Approved RAMS and permits Li Bai (West) ● Appropriate PPE
6 Blasting ● Shotfirer and authorized persons to check the tunnel thoroughly before giving clearance next activity after blast Barricades (Hard and Soft) 29 January 2023 90
● Electrocution ● Implementation of blasting before / after checklist Wan Chaojie (East) ● Pretask card must be implemented
● Surrounding area warned by sounding siren and voice message via megaphones
● Poor cable management ● License and permit of shotfirer (Police)
● Electrical Detonator connected and handled by Blaster/shotfirer only, no phones/torches within 5m.
● Fall from height ● Explosive vehicle and driver documents, fire supression for tunnel.
● Explosion / shot Firing shall be carried by blaster/shotfirer only.
● Poor equipment (man-lift, etc.) maintenance and condition
● Must be followed misfire procedure and assign blasting engineer for each blast
● Noise
● Skip bins to be provided fro each site to dispose /burn the rubish from blating material and misfire mterial
● Vibration

# Level 3 - Bechtel Internal and Selected External Distribution


● Third party inspection of machine shall be done and inspection tag to be displayed
● Ensure heavy equipment operation area must barricaded and posted safety signs
● Unauthorized Operator
● Ensure that equipment operator conducted daily inspection prior to operate and maintain checklist.
● Personnel injury / plant equipment damage due to vehicle maneuvering (MEPI)
● Equipment regular maintenance must be done as per the schedule.
● Poor equipment maintenance and condition.
● Ensure pedestrian access and vehice route segregation and MEPI training must be condcuted ● Pre-task card shall be obtained before starting the job
● Fall of Ground/unsupported ground
● Operator should maintain adequate distance from equipment/vehicle ahead ● Toolbox Talk shall be conducted before starting the job
● Failure of machine
● Strictly follow safe truck loading and unloading procedure ● Approved TMP ● TBT must be conducted
● Equipment Collision Li Bai (West)
7 Mucking & Haulling
● Over loading of dump truck
● Max Speed limit of 20km/hr shall be maintained ● Approved RAMS and permits Barricades (Hard and Soft) ● Exclusion zone must provided 29 January 2023 90
● Ensure dumping operation must be done on level and compacted surface of ground ● Equipment to have valid documents
Wan Chaojie (East) ● Must wear Appropraite PPE
● Muck falling on road
● Must use appropraite PPE ● Operator to have valid documents
● Uneven ground
● Implemention of fire supression system in all diesel tunnel equipemnt and ABC Extinguisher in cabs. ● Daily Inspection Checklist
● Dust Inhalation. Fumes from deisel equipment
● Between the end of mucking and start of shorcreting the open face a Exclusion Zone should be maintained
● truck Fire
● Ventillation system should be adjusted during mucking operations to improve air quality
● Reversing and run away vehicles
● Suficient lighting shall be availabe during mucking activity (Lux 100), plus vehicle lights and task lighting.
● Install the Niches/turning places periodically and run away sand pits in front of transformers

● GMD need to be provided (wall mounted and hand held) ● Pre-task card shall be obtained before starting the job
● Ventillation system need to adjust as per the tunnel requirements ● Toolbox Talk shall be conducted before starting the job regarding
● Oxygen deficiency ● TBT must be conducted regarding Ventilation and air quality
● Must be assigned authorized gas testers ventilation and air quality Li Bai (West)
Ventillation and Air Qaulity ● Toxic gases build up
● Approved RAMS and permits
Confined Space Entry ● Must be maintained the GM record Info
● Unnecessary equipment/material must be keep out of the tunnel Wan Chaojie (East)
● Dust fumes ● Must wear Appropraite PPE
● Water spraying need to be done during mock out to contro dust ● Gas monitoring records to be maintained
● All diesel engines to be Cat IV engines and run on ULS Fuel

