Professional Documents
Culture Documents
UDC 625.888
BS 5931:1980
Cooperating organizations
The organizations marked with an asterisk in the above list, together with the
following, were directly represented on the committee entrusted with the
preparation of this British Standard:
Contents
Page
Cooperating organizations Inside front cover
Foreword ii
0 Introduction 1
1 Scope 1
2 References 1
3 General considerations 1
4 Machines for forming in situ edge details 1
5 Section size and tolerances 2
6 Trial lengths 2
7 Asphalt sections 2
8 Concrete sections 4
Appendix A Characteristics of machines for
forming in situ edge details 7
Figure 1 — Typical cross sections of asphalt kerbs 8
Figure 2 — Typical cross sections of concrete kerbs 9
Table 1 — Classification of auger powered kerb
Licensed copy:Mouchel Limited, 13/10/2017, Uncontrolled Copy, © BSI
extruder machines 7
Publications referred to Inside back cover
© BSI 03-1999 i
BS 5931:1980
Foreword
Extruded asphalt kerbing was introduced into the United Kingdom from the USA
in 1961 and concrete some years later, since which time a substantial amount of
experience has been obtained with their use. Some kerbs of this type have now
been in service for over 15 years with satisfactory performance. These
recommendations set out to give general information on such kerbs based on this
experience.
This code recommends good practice for the production of both asphalt and
concrete edge details. Specific reference to either material is made only where
their individual characteristics warrant such reference.
A British Standard does not purport to include all the necessary provisions of a
contract. Users of British Standards are responsible for their correct application.
Compliance with a British Standard does not of itself confer immunity
from legal obligations.
Licensed copy:Mouchel Limited, 13/10/2017, Uncontrolled Copy, © BSI
Summary of pages
This document comprises a front cover, an inside front cover, pages i and ii,
pages 1 to 10, an inside back cover and a back cover.
This standard has been updated (see copyright date) and may have had
amendments incorporated. This will be indicated in the amendment table on the
inside front cover.
ii © BSI 03-1999
BS 5931:1980
© BSI 03-1999 1
BS 5931:1980
The selection of a machine for a particular project In the case of line-guided machines the surface
should take account of: regularity of the top of the kerb should be
a) the material to be laid; within ± 3 mm of the theoretical line.
b) the section dimensions; The horizontal alignment should not depart from
the intended line by more than ± 13 mm nor deviate
c) in the case of concrete, whether dowels or
from the straight by more than 3 mm in 3 m.
reinforcement are to be included.
Where false falls have been provided in the
Asphalt may be laid by only certain of the extrusion
pavement surfacing to assist drainage in the
machines.
channels, except where a line-guided machine is
Plain concrete may be laid by either extrusion or slip used, special measures are usually necessary to
forming machines. ensure that the kerb level follows the true road level
Reinforced concrete or that containing vertical rather than that of the falls. It may simply require
dowels, may be laid by most slip forming machines adjustments to be made to the height of the wheels
but not by extrusion machines. of the extrusion machine or it may be necessary to
4.2 Auger powered extrusion machines. To run the machine on a short length of suitably
achieve the correct density there is a critical supported track or board, placed at the required
relationship between machine mass, auger size and datum. Alternatively, consideration should be given
number of augers to the cross-sectional area of the to the use of pre-extruded kerbs laid on an in situ
mould. The density of the extruded section is a bed such as would normally be laid for conventional
Licensed copy:Mouchel Limited, 13/10/2017, Uncontrolled Copy, © BSI
2 © BSI 03-1999
BS 5931:1980
7.2 Materials. A nominal coarse aggregate content 7.3.5 Laying. It is essential that all machine parts in
within the range 20 % to 30 % is recommended, contact with the asphalt are cleaned of all adhering
although other stone contents have been material at the end of the day’s production or if a
successfully used. The nominal size of the coarse delay occurs which will allow the asphalt to cool
aggregate should not exceed 20 mm and will within the machine. The mould should be
normally be 10 mm. The aggregate type and other pre-heated and may require intermittent reheating.
properties should comply with the requirements of The asphalt mix may be fed to the hopper of the
BS 594. The binder content of the asphalt mix extrusion machine by hand or by mechanical means.
