Professional Documents
Culture Documents
strata like
concrete,
conglomerate,
rock etc soil
including back MEASUREMENTS SHEET
PROJECT
filling :- Construction with of Basti Rasheedabad Mosque, Khanewal.
BOQ.Item SR. excavated soil in MEASUREMENTS
DESCRIPTION
layers not NO. QUANTITY UNIT
No No. LENGTH BREADTH HEIGHT
exceeding 6"
Excavation
thickness in
1.01 depressions,
1 around
sec-A grid 2/B~D 1 31.670 3.67 5.00 581.14 Cft
2 foundations
sec-A grid 7/B'~D 1 21.000 3.67 5.00 385.35 "
3 including
sec-K disposal
grid 7/B 1 16.170 5.67 5.00 458.42 "
Providing
of surplus
sec-B and
earth,
grid B/2~4
4 applying
cutting+ 5~6 Anti- and 1 11.500 3.67 5.00 211.02 "
5 Termite "
removing all the 1 16.625 4.67 5.00 388.19 "
6 Treatment
growth, sec-G undertrees, 1 12.000 3.17 5.00 190.20 "
floorssec-E
bushes, small
and
7 sec-J grid 1'+7'/Dstriping, in 2 2.500 2.67 5.00 66.75 "
portion parallel to
8 foundations
hard
sec-E
standing
& sec-G
(bed
and
at 2 2.500 3.17 5.00 79.25 "
& sec-J abovesides)
vertical
disposal (grid
as
9 with grid 1+8
1'+7'/C)
approved/ 2 47.330 3.17 5.00 1,500.36 "
directed (i/c all
10 pressureC~F+G~K
sec-J grid 1 / F~G
spraying 1 20.420 2.67 5.00 272.61 "
lead and
sec-D (x-dir) lift)
grid
11 equipment,
complete using
etc as 2 12.920 3.67 5.00 474.16 "
3+6 / D~F
12 Biflex
sec-C grid
directed proand FMC
D/2~7 as 1 38.125 4.17 5.00 794.91 "
sec-D
USA
per or(y-dir)
Mirage
instructions grid 5
of
13 1 22.770 3.67 5.00 417.83 "
sec-FE/3~6grid F/1~3
14 %Engineer SCIn 2 13.750 3.17 5.00 435.88 "
(charge.
sec-D
sec-H,G+Distributors
6~8
(x-dir) grid
(y-dir)
15 Friends 2 23.500 3.67 5.00 862.45 "
grid3'+5'
G+J+K / G~K / 1~3'
16 International 6 14.500 3.17 5.00 1,378.95 "
+ 5'~8 ,,,,,, + K /
17 Marketing
sec J (Grid
3'~5' j'/1~3') 1 14.500 2.67 5.00 193.58 "
18 Rawalpindi/Ibd
Boundary Wall 1 361.330 2.00 3.00 2,167.98 "
Ph: 051
Total - 10,859.03 Cft
4575690 - 1 &
Add 20% extra 13,030.84 Cft
Cell No: 0346 -
4993037) as
Anti-termite
approved
Providing, mixing,
1.02 pesticide
laying solution
and
1 through
grid 2~7
compacting / B~C an 1 22.630 44.25 - 1,001.38 Sft
approved
2 cement C~Ksub-
grid 1~8 /concrete 1 68.000 54.75 - 3,723.00 "
contractor, as
1:4:8 per
under "
manufacture's
foundations, Total etc 4,724.38 Sft
specifications
at any elevation and
Add
all to 5%
the extra
approval 4,960.60 Sft
with sand and
of
crush theof Engineer
size 3/4"
Incharge
Concrete
and 1:4:8(The
down (of
1.03 contractor quarryis/
approved
required
1 source)
sec-A grid including
2/B~D to 1 31.670 3.67 0.33 38.36 Cft
provide
curing five years
and form
2 sec-A grid 7/B'~D 1 21.000 3.67 0.33 25.43 "
guarantee for full
3 work sec-K etc,
effectivenessgrid all7/B as
of 1 16.170 5.67 0.33 30.26 "
per
sec-B grid drawings,
B/2~4
4 the 1 11.500 3.67 0.33 13.93 "
+anti-termite
specifications
5~6
5 complete
treatment). " etc as 1 16.625 4.67 0.33 25.62 "
Complete
6 directed sec-G etc as
and as 1 12.000 3.17 0.33 12.55 "
7 directed
per sec-E
sec-J and
gridsmall
instructions
1'+7'/D as
of 2 2.500 2.67 0.33 4.41 "
per instructions
portion
Engineer parallel to of
In
8 sec-E & sec-G at 2 2.500 3.17 0.33 5.23 "
Engineer
sec-J above (grid
charge.