● Daily internal (checklist) and Third party inspection of machine shall be done and inspection tag to be displayed
● Inexperienced LAG installers.Unauthorized Operators of equipment and tools
● Exclusion Zone under unsupported ground and Restruicted Zone around lifting/plant.Barracades and signage
● Poor equipment maintenance and condition.
● Equipment regular maintenance must be done as schedule.
● Poor rigging techniques
● Ensure pedestrian access and vehice routes segregation and MEPI training must be condcuted
● Failure of machine ● Provison of approved RAMS
● Qualified / certified rigger be the only person to give signal to the rib erector / telehandler operator.
● Man Machine Interface ● Implementation of Pre task briefing cards.
● All rigging tools must be certified by Third Party with Safeworking loads (SWL) displayed on each tool / equipment ● Obtain Pretask briefing card
● Overload ● Arch installation safe work procedure must be in place Li Bai (West) To be determined
9 Lattice Arch Installaiton ● Weight of Lattice Girder shall be determined prior to any lifting to prevent from overload Barricades (Hard and Soft) ● Approved RAMS must communicated to the relevant crew
● Failure of lifting clamps ● Must be implement excavator and attachment device daily inspection Wan Chaojie (East) depending on RESS
● Lifting clamp must be inspected, tested and certified. SWL identified and displayed on it. ● Exclusion zones and safety signs must be provided
● Pinch points/ hand injury checklist
● Operators and working crew should maintain a firm footingon the platform floor at all times.
● Fall from height ● Lifting plan must on place
● No one will be allowed to sit or climb on midrail or handrail for any work
● Inappropraite PPE
● Ensure full body harness 100% tie off with manufacturer recommended secure substantial hooking point
● Falling Objects
● Must use approprate PPE
● Fire
● Welding activitin done by 3rd party certified welders under a hot work permit

BATCHING PLANT

● Unauthorized personnel must be kept away from the operations


● Ensure no metal body is in touch with any terminals and adequate fall protection for the de-assembled metal bodies.
● Electric Shock/ Electrocution
● Physical inspection around operating area is to be carried out with the general arrangement safety measure
● Exposed Energized Terminals
● Ensured dedicated Residual current devices (RCDs) are used to provide supplementary protection for the equipment.
● Fire ● Before starting the activity ensured that Pretask brieifing card briefing
● Operatives involved for operating activity, must aware the Lock-out/Tag-out (LOTO) system procedures. ● Obtain Pretask briefing card
● Chemical Burns done Li Bai (West) Done for Both Batching
10 Operation of the Batching Plant ● Physical separation should be provided to leads/connection terminals to avoid any contact with any live circuits LOTO (Lockout/Tagout) ● Apprvoed RAMS must be communicated to relevant crew
● Failure of testing kits ● Approved MS must be in place Wan Chaojie (East) Plant
● Ensured operatives adequately trained, experienced and knowledgeable to minimise risks. ● Lock out & Tag out system implemented by competent person
● Explosion ● CRCC approved LOTO procedure implementation
● Ensure the far end of electrical circuits are properly isolated, separated and barricaded.
● Fatality
● Exclusion zones and need to be provide safety signs
● Confined space hazards
● Only 3rd party certified crew allow to work inside confined space under a permit system.
● MEPI and Contact with moving parts of the machinery
● Provsion of approprate PPE

● Third party inspection of machine shall be done and inspection tag to be displayed.
● Certified operators with valid Saudi driving license, and approve 3rd party certificate and competency card.
● Unauthorized Operator ● Ensure crane set up area must be well compacted and tested. It shall be placed on firm and levelled ground area.
● Uncompact ground ● All outriggers fully extended with crane Outrigger pad of 400% bearing capacity.
● Crane toppling ● Ensure barricade around the swing radius of crane and sign posted to prevent people entry. ● Provison of approved RAMS
● Poor rigging techniques ● All rigging gears must be certified by Third Party. Rigger is responsible for inspection of all rigging gears prior to work. ● Implementation of Pre task briefing cards. ● Obtain Pre-task briefing card
Li Bai (West)
11 Lifting and Structure Erection ● Damage rigging tools ●Tools with broken /missing tags shall be removed immediately from the site. ● Steel Structure installation safe work procedure must be on place Barricades (Hard and Soft) ● Approved RAMS must communicate with relevant crew 29 January 2023 90
● Overload or unstable/unsymetrical load ● Weight of accessories shall be determined prior to any lifting to prevent from overload ● Must be implement manleft daily inspection checklist
Wan Chaojie (East) ● Exclusion zones and safety signs must be provided
● Fall of person from height ● Follow the EPM approved lifting plan as per manufacturer recommendation for silo erection. ● Lifting plan must on place
● Fall of material from height ● Man lift machine and operator must be 3rd party certified.
● Pinch points ● All persons who will work at height will have completed working at height training.
● Workforce and operator must necessarily wear double lanyard, full body shock absorbing harness & ensure 100% tie
off with manufacturer recommended secure substantial hooking point.

EAST CAMP

Ensure access routes are sufficient and safe to use.