should normally lie within the range 6 % to 9 % During laying, the machine should be operated as
although some aggregates may require 0.5 % to 1 % far as possible at a constant speed. The engine
more binder. It is recommended that the binder should not be kept running whilst waiting for
be 50, 70 or 100 penetration grade. In general the materials as distortion of the laid kerb could occur.
upper range of binder content and the lower range Asphalt should not be permitted to remain in the
of penetration will lead to a more durable kerb. In hopper for any length of time whilst the machine is
situations where the kerbs will be immediately not in operation as this could result in the
adjoining a carriageway and where there is a high temperature of the material becoming too low for
risk of mechanical damage from vehicle impact, a satisfactory compaction and will encourage the
harder grade of binder (e.g. 35-pen), coupled with machine to lift and distort the profile. The usual
the upper range of coarse aggregate content may be restrictions on working in adverse weather
considered more appropriate.
Licensed copy:Mouchel Limited, 13/10/2017, Uncontrolled Copy, © BSI
© BSI 03-1999 3
BS 5931:1980
Where the line and/or level of the kerb are purposely 8.2 Materials
discontinued, hand-finishing may be necessary. 8.2.1 Cement. The cement used in the concrete mix
Sharp bends, such as those associated with off-set should be ordinary Portland cement complying with
gullies, can be formed by pre-extruding the kerb and the requirements of BS 12, Portland blast furnace
then placing it by hand and bonding with tackcoat in cement complying with the requirements of BS 146,
the required position. Similarly, for dropped kerbs or a blend of ordinary Portland cement premixed
at entrances, the asphalt kerb can be pre-moulded, with pozzolanic pulverized fuel ash. If pozzolanic
cut to length and set by hand. Alternatively, pulvarised fuel ash is used it should satisfy the
dropped kerbs may be formed by extruding in the requirements of BS 3892. Where there is a risk of
normal way and then striking off the top part of the sulphate attack, sulphate resisting cement
kerb and hand-finishing to the desired height and complying with the requirements of BS 4027 should
configuration using a suitable template or jig made be used, without the addition of pulverized fuel ash.
to conform to the pattern required.
8.2.2 Aggregates. The aggregate should comply with
7.4 Testing. Sampling and testing of the asphalt the requirements of BS 882.
kerb mix should be carried out in accordance with
standard methods as laid down in BS 598. The 8.2.3 Admixtures. An air-entraining agent should
actual percentages by mass of coarse aggregate, fine always be incorporated in the concrete mix to
aggregate, filler and soluble binder, should comply provide additional protection against frost attack.
with the requirements of Appendix A of In addition, a water reducing admixture
(plasticizing agent) in accordance with the
Licensed copy:Mouchel Limited, 13/10/2017, Uncontrolled Copy, © BSI
BS 594:1973.
recommendations of CP 110 may also be used if it is
It has not been possible to include other forms of shown to be a necessary aid to the laying process or
testing for extruded edge details as no suitable tests the production of a satisfactory surface finish. All
specifically for this type of construction have been relevant admixtures should comply with the
developed and furthermore some existing tests are requirements of BS 5075.
not applicable in these circumstances.
8.2.4 Water. The water used for making concrete
7.5 Maintenance and repairs. Repairs to asphalt should be clean and free from harmful matter in
kerbs are relatively simple, involving the removal of such quantities as would affect the properties of the
the damaged section, and the hand-placing of concrete in the plastic or hardened state. (See the
pre-extruded sections of kerbing. In such cases, a Appendix to BS 3148:1959)
bond between the new section of kerb and the
surfacing should be made by the use of a suitable hot 8.3 Recommended mix proportions
applied bitumen or synthetic resin adhesive. The 8.3.1 Mix proportions. Because the scale and nature
joints between the old and new sections of kerb of the work will generally not justify the application
should be sealed with the use of an appropriate of mix design procedures and the associated testing,
sealant or alternatively be gently heated to fuse the it is recommended that the concrete mix be specified
joint. In the event of extensive repairs being in the form of a special prescribed mix in accordance
necessary, it may prove easier and more economical with the requirements of BS 5328. There is a
for an extrusion machine to be used to lay new suitable form in Appendix C of BS 5328:1976 which
sections. should be used to specify the concrete required and
provide the supplier with all the necessary
8 Concrete sections information.
8.1 General. Even long lengths of extruded or In order to ensure that the air-entrained concrete
slip-formed edge details will require relatively small has adequate strength, it is recommended that the
quantities of concrete, and the scale and nature of combined dry mass of the coarse and fine aggregate
the work will generally not justify the application of to be used with 100 kg of cement, should not
mix design procedures and the associated testing. exceed 600 kg. This ratio corresponds
For example, the number of strength test results approximately with a cement content of 300 kg per
would probably be too few to be statistically cubic metre of compacted concrete.