9 Incharge.grid 1+8
1'+7'/C) / 2 47.330 3.17 0.33 99.02 "
10 (PaymentC~F+G~K
sec-J grid shall1 / F~G be 1 20.420 2.67 0.33 17.99 "
sec-D (x-dir) grid
11 made as per 2 12.920 3.67 0.33 31.29 "
3+6 / D~F
12 covered
sec-C grid area)D/2~7 1 38.125 4.17 0.33 52.46 "
sec-D (y-dir) grid
13 1 22.770 3.67 0.33 27.58 "
sec-FE/3~6grid F/1~3
14 2 13.750 3.17 0.33 28.77 "
+ 6~8
Providing, mixing,
laying, vibrating
and curing
reinforcement
cement concrete
sec-D
sec-H,G (x-dir) grid
(y-dir)
15 (RCC 1:2:4) in 2 23.500 3.67 0.33 56.92 "
grid 3'+5'
G+J+K
Foundation / G~K / 1~3'
using
16 6 14.500 3.17 0.33 91.01 "
+ 5'~8of,,,,,, +K/
17 crush
sec J (Grid required
j'/1~3') 1 14.500 2.67 0.33 12.78 "
size 3'~5'(1/2" and
18 down)underand planter sand 2 4.375 1.88 0.38 6.15 "
(of approved 0.00 "
quarry / source) 0.00 "
with minimum
Total 573.61 Cft
compressive
Add 5% extra 602.29 Cft
cube
Concrete 1:2:4strength
(Foundation) of
3000 psi at 28
1.04
days, in the RCC
1 works
sec-A gridas 2/B~Dshown 1 31.670 3.00 1.00 95.01 Cft
2 onsec-A grid 7/B'~D
drawings at 1 21.000 3.00 1.00 63.00 "
3 any sec-K grid 7/B
height/floor, 1 16.170 5.00 1.00 80.85 "
sec-B grid B/2~4
4 including the cost 1 11.500 3.00 1.00 34.50 "
of form+ 5~6work but
5 " 1 16.625 4.00 1.00 66.50 "
6 excluding sec-G
the cost
1 12.000 2.50 1.00 30.00 "
of sec-E reinforcing
small
7 steel
sec-J grid 1'+7'/D 2 2.500 2.00 1.00 10.00 "
portionallparallel
Providing, as per
mixing, to
8 laying,
sec-E above
drawings & sec-G
vibrating at 2 2.500 2.50 1.00 12.50 "
sec-J (grid
9 and grid
specifications1+8
1'+7'/C) /
curing 2 47.330 2.50 1.00 236.65 "
C~F+G~K
complete grid 1etc
10 reinforcement
sec-J / F~G as 1 20.420 2.00 1.00 40.84 "
sec-D (x-dir)
directed
cement and
concretegrid
as
11 2 12.920 3.00 1.00 77.52 "
3+61:2:4)
/ D~F inof
per instructions
12 (RCC
sec-C grid D/2~7 1 38.125 3.50 1.00 133.44 "
Engineer
following
sec-D (y-dir)works gridIn
13 charge.
using Margalla 1 22.770 3.00 1.00 68.31 "
sec-FE/3~6grid F/1~3
14 crush of required 2 13.750 2.50 1.00 68.75 "
sec-D +(x-dir)
sec-H,G 6~8 grid
15 size (1/2"(y-dir) and 2 23.500 3.00 1.00 141.00 "
grid3'+5'
G+J+K / G~K / 1~3'
16 down) and 6 14.500 2.50 1.00 217.50 "
+ 5'~8 ,,,,,, + K /
Lawrancepur
17 sec J (Grid j'/1~3') 1 14.500 2.00 1.00 29.00 "
sand 3'~5' with
Total 1,405.37 Cft
minimum
Add 5% extra
compressive 1,475.64 Cft
Concretecube
1:2:4 strength
(Plinth Beams) of
1.05 (a) 3000 psi at 28
1 days, in PB-3the RCC 1 12.330 1.13 1.00 13.87 Cft
2 works as
Sec A shown 1 40.000 0.75 1.00 30.00 "
3 on drawings " at 1 40.000 0.88 0.33 11.55 "
any height/floor,
4 " 1 40.000 0.38 1.00 15.20 "
including
PB-1 (Grid the 2cost /
5 of form work but 1 21.500 1.13 1.00 24.19 "
PB-1B~C) (Grid 7 /
6 excluding the cost 1 20.000 1.13 1.00 22.50 "
PB-1 B~C)
(Grid 1+8 /
7 of reinforcing 1 19.255 1.13 1.00 21.66 "
PB-2C~F) (Grid C /
8 steel all as per 2 4.125 1.13 1.00 9.28 "
PB-21~2(Grid
+ 7~8) 2+7 /
9 drawings 2 4.625 1.13 1.00 10.41 "
PB-6C~D) (Grid D /
10 specifications 2 4.500 0.75 1.00 6.75 "
1~2 (Grid
PB-4 + 7~8) D/
11 complete etc as 1 37.000 0.75 1.00 27.75 "
2~7)
12 directed
PB-5 (Gridand E/3~6) as 1 25.000 0.75 1.00 18.75 "
per instructions
PB-2 (Grid F / of
13 2 12.000 1.13 1.00 27.00 "
Engineer
PB-41~3(Grid
+ 6~8) 3+6 In /
