Installation of Working Without valid Valid permit to be obtained from POS &
Cable Trays permit. ORPIC before starting any job.
Personnel Injuries due to All people should undergo POS & ORPIC
Induction.
slips, trips & falls.
Tool Box Talk to be conducted before
People hit by moving starting any job on daily basis.
Vehicles. Ensure sufficient water is available at site
People falling into the and also convey the message in Daily Tool
Concrete Trench. Box Talk.
Unsafe Access or Egress. A Competent Supervisor should be
Toxic gas. available at site at all times.
Banksmen should accompany the vehicles
Dust.
all the times.
Noise. Area to barricaded and cordoned off to
Manual Handling. restrict the movement of people.
Awkward position. Adequate signboards and flickering lights
Electrocution. to be fixed to warn the night users.
Defective Power Tools. Sufficient access and egress to be provided.
Ladders shall be secured using suitable
Personal Injury to sharp
means.
edges. Sufficient no. of lights to be provided.
Unguarded Power tools. Gas test to be conducted before people
Working at Height. entering the excavated pit.
Fall of Materials. All power tools should be inspected before
Poor housekeeping. use.
All power tools should have adequate
Heat Stress.
guards.
Adverse weather condition
Periodical inspection of power tools to be
like Extreme heat, Extreme carried out.
high winds, Extreme dust Only trained and competent people should
lightening, etc. be allowed to operate power tools.
Only trained and competent people should
carry out erection and alternation of
mobile scaffolding.
Before using the mobile scaffolding it has
to be inspected and certified by a
competent scaffolding inspector.
Mobile scaffolding has to be inspected and
recertified on weekly basis by a competent
scaffolding inspector.
All loose materials to be kept in a bucket or
container while working at height.
While shifting the mobile scaffolding no
persons should be on the top.
Scaffolding wheel should be of good quality
and in good condition.
Before climbing the scaffold worker has to
make sure the wheel lock has been
secured.
In any adverse weather condition work
activities will be suspended and renewed
only after the weather condition is apt for
the activities.
Adequate PPE to be used for the job.
The work area to be kept clean and free of
obstruction.
After finishing the work, housekeeping to
be carried out.