significant and reliable. The mix proportions 8.3.2 Proportion of fine aggregate. The most suitable
recommended in this code of practice have been mix to use in a laying machine depends upon both
selected to provide durable concrete having a the type of machine and the aggregate. To achieve a
sufficient characteristic strength. well sealed surface, the proportion of fine aggregate
will usually need to be between 45 % and 55 % of
the total mass of aggregate depending upon the
maximum size of the aggregate and the grading of
the sand.
4 © BSI 03-1999
BS 5931:1980
8.3.3 Maximum aggregate size. The size of aggregate With line-guided machines, the spacing of the
which is to be used should be related to the supports for the line varies. On a straight line they
cross-sectional area and the type of laying machine. should be placed at about 5 m centres but on curves
The nominal maximum size of aggregate should the spacing should be reduced.
generally not exceed 20 mm. For some cross sections With both types of machine the accuracy of the
of finished concrete and for certain types of laying product depends to a large extent on the care and
machine, it may be found necessary to use 10 mm attention paid to the initial setting out.
sized aggregate in order to achieve the correct
8.5.2 Supply of materials. Laying machines are
profile or a satisfactory surface finish.
usually supplied by ready-mixed concrete and it is
8.3.4 Air content. Since the optimum volume of air normally necessary to combine a slow rate of
in air-entrained concrete is indirectly related to the discharge with a slow forward movement of the
maximum size of aggregate in the mix, it is delivery truck. Generally, a truck on which the
recommended that the total air content of the fresh drum is powered by a separate engine has an
concrete should be as follows. advantage, since the speed of drum discharge can be
For 10 mm and 20 mm nominal maximum changed independently of the truck speed. The
size: 6 % quantity of concrete ordered should be decided,
For 40 mm nominal maximum size: 4.5 % taking into account the distance it has to be
delivered, the size of section and the time it will take
The percentage air content should be maintained
to complete the discharge.
Licensed copy:Mouchel Limited, 13/10/2017, Uncontrolled Copy, © BSI
© BSI 03-1999 5
BS 5931:1980
8.5.5 Joints. In many cases, joints will not be Splayed kerbs to channel surface water into off-set
required except for aesthetic reasons or where gullies may be formed by pre-forming the kerbs on
contraction joints are introduced to limit random to polyethylene sheeting, and bonding them into
cracking. It may also be necessary to match joints position with a synthetic resin mortar after the
already in the surface upon which the concrete concrete has hardened.
section is laid. In this case, expansion and 8.5.7 Curing. The exposed faces of sections should
contraction joints should be formed in the kerb be cured immediately after laying to prevent rapid
section to match the position and width of joints in moisture loss and to reduce the effects of solar
the underlying surface or structure. For concrete radiation.
containing coarse aggregate other than flint or
A sprayed, resin based, aluminized curing
quartzite, or similarly hard aggregate, these joints
membrane is the most convenient and efficient
may be sawn in the hardened concrete.
method of curing.
Where flint or quartzite coarse aggregate is used or
when contraction cracks are likely to occur before 8.6 Testing
satisfactory sawing can take place, the joints should 8.6.1 Air content. The air content of the
be wet formed in the concrete while it is still plastic. air-entrained concrete should be determined during
A method which may be used for wet forming the trial and at least once a day and not less than
expansion joints involves the placing of a pair of once for every five loads during the course of the
shaped plates over the section with a gap between work. The test should be carried out at the point of
Licensed copy:Mouchel Limited, 13/10/2017, Uncontrolled Copy, © BSI
them equal to the joint width. The plastic concrete laying, using an air meter as described in BS 1881.