14 charge. 2 14.250 0.75 1.00 21.38 "
D~F)
15 Sec C 1 22.000 0.75 1.00 16.50 "
PB-7 (Grid 1+8 /
16 2 20.250 0.75 1.00 30.38 "
PB-7G~K) (Grid K /
17 2 16.500 0.75 1.00 24.75 "
1~3' (Grid
PB-8 + 5'~8) G/
18 2 16.500 0.75 1.00 24.75 "
PB-91~3' + 5'~8)
(Grid 3'+5' /
19 2 15.255 0.75 1.00 22.88 "
PB-10 G~K)(Grid J /
20 1 16.500 0.75 1.00 12.38 "
PB-11 1~3')
(Grid K /
21 1 16.750 0.75 1.00 12.56 "
3'~5')
laying, vibrating
and curing
reinforcement
cement concrete
(RCC PB-12 1:2:4)
[x-dir]in
22 following 2 11.920 0.75 1.00 17.88 "
(Grid / works
3°+3[x-dir]
PB-12 G~J')
23 using Margalla 1 4.810 0.75 1.00 3.61 "
(Grid
PB-122 [y-dir]
/ J~J')
24 crush of required 1 7.940 0.75 1.00 5.96 "
(Grid H / 3°~3')
25 size Sec (1/2"J and 1 16.500 0.75 1.00 12.38 "
26 down)Boundary wall and 1 361.330 0.75 0.75 203.25 "
Lawrancepur 0.00 "
sand with
Total 647.54 Cft
minimum
Add 5% extra
compressive 679.92 Cft
Columns
cube strength of
1.05 (b) 3000 psi at 28
days, in the LVL
Slab +17.5' RCC
1 works as
C-1 shown 5 1.125 1.125 22.17 140.29 Cft
2 on drawings C-2 at 4 1.500 0.750 22.17 99.77 "
any height/floor,
3 C-3 2 1.750 0.750 22.17 58.20 "
including the cost
4 of formC-4 work but 1 1.125 0.750 22.17 18.71 "
5 excluding C-6 xthe2 cost 4 0.750 0.605 22.17 40.24 "
ofSlab +14.5' LVL
reinforcing
steel all
6 Providing, C-5as per
mixing, 2 0.750 0.750 19.17 21.57 "
drawings
laying, vibrating
Slab +12.5' LVL
specifications
7 and C-1 curing 4 1.125 1.125 17.17 86.92 Cft
complete etc as
reinforcement
8 C-4 4 1.125 0.750 17.17 57.95 "
directed concrete
cement and as
Slab +14'
per instructions
(RCC LVL
1:2:4) inof
9 following
Engineer C-7 works In 2 1.500 0.750 18.67 42.01 "
10 using
charge.C-8 Margalla 2 1.500 0.750 18.67 42.01 "
Slab +11.75'
crush LVL
of required
11 size (1/2" C-5 and 4 0.750 0.750 16.42 36.95 "
down)
12 Minaret over roof and 4 0.750 0.75 12.75 28.69 "
Lawrancepur "
sand with
Total 673.29 Cft
minimum
Add 5% extra
compressive 706.95 Cft
Concrete cube
1:2:4 (Slab
strength & Beams)
of
1.05 (c) 3000 psi at 28
days,
Slab: in the RCC Cft
1 works
grid 2~7as/ B~D shown 1 30.750 44.25 0.50 680.34 "
on drawings
2 Verandha roof grid at 1 11.750 28.50 0.50 167.44 "
any height/floor,
Slabs at B/S of verandah slab "
including the cost
3 of form "work but 2 24.250 6.625 0.50 160.66 "
4 excluding" the cost 2 17.125 7.50 0.50 128.44 "
5 of reinforcing
" 2 6.375 1.00 0.50 6.38 "
6 steel
Slab atall gridas4,5per
/ 1 19.875 20.25 0.50 201.23 "
Slabs at grid
7 drawings 2 23.750 18.25 0.50 433.44 "
2+7 / G~K
specifications
8 complete" etc as 4 2.000 1.00 0.50 4.00 "
D/d doam
9 directed and as -1 37.181 0.50 -18.59 "
(3.142xd^2/4)
Beams:
per instructions of "
TB (Grid G~K /In
10 Engineer 4 20.250 0.75 0.50 30.38 "
1+3'+5'+8)
11 charge. D/d col 2 1.750 0.75 0.50 1.31 "
12 D/d col 2 1.125 0.75 0.50 0.84 "
TB (Grid G+K /
13 5 16.500 0.75 0.50 30.94 "
Sec1~3'F at+ 5'~8)
grid K /
14 1 16.750 0.75 1.50 18.84 "
Sec 3~5J at grid
15 2 16.750 0.75 0.50 12.56 "
H+J
Sec D /at3~5
grid
16 Sec 2 19.255 2.08 0.50 40.05 "
1+8D/ at C~Fgrid
17 1+8 / C~F 2 19.255 0.25 0.33 3.18 "
(bottom rib)
Sec D at grid F /
18 Sec D at grid F / 2 12.000 2.08 0.50 24.96 "
1~3 + 6~8
19 1~3 + 6~8 2 12.000 2.08 0.50 24.96 "
TB (bottom
at grid Crib)/ 1~2
20 2 4.125 0.75 0.50 3.09 "
TB at+grid 7~83+6 /
21 2 10.000 0.75 0.50 7.50 "
LB5 at D~Fgrid E /
"
3~6
22 Upper portion 1 25.000 1.50 0.50 18.75 "
23 upper ribs 1 25.000 0.25 0.33 2.06 "
24 lower portion 1 25.000 0.75 1.50 28.13 "
25 lower ribs 1 25.000 0.38 0.38 3.61 "
26 TB at grid D / 2~7 1 37.000 0.75 0.50 13.88 "
TB-1 at grid 7 /
27 1 14.875 1.13 0.50 8.37 "
TB-1 B'~Cat grid 2 /
28 1 21.500 1.13 0.50 12.09 "
TB at B~C grid 2+7 /
29 2 4.625 0.75 0.50 3.47 "
Sec C~D E at Grid
30 1 35.670 2.00 0.50 35.67 "
B/2~6
31 BB-3 1 6.250 1.125 1.50 10.55 "
32 BB-3a 1 4.375 1.125 1.50 7.38 "
33 BB-4 1 9.000 1.50 1.50 20.25 "
34 B-1 2 27.250 1.00 1.50 81.75 "
35 B-2 4 5.290 1.00 1.50 31.74 "
Ring Beam
36 1 49.518 1.00 1.50 74.28 "
(L=2x3.142xr)
Mehrab upper
37 1 9.000 0.75 1.00 6.75 "
Mehrab beam lower
38 1 12.570 0.75 1.00 9.43 "
Side archbeam portion
39 Beams at 2 11.250 0.75 16.88 "
of Mehrab
intermediate "
40 levels
Sec A 1 25.000 0.75 1.00 18.75 "
41 Sec B 2 15.000 0.75 1.00 22.50 "
42 Sec G 2 15.250 0.75 1.00 22.88 "
Shade
Providing, mixing, "
Projection:
43 laying,Secvibrating
A 1 44.250 0.514 22.74 "
44 and Sec Bcuring 2 10.750 1.140 24.51 "
45 reinforcement
Sec C 1 28.500 0.300 8.55 "
46 cement Secconcrete
D 2 50.750 0.300 30.45 "
47 (RCC Sec 1:2:4) in
E 1 105.750 0.970 102.58 "
following works
48 using SecMargallaF 1 20.250 0.490 9.92 "
49 crush Sec G
of required 2 19.875 0.490 19.48 "
50 size Sec (1/2"H and 2 67.625 0.490 66.27 "
51 down) Sec J and 1 20.250 0.490 9.92 "
Lawrancepur "
sand with
Total 2,705.52 Cft
minimum
Add 5% extra
compressive 2,840.80 Cft
Concretecube
1:2:4 strength
(Lintel Beams)
of
1.05 (d) 3000 psi at 28
days,LB-3 (Grid
in the RCC 0.00 Cft
works B/2~3)
as shown
1 Sec 2-2 1 3.375 0.75 1.50 3.80 "
2 on drawings " at 1 3.375 1.62 0.25 1.37 "
any height/floor,
3 " 1 3.375 2.00 0.50 3.38 "
including the cost
4 of form Secwork 3-3 but 2 6.625 0.75 0.75 7.45 "
5 excluding" the cost 2 6.625 1.25 0.33 5.47 "
LB-3a (Grid
6 of reinforcing 0.00 "
B/5~7)
7 steel Sec all 2-2
as per 1 3.375 0.75 1.50 3.80 "
8 drawings " 1 3.375 1.62 0.25 1.37 "
specifications
complete etc as
directed and as
per instructions of
Engineer In
9 " 1 3.375 2.00 0.50 3.38 "
10 Sec 3-3 2 6.625 0.75 0.75 7.45 "
11 " 2 6.625 1.25 0.33 5.47 "
LB-1 (Grid
0.00 "
7/B~C)
12 Sec 1-1 1 17.375 0.75 0.27 3.52 "
13 " 1 17.375 1.13 0.50 9.77 "
14 " (Arch portion) 3 13.347 0.38 15.02 "
15 Grid 7/C~D 1 4.625 0.75 0.75 2.60 "
LB-2 (Grid
0.00 "
2/B~C)
16 Sec 1-1 1 17.375 0.75 0.27 3.52 "
17 " 1 17.375 1.13 0.50 9.77 "
18 " (Arch portion) 3 13.347 0.38 15.02 "
19 Grid 2/C~D 1 4.625 0.75 0.75 2.60 "
LB-4 (Grid
0.00 "
D/2~7)
20 Beam 1 33.250 0.75 0.75 18.70 "
21 Arch Portion 1 13.480 0.75 10.11 "
LB-9 (Grid C /
22 2 4.125 0.75 0.75 4.64 "
1~2 (Grid
LB-7 + 7~8)8 /
0.00 "
C~F)
23 Beam 1 22.250 0.75 0.75 12.52 "
24 Arch Portion 2 5.500 2.00 0.75 16.50 "
D/d Arch inner
25 -2 5.460 0.75 -8.19 "
LB-8portion
(Grid 1 /
0.00 "
C~F)
26 Beam 1 22.250 0.75 0.75 12.52 "
27 Arch Portion 1 5.500 2.00 0.75 8.25 "
D/d Arch inner
28 -1 5.460 0.75 -4.10 "
LB-9portion
(Grid 3+6 /
29 2 14.250 0.75 0.75 16.03 "
LB-6D~F)
(Grid F /
0.00 "
1~3 + 6~8)
30 Beam 1 13.875 0.75 0.75 7.80 "
31 Arch Portion 1 5.500 2.00 0.75 8.25 "
D/d Arch inner
32 -1 5.460 0.75 -4.10 "
LB-9 portion
(Grid G /
33 1 16.500 0.75 0.75 9.28 "
