Tasks Start Date days to complete

Project background 5-Apr-22 7


Literature Review 12-Apr-22 8 GANTT CHART
Performing Tutorial Tasks 20-Apr-22 12
5-Apr-22 5-May-22 4-Jun-22 4-Jul-22 3-Aug
Understand IOT and ESP32 01-May-22 20
Hardware Implementation Project background
22-May-22 70
Project testing phase 1 Literature Review
1-Aug-22 15
Performing
Creating a graphical user interface (GUI) fo Tutorial Tasks
17-Aug-22 40
Mobile Application desgining Understand IOT and 2-Oct-22
ESP32 35
mobile application testing phase Hardware Implementation
15-Nov-22 8
final project testing Project testing phase 1
24-Nov-22 6
Creating a graphical user interface
(GUI) for app
Mobile Application desgining
mobile application testing phase
final project testing
GANTT CHART
un-22 4-Jul-22 3-Aug-22 2-Sep-22 2-Oct-22 1-Nov-22 1-Dec-22
task start dates end dates
Project background 5-Apr-22
Literature Review 7-Apr-22
Performing Tutorial Tasks 15-Apr-22
Understand IOT and ESP8266 27-Apr-22
Hardware Implementation 17-May-22
Project testing phase 1 25-Jul-22
Creating a graphical user interface (GUI) for app 10-Aug-22
Mobile Application desgining 10-Oct-22
testing phase 2 27-Oct-22
final testing phase 3 5-Nov-22