You are on page 1of 2

BOX CULVERT 98+295

SL No. DESCRIPTION OF ITEM QUANTITY UNIT UNIT RATE

Proposal for labour rates for culvert,drain & bridge works


1
Earth work in excavation of foundation for structure 240 cum 50

labour charges for mixing , laying,compacting & curing of


2 pcc & rcc in box culvert. Vibrating by vibrator and 33.285 cum 700
finishing all complete as derected by engineer in charge

Labour charges for strainghtening, cutting ,febrication, as


3 1.41 Mt 2000
per bbs
Labour charges for unloading from truck/trailer,
erection, placing & binding of rainforcement of all dia in
4 1.41 Mt 4000
position as per drawing including cost of binding wire
(18 to 20 SWG).
Labour charges for fixing & removing of shuttering for all
5 pcc, raft, slabs & walls of box culvert including staging 130.8 sqm 300
oiling ,strutting, bracing, propping etc

Proposal for labour rates for culvert,drain & bridge works

6 Providing fixing & removing of shuttering for all pcc, raft,


slabs & walls of box culvert including staging 130.8 sqm 400
oiling ,strutting, bracing, propping etc
Proposal for labour rates for culvert,drain & bridge works
7
Labour charges for fixing of weep holes 28 Nos 50
Proposal for labour rates for culvert,drain & bridge works
8 Labour charges for unloading of cement bags from 227 bag 5
trailer,tipper etc at store
Proposal rates for culvert & drain works
Earth work in excavation of foundation for structures in
9 all types of soil excluding rock, including all lifps and 240 cum 200
leaves complete as per drawing and technical
specifications cluse 304 (soil,ordinary rock,hard rock)
Proposal rates for culvert & drain works (M15)
Providing and laying cement concrete PCC M15 garde in
10 foundation levelling course including centering and 3.15 cum 7100
shuttering all complete as per drawing and technical
specification sections 1500,1700 and 2100
Proposal rates for culvert & drain works (M25)
Reinforce cement concrete in super structure including
11 centering and shuttering but excluding reinforcement
complete as per drawing and technical specifications 30.135 cum 9000
1500,1700 and 2200

Proposal rates for culvert & drain works (TMT)


Providing and fixing in position TMT Fe500 grade
12 reinforcement bar in foundation, sub structures , super
structure etc. Complete as drawing and technical 1.41 Mt 69000
specifications section 1600

TOTAL Rs.
AMOUNT

12000.00

23299.50

2820.00

5640.00

39240.00

52320.00

1400.00

1135.00

48000.00

22365.00

271215.00

97290.00

576724.50