LB-101~3')
(Grid G /
0.00 "
5'~8)
34 Beam 1 16.500 0.75 0.75 9.28 "
35 Arch Portion 1 7.500 3.00 0.75 16.88 "
D/d Arch inner
36 -1 12.090 0.75 -9.07 "
portion
LB-9 (Grid
37 3 21.750 0.75 0.75 36.70 "
3'+5'+8 / G~K)
38 D/d col -2 0.750 0.75 0.75 -0.84 "
39 D/d col -4 2.750 0.75 0.75 -6.19 "
LB-13 (Grid 1 /
40 1 1.00 "
G~K)
41 Beam 1 20.250 0.75 0.75 11.39 "
42 Arch Portion 1 4.125 2.00 0.75 6.19 "
D/d Arch inner
43 -1 4.320 0.75 -3.24 "
portion
44 Arch Portion 1 5.080 2.75 0.75 10.48 "
D/d Arch inner
45 -1 5.460 0.75 -4.10 "
LB-11 portion
(Grid K /
46 0.00 "
1~3' + 5'~8)
47 Beam 2 16.500 0.75 0.75 18.56 "
48 Arch Portion 4 5.500 2.00 0.75 33.00 "
D/d Arch inner
49 -4 5.460 0.75 -16.38 "
LB-12 portion
(Grid K /
50 0.00 "
3'~5')
51 upper beam 1 16.750 1.00 0.75 12.56 "
52 lower beams 2 5.375 0.75 0.75 6.05 "
53 upper arch 1 7.500 3.25 0.75 18.28 "
laying, vibrating
and curing
reinforcement
cement concrete
(RCC
D/d Arch1:2:4) innerin
54 following works -1 -9.430 0.75 7.07 "
portion
55 usinglower arches
Margalla 2 5.375 2.00 0.75 16.13 "
D/d Arch inner
56 crush of required -2 4.270 0.75 -6.40 "
LB-9 portion
(Grid J /
57 size (1/2" and 1 16.500 0.75 0.75 9.28 "
Lintel1~3')
at court
58 down) and 2 22.000 0.54 0.25 5.94 "
yard walls
Lawrancepur "
sand with
Total 385.52 Cft
minimum
Add 10% extra
compressive 424.08 Cft
Concrete 1:2:4
cube (Dome
strength / Mehrab)
of
1.05 (e) 3000 psi at 28
days, Dome:
in the RCC Cft
works
R = 6.88' as +shown0.25' "
onA = drawings
(4 x 3.142 xat
1 1 319.459 0.50 159.73 "
any r^2)/2
height/floor,
Mehrab: "
including the cost
R = 4' + 0.50'but
ofA form "
= (4 xwork3.142 x
2 excluding the cost 1 63.625 0.50 31.81 "
r^2)/4
ofMinaret Dome:
reinforcing "
Providing,
steel all +
R = 1.75' mixing,
as per
0.29' "
A = (4 x vibrating
laying,
drawings 3.142 x
3 1 26.151 0.50 13.08 "
Middle r^2)/2
Vertical
4 and
specifications curing 1 12.568 0.25 0.50 1.57 "
portion
reinforcement
Lower
complete Vertical
etc as
5 1 12.819 0.29 1.00 3.72 "
cement
directed concrete
portion
Projection and
at Sec as
6 (RCC 1:2:4) inof
per instructions 1 10.000 1.50 15.00 "
C-C
Beams
following
Engineer works In 8 2.500 0.75 0.75 11.25 "
(intermediate)
using
charge. Margalla "
crush of required "
size (1/2" and "
down) and "
Lawrancepur "
sand with
Total 236.16 Cft
minimum
Add 10% extra
compressive 259.77 Cft
Concrete
cube 1:2:4 (Shelves)
strength of
1.05 (f) 3000 psi at 28
1 days,Shelves
in the RCC 12 4.000 1.25 0.17 10.20 Cft
2 works as " shown 4 4.000 2.00 0.50 16.00 "
3 on drawings
Shelves at 6 6.750 1.25 0.17 8.61 "
any height/floor,
4 " 2 6.750 2.00 0.50 13.50 "
including the cost
of form work but "
excludingTotal the cost 48.31 Cft
Providing
Add
of 5%reinforcing laying
extra 50.72 Cft
Steel
steel 60
all
Steel 60 Grade asgrade
per
Providing
completet
drawings and
as
1.06 Cft/KG
laying
directed first class
specifications by
1 Footing
burnt
Engineer brick 1 Kg #REF! 3.50 #REF!
complete etc as
2 Plinth
masonry Beam 1 Kg #REF! 2.50 #REF!
directed for
Incharge andwallsas
3 Column
per9"instructions
thick and of 1 Kg #REF! 3.75 #REF!
4 above
Roof
EngineerSlab/Beam in
In 1 Kg #REF! 3.00 #REF!
5 Foundation
Lintol Band Beam
charge. and 1 Kg #REF! 2.50 #REF!
6 superstructure
Dome / Mehrab at 1 Kg #REF! 2.00 #REF!
