PROJECT NAME: Construction of 220 kV OHTL 4 Hurghada locations El Baraka company

Sr. No Item Description Unit Unit Rate


Excavation and backfilling
1 in class-2 soil M³ 180
2 Excavation and backfilling M³ 130
3 Excavation and backfilling M³ 100
4 Backfilling soil (with M³ 150
Backfilling from mother soil M³ 50
5 Reinforcement steel cutting, MT 1,700
6 Stub setting using template tower 2,500
7 Stub setting using V-Block tower 2,000
8 Lean concrete (with M³ 1,450
9 Concrete Supply)
RCC concrete (with Concrete M³ 1,800
10 Supply)
Foundation insulation M² 65
11 painting (including
Installation supply of Tower
of Earthing 800
system
Soil replacement if required
12 (Using sand and gravel) M³ 150

13 Access Road Km 50000


14 Tower Erection Ton 1600
Total A (Civil works )