PROJECT TITLE
ACTIVITY : PILECAP
Site supervisor has to ensure that the soil around the side of piles has to be cleared out manually by
general workers using the hoe.
b) Cut off level Transfers the TBM provided by Main Con. to the side of each R.C. piles by using levelling instrument.
Cutting off pile is done by a gang of concretor (i.e. 4 workers per gang) using the two concrete breakers
connect to a compressor machine. Production rate is about 16 numbers of piles cut off per day.
Pile starter bars lapping should refer to the drawing specification.
c) Lapping Pile starter bar lapping should refer to the drawing specification.
2. Lean Concrete Site supervisors check the level by using levelling instrument.
Site supervisors check the pile caps width to ensure pile caps base are fully covered by the lean
concrete before the installation of formwork.
Grade 15 concrete shall be used and by hoisting method using 25 tons mobile crane and concrete
chute .
3. Installing Formwork Site supervisor transfers all the gridline points from the reference points given by the licensed surveyor to
the timber reference pegs according to the construction drawing.
Formwork shall be installed according to the transferred gridline.
Go through Reinforced Concrete Inspection Form Checklist, Item (1) Formwork (as per attached) to
ensure compliance with QA/QC requirement. Site supervisors check the verticality of formwork by using
method of spirit level.
Site supervisor ensure the formwork strutting and bracing are adequate in order to ovoid the leakage of the
mortar.
5
COMPANY NAME Safe Work Method Statement
PROJECT TITLE
ACTIVITY : PILECAP
4. Installing Rebar Site supervisors check the Mill certificate from the supplier the material delivery to site and cover with
canvas.
Prefabricate of pile cap steel rebar cages and column stumps steel bar according to the construction
drawing.
Lower down the steel cages by hoisting using mobile crane into the formwork according to the
construction drawing.
Site supervisors ensure that the rebar are to be free from dirt and rust.
5 Concreting Go through Reinforced Concrete Inspection Form Checklist, Item (3) Concreting (as per attached) to
ensure compliance with QA/QC requirement.
Ready Mix Concrete shall be used according to the Specification which is approved by Consultant
Engineer.
Site supervisors check for dispatch time to ensure concrete from the concrete truck can be placed within
45 minutes.
Concreting is done by hoisting method using 25 tons mobile crane and concrete chute (size = 0.35 m ³) or
using the concrete pump truck.
Site supervisor checks that concrete slump is 100mm ± 25mm for normal mix or 125mm ± 25mm for
pump mix in compliance with the approved Trial Mix design witnessed by Clerk of Works.
Poker Vibrators to be carry out by skilled concretor to ensure proper compaction.
Site supervisors check for any cracks or honeycombs of the concrete. If any, then apply for approval of
the method of rectification.
6
COMPANY NAME Safe Work Method Statement
PROJECT TITLE
ACTIVITY : PILECAP
8 Backfilling Site supervisors has to ensure that the unsuitable materials (e.g. waste timber, rubbish, cut off piles etc.)
cannot be backfilled.
Site supervisor has to check the backfill is done to pile cap surface level by the excavator. (i.e. Hitachi EX
200)
Site supervisor has to check the backfilling works near to the pile cap shall be done manually by
manpower using hoe.