Crane must be set up on firm, compacted and level ground, ensure pads under the crane outriggers.
Crane shall be certified by third party and display SWL, Crane operator certified with TUV card.
Imbalanced load
Ensure rigging accessories / tools must be certified and colour coded.
Crane failure
Only approved competent riggers are allowed to do the rigging job. Provison of approved RAMS
MEPI: Run over or hit by vehicles/plant Obtain Pretask briefing card
Tunnel Niches, Transfomer and Barricade the swing radius of crane and unloading area. Display signage for Restricted Zone/Open excavation. . Implementation of Pre task briefing cards. Li Bai (West)
12 Overhead obstructions Barricades (Hard and Soft) Approved RAMS must be communicated to relevant crew 29 January 2023 90
Pump Installation Do not take rest in or under vehicles Must be implement crane daily inspection checklist Wan Chaojie (East)
Musculoskeletal disorders Working area must be barriecded and safety signs must be provided
All vehicles must be fitted with reverse alarm / Flashing light. Traning record of the relevant crew
Hand injuries
The work place and all access to be well illuminated and enforce Speed limit
Cut & bruises
Ensure adherence with sufficient and appropriate PPE and Limit manual load carrying to 20 kg per person

Visual checks of all portable electrical equipment, switches, plugs & power leads.
Employee/workers training is provided to minimize exposure to these hazards.
Frequent intake of water and more break time of workers to allow body temperature to cool down.
Any hazardous waste materials or toxic dusts, gases resulting from cutting are under a Hot works permit.
Exposure to excessive; Noise, Dust, Vibration, Lighting
All ducted dust, fumes & vapor extraction systems are regularly maintained & cleaned
Electrical, Live Electrical Cable.
Fire watch and correct type of fire extinguishers are readily available in all workspaces & positioned near exit Pretask card shall be obtained before starting the job
Exposure to; Heat, Burns & Scalds, Friction, Obtain Pre-task briefing card
Installation of Cable trays and doorways. Toolbox Talk shall be conducted before starting the job Li Bai (West)
13 Defective and uninspected hand and portable electrical tools Barricades (Hard and Soft) Approved RAMS must communicate with relevant crew 29 January 2023 90
pipework Use tool lanyard for hand tools. Removal or protection of panels/equipment below the activity. Approved RAMS Wan Chaojie (East)
Combustible and flammable materials nearby. Working area must be barricaded and safety signs must be provided
Effectively maintain barricade.
Sparks from grinding and cutting operation.
Training and Supervision of personnel when using full body harness.
Sharp and pointed edges
Scaffolds and temporary platforms shall have inspection tag signed by a certified Scaffolding Inspector.
A-frame ladder inspected and tag. Use scaffolding instead of ladder when it is necessary and appropriate.
Clear safety glasses worn all the time when hand(s) is working above the head.

# Level 3 - Bechtel Internal and Selected External Distribution


Always ensure that the scaffolds used for cable pulling inspected and green tagged.
All involved crew are trained in Working at height.
Ensure use of approved types of ladders. Inspect, color coded the ladders before and after use.
Ensure ladder is set on stable and level surface. Follow three-point contacts while using ladder. ● FLHA (Field Level Hazard Analysis) shall be obtained before
Tug/Pull Out of cable drum, may struck from the reel of cable. Only one person on a ladder at a time. Use both hands when climbing & descending a ladder. Use hand line to Risk assessment should to be communicated to all concerned personnel
starting the job
Tripping hazards / move material or tools up a ladder. Li Bai (West) prior commencing the job.
14 Cable Pulling ● Toolbox Talk shall be conducted before starting the job Barricades (Hard and Soft) 29 January 2023 90
Manual Handling: Musculoskeletal disorders Do not carry anything while climbing ladder. Use gin wheel or other mechanical means for hoisting materials. Wan Chaojie (East) Approved RAMS must be communicated to the relevant crews
● Approved RAMS and permits
Back injuries for manual handling One worker should hold the ladder when someone working on the ladder. Working area must be barricaded and safety signs must be provided

Need to assign MEPI Champion for safe material loading and unloading
Driver must impelment daily vehicle checklist
Exclusion zone to be provided where the activity is occurring.
Area under compaction should be properly barricaded toavoid unauthorized entrance of people and vehicles.
Overfilling/overloading MEPI training to be conducted for crew engaged.
Provide adequate number of spill kits and granules and follow the SDS guidlines ● FLHA (Field Level Hazard Analysis) shall be obtained before
Mechanical failure
All plant and equipment mobilized will be fully compliant to N E O M - N P R - S O P - 0 3 6 Rev 0 2, Dec2020 starting the job Risk assessment should to be communicated to all concerned personnel
Burn Injury
All waste to be segregated on site and it must be broughtback to the appropriate waste containers or skips. ● Toolbox Talk shall be conducted before starting the job Li Bai (West) prior commencing the job.
15 Asphalt Work Consumption of diesel and hazardous substances Excavation & Trenching 29 January 2023 90
Proper & safe access should be provided for transportationand on roads for any potential movement of loose ● Approved TMP Wan Chaojie (East) Approved RAMS must be communicated to relevant crews
Waste collection and Waste generation
materialmust be set properly. ● Approved RAMS and permits Working area must be barricaded and safety signs must be provided
Driver loss the control of the vehicle, Traffic management
Equipment over turning. Reduce speed where conditions warrant, such as on curves, at night, in congested areas, steep grades and wet or
foggy conditions.

Obtain permit to dig FLHA (Field Level Hazard Analysis) shall be obtained before
Damage property /Plant Undergound Utilities drawings must be provide before excavation, check if original workers still on project. starting the job Risk assessment should to be communicated to all concerned personnel
Services Excavation and Electrical hazards Underground utilities need to scan by Cat scanner Toolbox Talk shall be conducted before starting the job Li Bai (West) prior commencing the job.
16 Trial hole should be dug. Excavation & Trenching 29 January 2023
installation Fuel and Gas lines Manual digging must be provide to relevant crew Wan Chaojie (East) Approved RAMS must communicated to relevant crews
Failure of excavation Manual digging with insulated tools Approved RAMS must be communicated with crew Working area must be barricaded and safety signs must be provided
Confined Space
• Competent person to inspect location and load path assessment before lifting equipment operations. FLHA (Field Level Hazard Analysis) shall be obtained before
• Adhere to lifting equipment manufacturer recommendation. starting the job Risk assessment should to be communicated to all concerned personnel
Loading & Unloding Material Unstable load, over load, etc.Lifting equipment tipping over. • Availability of load chart. Load chart is available inside/outside operator’s cab. Toolbox Talk shall be conducted before starting the job Li Bai (West) prior commencing the job.
17 • Pre-start tele handler checklist must be filled by operator and crossed checked by HS supervisor at start of each Lifting Operations 29 January 2023 90
with lifting equipment Material falling or dropped. MEPI traning must be provide to relevant crew Wan Chaojie (East) Approved RAMS must communicated to relevant crews
Load / counterweight /boom hitting construction personnel and/or nearby structures. shift. Approved risk assessment must be communicated with crew Restricted Zone must be barricaded and safety signs must be provided
• Operator shall ensure that lifting equipment will be positioned on a stable, properly compacted soil/ ground
capable to withstand the weight of the load.
• Competent person inspection of location and load path assessment before lifting equipment operations.
• Adhere to lifting equipment manufacturer recommendation.
• Availability of load chart. Load chart is available inside/outside operator’s cab.
• Pre-start tele-handler shift checklist must be filled by operator and crossed checked by HS supervisor.
• Operator shall ensure that lifting equipment will be positioned on a stable, properly compacted soil/ ground
capable to withstand the weight of the load.
• Outrigger shall be fully extended positioned on stable ground. FLHA (Field Level Hazard Analysis) shall be obtained before
• Must be provide MEPI (Mobile Equipment Personal Interface) training to relevant team. starting the job Risk assessment should to be communicated to all concerned personnel
Demobilisation and Adit Lifting equipment tipping over. • Restricted Zone must be maintained in thelifting area as deemed suitable by site supervisor. Toolbox Talk shall be conducted before starting the job Li Bai (West) prior commencing the job.
18 Lifting Operations 07 February 2023 90
Handover Material falling or dropped. • Load shall never be lifted over the operatives or walkways. No one to go under a suspended load. MEPI traning must be provide to relevant crew Wan Chaojie (East) Approved RAMS must communicated to relevant crews
Load / counterweight /boom hitting construction personnel and/or nearby structures. •All lifts to be planned and supervised by competent people before lifting operations commence. Approved risk assessment must be communicated with crew Working area must be barricaded and safety signs must be provided
• Operatives to be warned before loads are to be moved.
• Material to be check by competent person to be safe to be moved/ lifted with the load from ground level to
check that materials are secure, stable and the lifting points are in good condition.
• When loading and unloading materials, if it is deemed unstable, the load will be put back down and a safer way
of moving it will be discussed with management and only be moved when it is approved.
• Only operatives involved in the loading and unloading operations will be allowed in the area.
• Unsafe load or lifting gear will be quarantined in a staging area

# Level 3 - Bechtel Internal and Selected External Distribution