in the gap should then be carefully removed, 8.6.2 Dry density. Where the scale or importance of
avoiding disturbance of the concrete on either side the work justifies the testing which is involved, the
and ensuring that no stones are left bridging the degree of compaction achieved in the concrete which
gap. A coarse toothed blade has been found to be is laid in the trial length should be such that its in
useful for removing the concrete in this way. The situ dry density, in the form of cut-out sections or
joint gap may need to be filled with a suitable cores, should be not less than 95 % of the average
compressible material. dry density obtainable in cubes prepared and tested
Contraction joints may be formed by simply making in accordance with the requirements of BS 1881.
an incision with a steel trowel or other sharp tool, If the engineer has reason to suspect that the
sufficient to reduce the strength of the section by concrete laid by the machine is of variable or
one-quarter to one-third. insufficient density, he should consider asking for
At the end of a day’s work the concrete should be cut cores to be cut and tested in accordance with the
back to a point where the cross-sectional profile is requirements of BS 1881-5.
satisfactory. Shortly before concreting is resumed, 8.7 Maintenance and repairs. Minor repairs can
the cut face should be wire brushed and dampened. readily be carried out by hand, using fine concrete or
8.5.6 Dropped kerbs, ramps and splays. sand/cement mortar.
Consideration should be given to forming dropped Where short sections have to be replaced, this can
and ramped kerbs from full height sections by either be done in situ between formwork or by
striking off the top part of the kerb and hand replacing with sections which had been previously
finishing to the desired height and configuration formed on to polyethylene sheeting at the time the
using a suitable template or jig made to conform to original work was done, and cut into lengths for
the pattern required. Alternatively, dropped and storage. The use of synthetic resin bonding agent is
ramped kerbs may be formed by means of a special a convenient method of fixing these previously
attachment on the laying machine but it is unlikely formed sections.
that this method will result in any reduction in the
amount of hand finishing required.
6 © BSI 03-1999
BS 5931:1980
kg mm mm m2 mm mm m2 Remarks
300 80 150 0.01 300 260 0.0775 Small sections use a single 100 mm
auger. The larger sections use a
single 130 mm or 150 mm auger.
300/450 80 150 0.01 300 460 0.09 Small sections with single 130 mm
auger. Sections greater than 0.075 m2
require twin 150 mm augers.
600/700 160 190 0.0366 460 460 0.09 Small section with single 150 mm
auger. High or wide sections require
one 180 mm and one 200 mm auger.
850/1 000 250 300 0.06 410 650 0.2145 Smallest section with two augers.
Largest section with four augers.
1 000/1 200 300 400 0.1016 410 840 0.26 Smallest section with three augers.
Largest section with five augers.
These height and width figures are the minimum and maximum available, but the cross-sectional area figures are guides only and
will depend to some extent on the shape of the section.
© BSI 03-1999 7
BS 5931:1980
Licensed copy:Mouchel Limited, 13/10/2017, Uncontrolled Copy, © BSI
8 © BSI 03-1999
BS 5931:1980
Licensed copy:Mouchel Limited, 13/10/2017, Uncontrolled Copy, © BSI
© BSI 03-1999 9
Licensed copy:Mouchel Limited, 13/10/2017, Uncontrolled Copy, © BSI
10
blank
BS 5931:1980
Publications referred to
© BSI 03-1999
BS 5931:1980
Revisions
It is the constant aim of BSI to improve the quality of our products and services.
We would be grateful if anyone finding an inaccuracy or ambiguity while using
this British Standard would inform the Secretary of the technical committee
responsible, the identity of which can be found on the inside front cover.
Tel: 020 8996 9000. Fax: 020 8996 7400.
BSI offers members an individual updating service called PLUS which ensures
that subscribers automatically receive the latest editions of standards.
Buying standards
Orders for all BSI, international and foreign standards publications should be
addressed to Customer Services. Tel: 020 8996 9001. Fax: 020 8996 7001.
Licensed copy:Mouchel Limited, 13/10/2017, Uncontrolled Copy, © BSI
Information on standards
Copyright
Copyright subsists in all BSI publications. BSI also holds the copyright, in the
UK, of the publications of the internationalstandardization bodies. Except as
permitted under the Copyright, Designs and Patents Act 1988 no extract may be
reproduced, stored in a retrieval system or transmitted in any form or by any
means – electronic, photocopying, recording or otherwise – without prior written
permission from BSI.
This does not preclude the free use, in the course of implementing the standard,
of necessary details such as symbols, and size, type or grade designations. If these
details are to be used for any other purpose than implementation then the prior
written permission of BSI must be obtained.