6 any
Shelvesheight/floor 1 Kg #REF! 2.00 #REF!
set in cement
Total Kg #REF!
sand mortar 1:6
including 5 making% AdditionalQua Kg #REF!
Brick Work 9" thick
openings etc or above
as
2.01 shown on
drawings i/c cost
of all materials,
scaffolding,
labour, curing,
cleaning, raking
Slab +17.5' LVL Cft
1 grid 2+7 / B~C 2 20.000 1.13 14.50 652.50 "
2 under mehrab 1 12.000 0.75 7.00 63.00 "
3 Grid B/2~4 + 5~7 2 17.000 2.00 14.50 986.00 "
D/d shelves
4 -4 4.000 1.25 5.50 -110.00 "
portion
5 D/d col portion -2 1.500 0.75 14.50 -32.63 "
6 Grid 2+7 / C~D 2 4.625 0.75 14.50 100.59 "
7 Grid D/2~7 1 37.000 0.75 14.50 402.38 "
Slab +14.5' LVL "
8 Grid E/3~6 1 25.000 0.75 11.75 220.31 "
9 Grid 3+6 / D~F 2 14.250 0.75 11.75 251.16 "
Slab +12.5' LVL "
Grid C / 1~2 +
10 2 4.125 0.75 9.50 58.78 "
7~8
11 Grid 1+8 / C~D 2 5.250 1.13 9.50 112.22 "
12 Grid 1+8 / D~F 2 14.000 1.13 9.50 299.25 "
13 Grid F/1~3 + 6~8 2 12.000 1.13 9.50 256.50 "
Slab +14' LVL "
14 Grid 3'+5' / H~K 2 16.375 0.75 11.00 270.19 "
15 D/d opening -2 4.375 0.75 7.00 -45.94 "
16 Grid H / 3'~5' 1 16.750 0.75 11.00 138.19 "
17 Grid K / 3'~5' 1 16.750 0.75 11.00 138.19 "
Slab +11.75' LVL "
Grid G / 1~3' +
18 2 16.500 0.75 8.75 216.56 "
5'~8
19 Grid 1+8 / G~K 2 20.250 0.75 8.75 265.78 "
20 Add edge portion 2 21.500 0.38 0.38 6.05 "
D/d Detail-Q of
21 -2 44.160 0.75 -66.24 "
opening
D/d Jali "
22 Detail-1 -4 4.000 0.75 4.00 -48.00 "
23 Arch portion -4 5.460 0.75 -16.38 "
24 Detail-2 -2 3.000 0.75 4.00 -18.00 "
25 Arch portion -2 4.270 0.75 -6.40 "
Elevation-02 0.00 "
26 Detail-2 -1 4.000 0.75 4.00 -12.00 "
27 Arch portion -1 5.460 0.75 -4.10 "
28 Grid J/1~3' 1 16.500 0.75 8.75 108.28 "
D/d item # 2.17
29 D/d item #doors)
2.23 0.00 "
(wooden
30 (Aluminium #VALUE! "
Wind.) Total #VALUE! Cft
Add 10% extra #VALUE! Cft
BRICK MASONRY CONCRETE PLASTERING
PREPARED BY AS
Quantity Surveyor S
Ratio 1: 4 Ratio 1 :2:4 Ratio 1:2
Quantity "Cft" 285 Quantity "Cft" 436 Quantity "Sft" 2235
Bricks 3847.5 Cement"Bags" 76.736 Thickness "in" 0.5
Cement"Bags" 13.680 Sand "Cft" 191.840 Cement"Bags" 31.538
Sand "Cft" 68.400 Crush "Cft" 383.680 Sand "Cft" 78.846
3"
9" 4½"
PREPARED BY ASGHAR ALI
Quantity Surveyor SMEC/ACC
Detailed Cost Estimate of Madrasa Babo Khwaza Khela District Swat
Material
Labour Cost Material Cost Total Amount
Sr. No Description Qty Remarks
Cement Sand Crush Steel (Rs) (Rs) (Rs)
(Bags) Cft Cft Kg
1 Excavation - - - - - 108,540
2 Lean Concrete 1:4:8 under foundations - - - - -
3 RCC in Foundation - - - -
4 Lintel Beams - - - -
5 Roof beams 685.5 122 310 620
6 Stair 53.9 10 25 50
7 Slab 657.4 116 290 580
8 Columns Concrete 0.0 - - -
9 Steel 4324.7 4,325
10 Stone Masonary in Foundation -
11 Brick masonry 285.00 15 90
1/2" thick cement sand plaster in (1:2)
12 2,234.86 35 100
cement, sand
13 PCC 1:2:4 under the floor with sand 436.00 80 200 400
Providing and laying 3/4" thick Terrazzo
14 1,362.53
Flooring in grey cement (1:2)
15 Marble Skirting 145.98
16 3 x Coats of Plastic Emulsion paint 3,208.44
17 Door -
18 Window -
NET TOTAL 363 940 1,740 4,325 - - - -
Material Rate
Amount of Material
10 Add 5% extra contengencies
11 NET TOTAL AMOUNT
SUMMARY
CEMENT CONSUMPTION
A3 +A2 Class Qty
1:1.2:2.885 A-3 3000PSi
A1 Class Qty
1:1.2:2.885 A-3 3000PSi
8,081.34
8,081.34
1,653.00 0.035 47228.48
1,983.60 1983.6 70060.60902
4,768.90 4768.9 168437.3809
Class Qty
2
2
0 0.035 6
0 0 14
1 1 27
60.37
60.37
6.17 0.035 176.38 51,269.71
18.52 18.5 654.1152756
35.68 35.7 1260.044059
Lean Conc 39.35
#VALUE! Bed 37.8
#VALUE! Wall & slab 132.7
137.2
98
235.2 0.252
227.7912 29.4
7.4088 9.8
0.6937762788 14.57 14,875.36
1.35982 28.56 18,881.25
51269.71
674.9509869266 14,173.97
834.745036835 17,529.65
#VALUE!
