LEGAL INFORMATION
Copyright © 2016 ZTE CORPORATION.
The contents of this document are protected by copyright laws and international treaties. Any reproduction or
distribution of this document or any portion of this document, in any form by any means, without the prior written
consent of ZTE CORPORATION is prohibited. Additionally, the contents of this document are protected by
contractual confidentiality obligations.
All company, brand and product names are trade or service marks, or registered trade or service marks, of ZTE
CORPORATION or of their respective owners.
This document is provided “as is”, and all express, implied, or statutory warranties, representations or conditions
are disclaimed, including without limitation any implied warranty of merchantability, fitness for a particular purpose,
title or non-infringement. ZTE CORPORATION and its licensors shall not be liable for damages resulting from the
use of or reliance on the information contained herein.
ZTE CORPORATION or its licensors may have current or pending intellectual property rights or applications
covering the subject matter of this document. Except as expressly provided in any written license between ZTE
CORPORATION and its licensee, the user of this document shall not acquire any license to the subject matter
herein.
ZTE CORPORATION reserves the right to upgrade or make technical change to this product without further notice.
Users may visit the ZTE technical support website http://support.zte.com.cn to inquire for related information.
The ultimate right to interpret this product resides in ZTE CORPORATION.
Revision History
R1.1 2016-01-27 l Added the installation of the 2+0 XPIC configuration in “3.2.3
2+0 Buckle Installation”.
l Added the Installation of antenna in “Appendix B Installing
Antenna”.
l Added the installation and cable connection of the PIMDC in
“Appendix D, Installing the PIMDC”.
l Added the Installation of PSE in “Appendix E Installing PSE”.
l Added the completed installation in the power cable scenario,
PoE scenario, and AC power supply scenario in “Section 1.1
Completed Installation”.
l Added the steps of making the power cable plug in “Section
3.3 Installing the Power Cable”.
l Added the wire sequence description of the 568B standard
straight network cable in “Section 3.4.1 Installing the Ethernet
Cable”.
l Added the cross-connection description of the 2+2 XPIC
HSB protection configuration and the 2+2 XPIC SD
protection configuration in “Section 3.6 Installing the XPIC
Cross-Connection Cables (Optional)”.
II
Intended Audience
This manual is intended for:
Chapter 2, ZXMW NR8950 Installation Describes how to install the ZXMW NR8950.
Chapter 3, Cable Installation Describes how to install the cables of the ZXMW
NR8950.
Chapter 4, Installation Check Describes the checking process after the ZXMW
NR8950 installation is completed.
Chapter 5, Power On and Power Off Describes how to power on and power off the
ZXMW NR8950.
Appendix D, Installing the PIMDC Describes how to install the PIMDC and its
cables.
Conventions
This manual uses the following conventions.
II
1-1
1-2
1-3
1-4
l Non-professionals should not install or debug the system unless they are instructed
by professionals on the site.
l Installation personnel must be very careful of personal safety, and avoid accidents
such as electric shocks or personal injury due to falling objects.
l To avoid eye injury caused by laser beams, installation personnel must not directly
look at the cross-section of any optical fiber or the socket of an optical terminal during
the installation of optical fibers.
l Replacing any part or a device might result in unexpected dangers. Therefore,
replacement of any part or a device can be implemented only after authorization is
acquired.
l To ensure your safety, contact ZTE Corporation if you have any question.
1-5
Crystal Wire
connector punchdown
crimper tool
Crowbar Telescope
1-6
Tape Sleeve
Multimeter Grounding
resistance
tester
Compass GPS
1-7
1-8
Split in- Without For detailed information of the For detailed information of the
stalla- combiner installation process, refer to installation process, refer to
tion “2.2.1 1+0 Separate Installation “2.2.3 2+0 Separate Installation
(Single-Polarization)”. (Dual-Polarization)”.
With combiner For detailed information of the For detailed information of the
installation process, refer to installation process, refer to
“2.2.2 1+1 Separate Installation “2.2.4 2+2 Separate Installation
(Single-Polarization)”. (Dual-Polarization)”.
2-1
2. Rotate the guide pin 90° clockwise (from “V” to “H”), and place the guide pin marked
with “H” upwards, see Figure 2-2.
Note:
During the guide pin adjustment, please strictly perform the related operations in
compliance with the directions mentioned in Figure 2-2.
3. Place the guide pin on the guide hole, and tighten the guide screws clockwise, see
Figure 2-3.
2-2
Table of Contents
Buckle Installation ......................................................................................................2-3
Separate Installation.................................................................................................2-21
2-3
Table 2-2 Installation Components and Tools Used in 1+0 Buckle Installation
Antenna One
ZXMW One
NR8950
Hex One
wrench set
Lubricant One -
Prerequisite
The ZXMW NR8950 polarization mode is the same as that of the antenna.
Steps
1. Remove the waveguide diaphragm from the ZXMW NR8950's antenna interface, see
Figure 2-4.
2-4