You are on page 1of 7

FINISHING AND MISCELANIOUS WORK FOR FATTENING SHADE,FORAGE AND

MIX CHAMBER SHADE AND ISOLATED SHADE CONSTRUCTION WORK


ITEM DESCRIPTION UNIT QUANTITY U.PRC
A.) FINNISHING WORK FOR FATTENING SHADE
CNTRT EXCTD

1.00 WALL AND STEEL WIRE INSECT MESH WINDOW.


Fixing the wall with roof nail 0.2 mm G.S.I sheet around the m2 49.00
perimeter of 100.4 m to the height of 3.4 m on 5 layers of
horizontal members included,.0.1 m of it should be covered with
down massonary wall.

Fixing insect wire mesh windows with roof nail using ripped m2 21.00
eucaliptus tree frame around the two 35 m long sides.the total
length not exceeding 70 m and the height of 0.3 m including the
frame.

2.00 ANIMAL FEED BED OR PANE WORK.


Trachytic or equivalent stone massonary loop type wall JOINED m3 39.04
WITH (1:3) CEMENT SAND MORTAR acording to supervisor
instruction

30 cm thick basaltic or equivalent stone hard core well rolled , m3 16.42 16.20 800.00
consolidated and blinded with crushed stone.
7 cm thick C-25 360 kg cement/m3 concrete filled in to the feed m3 3.36
bed.
Supply , cutting , bending and fix in position .price shall
include tying wire.
Cement screed and make water proof surface.Animal feed bed m2 492.48
internal and top surface should be cement screed to be smooth ,
curved and water proofed.

Average 11 cm thick C-25 360 kg cement/m3 concrete filled the m3 37.40 25.00 4800.00
floor with 1-2% inclination from animal feeding pane toward the
drainage according to supervisers instruction.The price shall
include drainage work and burial of the existing 10 cm diameter
PVC pipe lying to drain out according to the superviser
instruction.

3.00 PAVMENT AND DRAINAGE WORK AROUND THE


SHADE
A).Trench excavation work m3 18.36 12.00 150.00
B).Average 40 cm thick retaining basalt rock massonary wall m3 16.20 16.20 2800.00
joined with (1:3) cement sand mortar around the shade to protect
runoff acording to the supervisers instruction.

C).Three coat of Plastering the external part of the retaining wall. m2 27.10

D).70cm wide and 10 cm thick smoothed concrete pavment m3 2.80


infront of the shade with ratio 1:2:3 placed on 10 cm thick
compacted granullar fill and 15cm thick hard core above it.

E).Supply and lay precast half concrete pipe open chanell around
the three sides of the shade acording to supervisers instruction for
external drainage system.unit price shall include excavation of
trench and supplying and spreading of redash or selected material
of minimum thickness 50mm below the pipe and 15cm thick
external supporting massonary.

a)1/2 Ø 30cm ml 70.00


b)1 Ø 30 cm(infront of door.) ml 4.00
4.00 ANIMAL TYING CHAIN
Animal tying pole or post each having Dia.10 to 12 cm and 1.8 pcs 100.00 80.00 200.00
cm long.30 cm of the post is under floor with wire mesh coating
and anchoring with floor concrete casting to center to center
distance of 70 cm and 0.2 m from animal feed wall according to
supervisers instruction.

TOTAL CARRIED SUM FOR A


REBATE IF ANY (%)
TOTAL AFTER REBATE
VAT (15%)
TOTAL WITH VAT
T. PRICE
CNTRT EXCTD

-
-

12,960.00

120,000.00

1,800.00
45,360.00

-
-
-
16,000.00

196,120.00

29,418.00
225,538.00
1st PAYMENT CERTIFICATE FOR FATTENING SHADE CONSTRUCTION WORK
PROJECT Fattening Shade Finnishing
construction work
LOCATION Kochira kebele

CLIENT SHEBEGNE MAHIBER

CONTRACTER SELAM CONSTRUCTION.

DATE 16/06/2015 E.C

PREVIOUS PAYMENT
no net vat tot
adv.pay 156,766.60 23,514.99 180,281.59
1st pay TOTAL WITH VAT
2 DEDUCTIONS
3 1 .PREVIOUS PAYMENTS
4 2. RETENTION (5%)
3.25% OF ADVANCE PAYMENT
4. PENALITIES
5. REBATE

TOTAL COST DUE TO CONTRACTOR

BIRR BY STATEMENT
One hundred thirty five thousand two hundred eleven and ninteen cents.
PREPARED BY------------------------------------- CHECKED BY ----------------------
SIGNATURE----------------------------------- SIGNATURE---------------------------
DATE---------------------------------- DATE---------------------------------
APPROVED BY---------------------------------
SIGNATURE-------------------------------
DATE----------------------------------
main contract 627,066.40

VAT (15%) 94,059.96


Total sum 721,126.36
supplimentary -
VAT (15%) -
Total sum -
varation order -
VAT (15%) -
Total sum -
Work Excuted
VAT (15%)

TOTAL WITH VAT


DEDUCTIONS
1 .PREVIOUS PAYMENTS -
2. RETENTION (5%) -
3.25% OF ADVANCE PAYMENT 39,191.65
4. PENALITIES

NET SUM 39,191.65


VAT (15%) 5,878.75

Tot deduction 45,070.40


NET SUM 117,574.95
VAT (15%) 17,636.24
TOTAL SUM 135,211.19

ECKED BY ----------------------