Professional Documents
Culture Documents
Section 15130 Pump Rev 0
Section 15130 Pump Rev 0
~I
0
w1..;..~JjW.l1\w~\ ..Y"'"
--'I
SECTION 15130:
KINGDOM
OFSAUDIARABIA ~~~I ~1
4I.j-1J1
RoyalCommissionfor Jubail & Yanbu (W.1 ~ ~I d4tJ1
SECTION 15130
PUMPS
TABLE OF CONTENTS
PART 1 GENERAL............................................................................................................ 1
1.05 REFERENCES..................................................................................................... 2
1.07 SUBMITTALS....................................................................................................... 4
3.05 INSTALLATION.................................................................................................. 17
3.10 TESTING............................................................................................................ 26
PART 1 GENERAL
B. Read this Section in close conjunction with SECTIONS 15051 and 15055.
A. Selection, furnishing, installation, testing and bringing systems into full satisfactory
operational conditions of pump.
B. The Contractor shall furnish all labor, materials, tools and equipment required to
make the work complete and ready.
C. The Contractor shall provide all temporary power supply, services, storage tanks, fill
and refill mediums, disposable strainers, chemicals, fuels and all whatever other
materials required for testing, commissioning and start ups.
1.05 REFERENCES
A. The referred codes and standards are intended to provide an acceptable level of
quality for materials, products and workmanship. In case of conflict between these
standards and the text of this Specification, the Specification text shall govern.
B. The latest revision of the referred codes and standards shall be used wherever
applicable. In case of conflict, the Contractor shall propose equipment, materials and
processes conforming to one group of codes and standards.
F. HI Hydraulic Institute
B. Abbreviations
1.07 SUBMITTALS
A. The Contractor shall submit to the Royal Commission, under the provisions of
SECTION 01330, the following items for review and approval before commencing
Work:
2. Product Data
c) Electrical characteristics.
d) Electrical Parameters
1) Pump speed in rpm.
2) Motor horsepower.
3) Motor frame size.
4) Service factor.
g) Pump Efficiency.
b) Lubrication instructions.
5. Shop Drawings
6. Millwright's Certificate
a) Certify that base mounted pumps (where applicable) have been aligned.
A. The Contractor shall be responsible for the quality of work and shall develop and
propose programs and methods of construction and testing such as to achieve the
specified quality to the approval of the Royal Commission in accordance with
SECTION 01450.
B. Quality Assurance
1. The manufacturer shall submit certificate including test data to show that pump
meets performance specifications.
2. Alignment
3. Contractor
B. In the absence of any of the above, best accepted industry practice shall be
employed throughout.
B. Fire pump fabrication, installation and testing shall be in conformance with NFPA 20.
1. General
e) Flooded Suction
1) When the liquid source is above the pump centerline, a flooded
suction condition exists, and a gate valve is required to shut off
the liquid supply for pump inspection and maintenance.
3. Discharge Piping
a) Discharge piping shall also be short and direct as possible, with few
elbows and fittings, to reduce head loss from friction.
b) If the piping is long, pipe diameter shall be one or two sizes larger than
the discharge opening.
c) Avoid high spots, such as loops, which will collect air and throttle the
system or lead to erratic pumping.
4. Valves
a) General
1) Valves are an important part of the installation, for they facilitate
priming of the pump, and control the volume of the pumped liquid.
5. Elbows
d) Suction piping for horizontal double suction pumps shall not be installed
with an elbow close to the suction flange of the pump except when the
suction elbow is in the vertical plane.
e) For double suction pumps, the last pipe elbow in the suction line to the
pump shall be perpendicular (not in the same plane) to the impeller
shaft.
a) Screen the suction piping to remove foreign matter that can clog the
pump and impair its capacity, or stop it completely. Small particles such
as sand, dirt, scale from inside pipe and other extraneous materials can
get into the close clearance parts of the pump and cause considerable
damage to the parts.
c) In applications where sticks, twigs, leaves and other large debris are
present, a larger outside screen shall be placed around the suction inlet
to prevent choking of the strainer.
d) This screen shall have sufficient openings so that flow velocity shall not
be less than 0.61m/s (2 ft/s).
8. Flexible Piping
9. Expansion Joints
b) The air pockets are a result of high points and improper installation of
elbows, reducers and valves in the suction piping.
c) Excessive air can also prevent proper pump packing lubrication with
resultant damage to them.
c) Where 2 or more pumps are connected to the same suction line, install
gate valves so that any pump can be isolated from the line.
2. The selection of pump type and pump drive shall be based on each specific
application requirements.
3. When selecting pumps, the availability of spare parts and the satisfactory
operation of identical pumps already in service shall be taken into account in
the final selection.
6. Horizontal pumps are preferred and shall be used unless suction conditions or
space limitations prohibit their application.
a) Sump service.
a) Temperature range.
b) PH limitation.
B. Pump Construction
C. Energy Evaluations
2. Selection of pumps and drivers shall take into consideration cost of energy.
D. Hydraulic Performance
2. Pump shall be such that it provides stable operation for the pump when
operating at any point on the curve.
3. Select pump operating point, to the left (shut-off) side of the characteristic
performance curve and lies on the maximum efficiency point, or not more than
5% below maximum.
4. Systems having considerable throttling shall have the pump selected on the
flat portion of the Head versus Flow Curve.
5. Select centrifugal pump for the calculated pump head without the addition of
safety factors.
6. Pumps that require NSPH operation shall be carefully evaluated and tested
before purchase.
E. Pump Drivers
2. Use variable frequency drive (VFD) for HVAC, plumbing and other pump
applications where flow and pressure modulation are required, and motors are
larger than 5 hp (3.73 KW).
2. Ensure that sufficient Net Positive Suction Head (NPSH) at pump suction is
provided.
3. Available NPSH shall always be equal or exceed the required NPSH of the
pump.
B. Pumps which require removal from the system piping for servicing the impeller are
unacceptable.
C. Allow sufficient space to be able to dismantle pump without disturbing the piping
system.
E. A clear space with ample headroom shall be allowed for the use of an overhead
crane or hoist sufficiently strong to lift the unit.
A. The Contractor shall deliver, handle and store equipment and materials units in
accordance with SECTIONS 01650 and 01660, as well as the following
requirements:
1. Receiving Pump
4. If the pump is not to be installed and operated soon after arrival, store it in a
clean, dry place having slow, moderate changes in ambient temperature.
5. Rotate the shaft periodically to coat the bearings with lubricant and to retard
oxidation, corrosion, and to reduce the possibility of false brinelling of the
bearings.
6. When unloading horizontal pumps, lift equally at 4 or more points on the base
plate.
8. For vertical pumps, use the lifting lugs or eyebolts found on the pump.
10. Be very careful not to damage any auxiliary piping or controls when moving
pumps.
11. Comply with ANSI/HI 1.4. Requirements for unloading, receiving and
inspection.
PART 2 PRODUCTS
2.01 GENERAL
A. All goods and products covered by these Specifications shall be procured, when
available, from an in-Kingdom manufacturer. Procurement of all goods and products
manufactured out-of-Kingdom must be approved by the Royal Commission.
C. Specific material selection shall rely on specific project, condition and application.
2.02 TECHNICAL
A. Pump Capacity
2.03 MATERIALS
1. Gray iron casting conforming to ASTM A48M or A278. Class of castings shall
be as specified in the documents.
C. Wearing Rings
D. Impeller and impeller seal ring shall be made of any one of the following material:
1. Provide cast iron impellers on pumps for closed loop systems, such as hot
water heating, chilled water, hot or cold glycol, unless otherwise indicated.
2. Provide bronze impellers on pumps for open loop systems such as domestic
hot water, domestic cold water, well water, condensing water or condensate,
unless otherwise indicated.
F. Coupling
G. Bearings
2. Select for 2 years minimum service life at maximum load condition or, rated for
minimum life of 10 000 hour, whichever is greater.
H. Mechanical Seal
I. Base plate
1. Full base.
J. All other pump parts shall be made from material compatible with pump's basic
material and suitable for the liquid being pumped.
K. Tubing and pipe shall conform to ASTM A53M or A120, and in any case, shall be
suitable for the service under consideration.
M. Motor
3. Quiet operating.
4. Motor shall be totally enclosed fan cooled where installed outdoors exposed to
the weather.
5. When the impeller supplied with the pump is smaller than the maximum sized
impeller that the pump casing can contain, then the motor driver shall be rated
for the maximum size of impeller that can be fitted.
A. Identification
2.05 FABRICATION
A. Whenever possible, the pumps shall be manufactured such that it shall be possible to
disassemble the rotor assembly with minimum disassembly of other parts such as
suction and discharge nozzles, bearing supports, etc., being left in place.
C. All foundry and machine work shall be in accordance with good practice for the class
of work involved.
D. All parts shall conform to the required dimensions and shall be free from defects that
will prevent proper functioning of the pump.
E. All like parts of same type pumps fabricated by the same manufacturer shall be
interchangeable.
H. Seal flush systems shall be equipped with appropriate controls, strainers and filters
as recommended by the manufacturer.
I. All internal parts, such as impeller, requiring surface treatment shall be sprayed with
PVC epoxy primer in accordance with pump manufacturer's standard practice.
J. Pump exterior shall be sprayed with PVC epoxy primer and shall be painted to meet
specific application requirements in accordance with pump manufacturer's standard
practice.
PART 3 EXECUTION
3.01 GENERAL
A. Inspection
1. The Contractor shall inspect each pump prior to installation to verify that
pumps are in conformance with these Specifications.
2. Examine all data and characteristics are complying with approved submittals.
3. Verify that pump power parameters are matching with site power supply.
4. Examine areas and conditions under which pumps are to be installed. Do not
proceed with work until unsatisfactory conditions have been corrected.
3.05 INSTALLATION
A. General
1. Pumps shall be provided with motors, starters, controls, pressure gages, and
vibration isolators.
2. Provide pipe size shut-off valve and strainer on suction, pipe size spring
loaded check valve and valve for throttling on discharge.
B. Layout
2. Pump arrangement shall ensure safe and easy access to all pump and other
equipment, if applicable, components for operation and maintenance
purposes.
3. Provisions for isolation, venting and draining the pump shall be installed to
permit internal inspection, repair or dismantling.
C. Location
1. Pumps shall be installed and located with the shortest, fewest number of
elbows, fittings and most direct suction pipe practical.
2. Place the pump as near as possible to the source of supply, if not installed on
a closed system.
3. When installing the pump, consider its location in relation to the system to
assure that sufficient Net Positive Suction Head (NPSH), where applicable, at
pump suction is provided.
4. Locate the pump so that there is plenty of room for inspection, maintenance
and service.
6. Locate the pump so that a hoist or crane can be used to move it without
interference from piping.
7. Locate pump on concrete floor with sub-soil underneath, for sound and
vibration absorption.
E. Alignment
1. Although the pump was properly aligned and tested at the factory. However,
since all pump bases are flexible, they may spring and twist during shipment.
3. If flexible coupling is used between the pump and its driver, shafts shall be so
supported and aligned as not to produce undesirable stresses and noise
during normal operation.
4. Never use flexible couplings to compensate for misalignment of the pump and
motor shafts.
7. The pumps shall not be connected to the piping system unless it is re-aligned.
8. After piping is completed and after the pump is grouted-in and bolted-down,
align it again.
9. Re-adjust the alignment from time to time while the unit and foundation are
new.
F. Piping
1. General
h) Where flanged joints are used, assure that inside diameters match
properly.
G. Pipe Alignment
2. Piping alignment shall never be achieved by force, this could produce strain on
the piping and the pump casing.
3. Line up the vertical piping so that the bolt holes in the pump flanges match the
bolt holes in the pipe flanges.
H. Suction Piping
I. Discharge Piping
J. Valve
1. Install full port isolation valves on both suction and discharge side of the pump
to allow servicing without draining the system.
6. Triple Duty Valve installed in the discharge line can be used to serve as a
check valve to protect the pump from water hammer, as a gate valve for
servicing and for throttling.
7. Factory designed combination valve inlet and discharge fittings can be used if
certified by pump manufacturer.
K. Elbows
1. Elbows shall not be used at the suction nozzle, but if it is unavoidable, they
shall be installed in a vertical position.
L. Reducers
3. Long radius reducing elbows can also be used to decrease from pipe size.
1. Provide drains for bases and stuffing boxes, piped to and discharging into floor
drains.
4. Drains must be located at the lowest point in the piping located near the pump.
N. Strainers
O. Pressure Gages
1. Install properly sized pressure gages in both the suction and discharge pump
nozzles or piping gage taps.
