Project BAN 600

Client BOSCH
Contractor DNS CONSTRUCTIONS
Work Excavation

Sl No Work Description Units Rate Qty

1 NAB SOUTH TRAIL PIT cft 17 106.67151


2 TANK Z4 cft 17 362.8144872
3 Near security cabin excavation cft 17 42.372
4 Near security cabin excavation cft 17 547.6581
TOTAL AMOUNT

TOTAL WORK DONE

TDS@1% -

Retention Money & Paper charges 10% of work


Done Valun -
past week balance amount
Advance -
Balance
Amount Remarks

1813.41567 17 Rupees /CFT


6167.8462824
720.324
9310.1877
18011.773652

18011.773652

180.11773652

17831.655916

1,492
0
19,324
Project BAN 600
Client BOSCH
Contractor DNS CONSTRUCTIONS
Work Excavation
Excavation QTY

Length
Sl No Description Unit Width (m) Height (m)
(m)

1 NAB SOUTH TRAIL PIT CUM 5.3 0.6 0.95


2 TANK Z4 CUM 3.6 2.01 1.42
3 Near security cabin excavation CUM 2 2 0.3
4 Near security cabin excavation CUM 4.7 2.2 1.5
Total Qty
Total
Quantity (Cum) Quantity Remarks
(Cft)

3.021 106.67151
10.27512 362.81449
1.2 42.372
15.51 547.6581
Total Qty 1059.52