#VALUE!
2563.485735239 53,833.20
32.70576377953 686.82 668 0.804808194
63.00220296063 1,323.05 1287 1.26323892
#VALUE!
#VALUE! 62.2900
#VALUE! 144.5350
522.2767
MAIN SUMMARY BASEMENT +GROUND FLOOR +FIRST FLOOR
Religious Building
Material
Labour Cost Material Cost Total Amount
Sr. No Description Qty Remarks
Cement Sand Crush Steel (Rs) (Rs) (Rs)
(Bags) Cft Cft Kg
1 Excavation 7,236.00 - - - - 108,540
2 Lean Concrete 1:4:8 under foundations 416.13 39 197 394 -
3 RCC in Foundation 272.00 48 120 239
4 Lintel Beams 445.5 78 196 392
5 Roof beams 511.9 90 225 450
6 Stair 56.9 10 25 50
7 Slab 2165.5 381 953 1,906
8 Columns Concrete 1037.3 183 456 913
9 Steel 14361.4 14,361
10 Stone Masonary in Foundation 4,482.00
11 Brick masonry 3,902.66 187 937
1/2" thick cement sand plaster in (1:2)
12 18,503.15 261 653
cement, sand
13 PCC 1:2:4 under the floor with sand 2,231.50 392 982 1,964
Providing and laying 3/4" thick Terrazzo
14 6,291.12
Flooring in grey cement (1:2)
15 Marble Skirting 690.34
16 3 x Coats of Plastic Emulsion paint 17,954.26
17 Door 178.50
18 Window 562.28
NET TOTAL 1,670 4,744 6,308 14,361 - - - -
Material Rate
Amount of Material
10 Add 5% extra contengencies
11 NET TOTAL AMOUNT
MAIN SUMMARY GROUND FLOOR
Religious Building
RCC in Columns
Excavation Lean Concrete Lintel Beams Roof beams Stair Slab Steel
Foundation Concrete
Sr. No Description Qty
1 Excavation 7,236.00
2 Lean Concrete 1:4:8 under foundations 416.13
3 RCC in Foundation 272.00
4 Lintel Beams 445.5
5 Roof beams 511.9
6 Stair 56.9
7 Slab 2165.5
8 Columns Concrete 1037.3
9 Steel 14361.4
10 Stone Masonary in Foundation 4,482.00
11 Brick masonry 3,902.66
1/2" thick cement sand plaster in (1:6)
12 18,503.15
cement, sand
13 PCC 1:2:4 under the floor with sand 2,231.50
Providing and laying 3/4" thick Terrazzo
14 6,291.12
Flooring in grey cement (1:2)
15 Marble Skirting 690.34
16 3 x Coats of Plastic Emulsion paint 17,954.26
17 Door 178.50
18 Window 562.28
NET TOTAL
Material Rate
1 STRUCTURAL WORKS:
1.01 b Excavation 7236 15.00 Cft 108,540
1.02 Lean Concrete 416 150.00 Cft 62,419
1.03 1:4:8
RCC inunder 272 280.00 Cft 76,160
1.04 foundations
Foundation
RCC in Super
a Structure
Plinth Beams - 320.00 Cft -
b Lintel Beams 446 280.00 Cft 124,743
c Roof beams 512 280.00 Cft 143,318
d Stair 57 280.00 Cft 15,945
e Slab 2166 280.00 Cft 606,340
1.05 Columns 1037 230.00 Cft 238,568
1.06 Concrete
Steel 14361 225.00 Kg 3,231,312
Total (Structural Works) 3,990,202
ABSTRACT OF COST GROUND FLOOR
Religious Building
- 15.00 Cft -
1.02 Providing, mixing, laying and compacting cement concrete 1:4:8 under foundations, at any
elevation with sand (from approved attached sources) and crush (from approved attached
sources) of size 3/4" and down including curing and form work etc, all as per drawings,
specifications complete as per instructions of Engineer In charge.
- 180.00 Cft -
1.03 Providing, mixing, laying, vibrating and curing reinforcement cement concrete RCC having
design mix in Foundation using crush (from approved attached sources) of required size
(1/2" and down) and sand (from approved attached sources) with minimum compressive
cylinder strength of 3000 psi at 28 days, in the RCC works as shown on drawings ,
including the cost of form work etc but excluding the cost of reinforcing steel as per
drawings specifications and as per instructions of Engineer In charge.
