3.

Installation of  Working Without valid  Valid permit to be obtained from POS &
Cable Trays permit. ORPIC before starting any job.
 Personnel Injuries due to  All people should undergo POS & ORPIC
Induction.
slips, trips & falls.
 Tool Box Talk to be conducted before
 People hit by moving starting any job on daily basis.
Vehicles.  Ensure sufficient water is available at site
 People falling into the and also convey the message in Daily Tool
Concrete Trench. Box Talk.
 Unsafe Access or Egress.  A Competent Supervisor should be
 Toxic gas. available at site at all times.
 Banksmen should accompany the vehicles
 Dust.
all the times.
 Noise.  Area to barricaded and cordoned off to
 Manual Handling. restrict the movement of people.
 Awkward position.  Adequate signboards and flickering lights
 Electrocution. to be fixed to warn the night users.
 Defective Power Tools.  Sufficient access and egress to be provided.
 Ladders shall be secured using suitable
 Personal Injury to sharp
means.
edges.  Sufficient no. of lights to be provided.
 Unguarded Power tools.  Gas test to be conducted before people
 Working at Height. entering the excavated pit.
 Fall of Materials.  All power tools should be inspected before
 Poor housekeeping. use.
 All power tools should have adequate
 Heat Stress.
guards.
 Adverse weather condition
 Periodical inspection of power tools to be
like Extreme heat, Extreme carried out.
high winds, Extreme dust  Only trained and competent people should
lightening, etc. be allowed to operate power tools.
 Only trained and competent people should
carry out erection and alternation of
mobile scaffolding.
 Before using the mobile scaffolding it has
to be inspected and certified by a
competent scaffolding inspector.
 Mobile scaffolding has to be inspected and
recertified on weekly basis by a competent
scaffolding inspector.
 All loose materials to be kept in a bucket or
container while working at height.
 While shifting the mobile scaffolding no
persons should be on the top.
 Scaffolding wheel should be of good quality
and in good condition.
 Before climbing the scaffold worker has to
make sure the wheel lock has been
secured.
 In any adverse weather condition work
activities will be suspended and renewed
only after the weather condition is apt for
the activities.
 Adequate PPE to be used for the job.
 The work area to be kept clean and free of
obstruction.
 After finishing the work, housekeeping to
be carried out.