(MOC/DOB/BP/F-10)

DEPARTMENT OF BRIDGE
WELL CASSION CONSTRUCTION INSPECTION CHECK LIST
INSPECTION CHECK LIST FOR WELL CASSION

PROJECT NAME: BRIDGE NO (1/54) CONSTRUCTION (80ft)


PROJECT TEAM: BRIDGE CONSTRUCTION SPECIAL UNIT (14)
PROJECT LOCATION: HTI LONE-TAR BAUNG-PATA-NABU-KAWKAREIK ROAD (84.5 KM-85.5 KM)
CONTRACTOR NAME: BRIDGE CONSTRUCTION SPECIAL UNIT (14)
PIER/ABUTMENT No. : A2 PILE No. : Cassion (U/S) DATE:

Design Construction Difference


Excavation Depth 8m m m
Pile Length 8m m m
Pile Diameter 2.4 m m m
Top of Rebar TP- m TP- m m
Top of Concrete TP- m TP- m m
Quantity of Concrete m 3
m 3
m3
Result
Check Item
Result Criteria
1. Pile center position <100mm
Pile Position 2.Inclination <1/100
3.Offset Point >4
4.Earth strength >0.1-0.2N/mm2
Machinery 5.Position Planning
6.Bit Adequate for diameter, Soil condition
>Larger than designed diameter by 150-
7.Diameter
200mm
Stand Pipe 8.Length <Buried to mad by 0.5m
<100mm (Center)
9.Position
<1/100 (Inclination)
10.Time Compare with test Pile
11.Drilling torque Compare with test Pile
12.Drilling Integrating galvanometer Compare with test Pile
Excavation 13.Support layar depth Cpmpare with Design
Cpompare with design Measure at least
14.Excavation Depth 8m
4point
15.Embedment to support layer >1.5D
CHECKED BY: APPROVED BY:

ဒစာသန်ြားဒဖေါင်
အငယ်တန်ြားအင်ဂျင်နယာ(၁)(မမ ြို့ ပြ)
တံတာြားအ ြားအဖြို့ (၁၄) ဥကကာဟန်ြား ဒ ေါ် ခိုငသ
် ဉ္ဇာဒေ ဒေမဖ ြား
ဦြားစြားအ ာရ (မမ ြို့ ပြ) လက်ဒ ာက်ညွှန်ကကာြားဒ ြားမြား(မမ ြို့ ပြ) တ
ို ယညွှန်ကကာြားဒ ြားမြား(မမ ြို့ ပြ)
တံတာြားအ ြားအဖြို့ (၁၄) တံတာြားအ ြားအဖြို့ (၁၄) တံတာြားအ ြားအဖြို့ (၁၄)
တံတာြားအ ြားအဖြို့ ၁၄ တံတာြားအ ြားအဖြို့ (၁၄)

(MOC/DOB/BP/F-10)

DEPARTMENT OF BRIDGE
BORED PILE CONSTRUCTION INSPECTION CHECK LIST
INSPECTION CHECK LIST FOR BORED PILE
PROJECT NAME: BRIDGE NO (1/54) CONSTRUCTION (80ft)
PROJECT TEAM: BRIDGE CONSTRUCTION SPECIAL UNIT (14)
PROJECT LOCATION: HTI LONE-TAR BAUNG-PATA-NABU-KAWKAREIK ROAD (84.5 KM-85.5 KM)
CONTRACTOR NAME: BRIDGE CONSTRUCTION SPECIAL UNIT (14)
PIER/ABUTMENT No. : PILE No. : DATE:
Adequate to soil condition 4 times by
16.Viscosity
one pile construction
Bentonite quanlity
Adequate to soil condition 4 times by
17.Specific gravity
one pile construction
Before
Primary bottom 18.Measuring deposition
After
Processing
19. Waiting time after excavation 20-30 minutes
20. Rebar cage length >Desigine length
Size
Number
21. Rebar cage Aligement Compare Design
Reinforcement
Spacer
work
Support
22.Inclination during placement <1/100
23.Preparation for pile head
Design
treatment
Secondary Before
24.Measuring deposition
bottom processing After

25.W/C <55%
26.Slump 120mm 180-210mm
Concrete quality 27.Strength 3500 psi 30N/mm2
28.Air Content 4.5% ± 1.5%
29.Chloride content 0.3kg/m3
30.Tremie length Buried to concrete more than 2m
31.Time duration
Concrete work
32.Quantity of concrete
33.Excess concrete About 0.8 – 1.0 m
CHECKED BY: APPROVEDE BY: