PROJECT: MUM1XO
NA
Pages : 2 of 9
PROJECT: MUM1X0
Pages : 3 of 9
TABLE OF CONTENTS
Sl. No. Description Page No.
1.0 Purpose 4
1.1 Scope 4
1.4 Manpower 4
1.6 Materials 4
1.7 Roles & Responsibilities (Including Name & Contact no. of the concerned person) 5
1.9 Procedure 6
1.13 Checklist 8
1.14 ITP 9
MUM1X0-LWC-XX-ZZ-MS-
Doc Ref :
C-0012
METHOD STATEMENT FOR
Rev : P0
ANTI TERMITE TREATMENT Date : 29th Sep ’22
Pages : 4 of 9
1.0 Purpose
The objective of this method statement is to carryout Anti termite treatment by meeting the
technical specification and complying with standards.
1.1 Scope
The scope of this method statement includes application of Anti termite agent along the
periphery of the buildings and other areas under “Yondr-MUM1X0 Data Center” project, while
executing it in accordance with technical specifications, Refer - MUM1X0-VAG-ZZ-ZZ-SP-A-0000.
1.6 Materials:
Imidacloprid - 30.5% SC as per IS16131-2015 Specification for imidacloprid suspension
concentrate & IS6313-2022 Code for anti-termite measures in building.
Water for mixing
MUM1X0-LWC-XX-ZZ-MS-
Doc Ref :
C-0012
METHOD STATEMENT FOR
Rev : P0
ANTI TERMITE TREATMENT Date : 29th Sep ’22
Pages : 5 of 9
Mr. Shihabudeen Surveyor shall ensure the markings and levels are established as per
Senior Surveyor approved drawings
9645399382
Mr.VIJI
Senior Engineer He shall be responsible for Executing in safe work method as per drawings
7530046299 and guide the supervisors and work men.
Mr.Ikbal Khan He shall be responsible managing all plant and machineries and labor
Assistant Engineer and safety of the workers.
9092262979
Mr.Senthil C He shall be responsible for ensuring the quality of work as per the
QA/QC Manager specifications and standards.
9003336119
He shall be responsible for assisting to engineer/supervisor to ensure the
safety of workers during the progress of work. Safety inductions of each
Mr.Kannan staff and workers shall be done and daily PPE check to be done and tool
EHS Manager box talk shall be carried out before the start of work. General safety
7397988247 awareness as well as particular safety precautions and guidelines for
activity to be carried out in that particular day shall be discussed. He shall
also ensure necessary permits are in place prior to start of activity.
He shall be responsible for storing of all materials. Also, responsible for
Store Officer maintaining the record of incoming and outgoing and up to date stock
details of materials.
Pages : 6 of 9
1.9 Procedure
C. SEQUENCES:
Chemical recommend by IS. 6313 part II 2013 (latest and revised) for projects:
Protection of
reference points Imidacloprid 30.5% SC
Brand: ImidaGold Plus 30.5% SC
Dose: 2.1 ml chemical per 1 liter of water
After the completion of the structure and backfilling work up to plinth level, the
area that needed to be treated with anti-termite agent shall be marked with
the help of line threads.
The treatment consists of
1) Treatment before PCC
2) Treatment around columns/footings
3) Treatment for Plinth area of the building
4) Treatment for external periphery
Treatment before PCC, the bottom surface of the excavation made (Pit for
PCC) shall be treated with the anti-termite agent at the rate of 5 l/m2 surface. If
water is used for ramming the earth or if the moisture content of the soil is high
the chemical treatment shall be carried out after rodding the earth at 150 mm
centers apart parallel to the wall surface and spraying the chemical emulsion
at the above dosage. After the treatment, the soil should be tamped in place.
Treatment around columns/footings, after completion of backfilling around the
columns up to the ground level, the chemical shall be poured up to the depth
of 500mm by injecting the holes around columns and entire backfilled area
around columns shall be treated @ 7.5L per Sq. m. of vertical surface.
Treatment for Plinth area of the building, treatment for finish floor filled surface to
create a continuous and undisturbed chemical barrier at entire filled soil within
the Plinth walls i.e. plinth filling, the spraying treatment shall be given horizontally
MUM1X0-LWC-XX-ZZ-MS-
Doc Ref :
C-0012
METHOD STATEMENT FOR
Rev : P0
ANTI TERMITE TREATMENT Date : 29th Sep ’22
Pages : 7 of 9
before the grade slab on filled /compacted soil surface. After the compaction
and watering is completed the entire plinth surface before soling/ PCC shall be
treated with chemical @ 5 liter per Sq. m.
Treatment for external periphery, After the building is complete, the earth along
the external perimeter of the building should be rodded at intervals of 150mm
and to a depth of 300mm and treat the chemical at the rate of 7.5 lt. Per Sq. m.
of vertical surface.
Concern Engineer and related workers will be required to wear the required standard
Protective & Safety
PPE, in particular Hi-Vis jackets must be worn at all times. (refer MUM1X0-LWC-XX-ZZ-HS-
Equipment
W-0001)
MUM1X0-LWC-XX-ZZ-MS-
Doc Ref :
C-0012
METHOD STATEMENT FOR
Rev : P0
ANTI TERMITE TREATMENT Date : 29th Sep ’22
Pages : 8 of 9
1.13 Checklist
C Post Inspection
Pages : 9 of 9
1.14 ITP
NATURE
FORMAT L&W
COMPONENT/ OF METHOD FREQUENCY REFERENCE L&W QC PMC /
S.NO OF EXECUTION
PROCESS CHECK/ OF CHECK OF CHECK DOCUMENT ENGINEER CLIENT
RECORD ENGINEER
TEST
Submission &
Approval of Document Before start the Project Method
1 Review - H H
work method Review ATT works Specification Statement
statement
Anti-termite
treatment Document Before start the Project
2 Review RFAM - R R
material Review works Specification
approval
Review Approved
First delivery IMIR - W A
Material Manufacturer Document RFAM
3
Inspection test Review Subsequent Approved
certificate IMIR - H A
deliveries RFAM
Approved
Surface Visual / Prior to start
4 Inspection Method Checklist C H S
preparation Measurement ATT
Statement
Approved
Mixing and Visual / Check
5 Inspection Each element Method C H H
application Measurement List
Statement
C - Check, I - Inspection, P - Perform, M - Monitor, R - Review, LTR - Lab Test Report , H - Hold ,W - Witness, S - Surveillance