P. Support
3. Supports shall be installed for the piping to keep its weight off the pump
casing.
4. Both the suction and discharge piping shall be independently supported near
the pump.
5. The pipe supports on the suction piping shall not rigidly tie down the suction
line close to the pump suction nozzle.
6. Assure that pipes are supported properly and do not rest on pump flanges.
7. Provide supports under elbows on pump suction and discharge lines 100 mm
and over.
8. Properly align piping and supports so that no strain is transmitted to the pump
when the flange bolts are tightened.
10. Provide floor stands and pipe suspension methods so that pumps will not be
required to support weight of piping.
11. It is preferable to support the discharge piping from overhead structural steel
whenever possible to allow for proper removal of discharge piping for
maintenance.
12. Support in-line circulators directly from inlet and discharge pipe. Do not use
flexible connections.
3.06 APPLICATION
A. Make sure that pump and pipe flanges are strictly parallel and properly spaced for
the gasket that will be used.
B. When flange bolts are used, line up the piping first, then loosely install flange bolts.
C. Check the piping alignment, and tighten the flange bolts until all bolts are tightened
securely.
D. Allow the grout to flow around wedges or shims to hold them in place.
E. The grout shall be puddled frequently to remove any air bubbles from the grout.
A. Mounting
3. The mounting bolts or studs shall be accurately located as per the applicable
manufacturer dimension sheet.
B. Foundation
2. The foundation for the pump must be sufficiently rigid to maintain alignment
and absorb any vibration or stress encountered during pump operation.
7. Use foundation bolts and larger pipe-sleeves to give room for final bolt
location.
C. Grouting
1. After the pump has been leveled, securely bolted to the floor and properly
aligned; a good grade of non-shrinking grout shall be poured inside the pump
base.
2. The entire base plate shall be completely filled with grout, to prevent lateral
movement of the base plate, and improve the vibration absorbing
characteristics of the foundation.
D. Electrical Requirements
1. General
c) The motor shall be wired in accordance with the wiring diagram found
on the motor nameplate.
f) Provide pump electrical panel board with visual push button controller
switch, etc; or connect pump to MCC (motor control center), where
applicable.
A. Protection
1. Protect pump against the possibility of flooding, as this can damage the drive
motor.
B. Final Alignment
1. Proper alignment shall be performed after base plate has been properly set
and grout has dried thoroughly according to instructions.
2. Final alignment shall be accomplished after the pump has been operated
initially for a sufficient length of time to attain operating temperature.
3. When normal operating temperature has been attained, secure the pump, re-
check alignment, and compensate for temperature accordingly.
5. After final alignment, dowel driver feet and pump to the base plate.
C. Identification
A. Prior to start-up, align and certify pumps with a flexible coupled drive using a qualified
millwright.
B. Temporary strainers shall be used during the commissioning and initial operating
period of the new installations to prevent foreign objects from entering the pump.
C. Pre-Start Checks
b) Check all connections to motor and starting device with wiring diagram.
d) Check suction and discharge piping and pressure gages for proper
operation.
e) Check seals.
j) Check Rotation
1) Ensure that the driver operates in the direction indicated by the
arrow on the pump casing.
D. Priming
1. The pump must not be run dry in the hope it will prime itself. Serious damage
to the pump may result if it is started dry.
3. All air shall be expelled from the suction piping and pump casing, and replaced
by the liquid to be pumped.
E. Operating Checks
1. Check the pump and piping to assure that there are no leaks.
3. Check and record voltage, amperage per phase, and kW, if an indicating
wattmeter is available.
5. Make all pump output adjustments with the discharge control valve.
7. After the temperature has stabilized, the pump shall be shut down and the
alignment rechecked.
9. Make sure all pump, motor and base plate mounting bolts are firmly tightened
down.
3.10 TESTING
1. Hydrostatic test.
2. Performance test.
4. Shop inspection.
D. The performance and NPSH tests shall be carried out in the presence of a
representative of the Royal Commission.
E. Field Testing
1. Perform field-testing of the pumps at the time of overall system start-up and
testing.
2. Each pump shall be tested at 5 points of operation from shut-off head to run-
out condition including the guaranteed pump's performance point.
6. Test all pumps hydrostatically for leaks at 1.5 times the design pressure.
END OF SECTION