- 350.00 Cft -
1.04 Providing, mixing, laying, vibrating and curing reinforcement cement concrete RCC having
design mix in following works using crush(from approved attached sources)of required
size (1/2" and down) and sand (from approved attached sources) with minimum
compressive cylinder strength of 3000 psi at 28 days, in the RCC works as shown on
drawings at any height/floor, including the cost of form work but excluding the cost of
reinforcing steel all as per drawings specifications and as per instructions of Engineer In
charge.
- 450.00 Cft -
1.06 Supply, cutting, bending, binding and fixing in position grade 40 high yield deformed steel
reinforcement bars conforming to ASTM-A-615 with minimum yield stress of 40,000 psi at
any height/floor, including the cost of binding wire of 16 gauge, unspecified overlaps, (not
shown in drawings) wastage, rolling margin, concrete cover blocks, removal of rust from
bars if any etc, complete in all respects as per drawings, specifications and to the approval
of the Engineer In charge (Spacer bars, un-specified laps and chairs will not be paid).
Complete etc as directed and as per instructions of Engineer In charge.
- 15.00 Cft -
1.02 Providing, mixing, laying and compacting cement concrete 1:4:8 under foundations, at any
elevation with sand (from approved attached sources) and crush (from approved attached
sources) of size 3/4" and down including curing and form work etc, all as per drawings,
specifications complete as per instructions of Engineer In charge. - 180.00 Cft -
1.03 Providing, mixing, laying, vibrating and curing reinforcement cement concrete RCC having
design mix in Foundation using crush (from approved attached sources) of required size
(1/2" and down) and sand (from approved attached sources) with minimum compressive
cylinder strength of 3000 psi at 28 days, in the RCC works as shown on drawings ,
including the cost of form work etc but excluding the cost of reinforcing steel as per
drawings specifications and as per instructions of Engineer In charge.
- 350.00 Cft -
1.04 Providing, mixing, laying, vibrating and curing reinforcement cement concrete RCC having
design mix in following works using crush(from approved attached sources)of required
size (1/2" and down) and sand (from approved attached sources) with minimum
compressive cylinder strength of 3000 psi at 28 days, in the RCC works as shown on
drawings at any height/floor, including the cost of form work but excluding the cost of
reinforcing steel all as per drawings specifications and as per instructions of Engineer In
charge.
- 370 Cft -
2.03 Providing, mixing and applying 1/2" thick cement
sand plaster in (1:6) cement, sand (as per
approved source of manufacturers list) mortar on
internal surfaces of straight or curved walls etc at
any height including chipping of concrete surfaces,
scaffolding, curing, grooves, chicken mesh at
concrete-masonary joints etc all as per drawings,
specifications. Complete and as per instruction of
Engineer In charge.
1,314.9 50 Sft 65,743
2.04 Providing and laying PCC 1:2:4 under the floor with
sand (as per approved source of manufacturers
list) and crush (as per approved source of
manufacturers list) of size 1/2" and down
including curing and form work etc all as per
drawings , specification complete and as per
instructions of Engineer incharge.
436 220 Cft 95,952
ABSTRACT OF COST BASEMENT
Religious Building
1 Plinth Beam Basement Long Wall 4 120.000 1.00 1.00 480.00 Cft
2 Plinth Beam Basement Short Wall 2 62.330 1.00 1.00 124.66 "
1 Roof Beam Beam Long Wall 3 120.000 1.00 1.00 360.00 Cft
2 Roof Beam Short Wall 2 35.500 1.00 1.00 71.00 "
Columns
Providing, mixing, laying, vibrating
and curing reinforcement cement
concrete RCC having design mix in
Coloumns using crush (from
approved attached sources) of
required size (1/2" and down) and
sand (from approved attached
sources) with minimum compressive
cylinder strength of 4000 psi at 28
days, in the RCC works as shown on
drawings at any height/floor, including
the cost of form work but excluding
the cost of reinforcing steel all as per
drawings specifications complete and
as per instructions of Engineer In
charge.
Total 1,850.69 Kg
4 Plinth Beam Short Wall Stirrups 125.66 2 3.500 3/8" 0.17 149.62 Kg
Total1/2" 1,740.64 Kg
Total1/2" 1,131.00 Kg
Detailed Cost Estimate
Religious Building
MEASUREMENTS UNIT
SR. NOS of NO of
DESCRIPTION QUANTITY
No bars Beam LENGTH DIA UNIT/WT
2 Roof Beam Long Wall Stirrups 241 3 3.500 3/8" 0.17 430.44 Kg
3 Roof Beam Short Wall 8 2 35.500 1/2" 0.30 171.76 Kg
4 Roof Beam Short Wall Stirrups 72 2 3.500 3/8" 0.17 85.73 Kg
5 Roof Beam Room 8 5 16.17 1/2" 0.30 195.59 Kg
6 Roof Beam Room Stirrups 62 5 3.500 3/8" 0.17 184.56 Kg
Total 3/8" 700.73 Kg
Total1/2" 1,281.81 Kg
2 Lintel Beam Long Wall Stirrups 241 2 3.500 3/8" 0.17 286.96 Kg
3 Lintel Beam Short Wall 8 2 35.500 1/2" 0.30 171.76 Kg
4 Lintel Beam Short Wall Stirrups 72 2 3.500 3/8" 0.17 85.73 Kg
5 Lintel Beam Room 8 5 16.17 1/2" 0.30 195.59 Kg
6 Lintel Beam Room Stirrups 62 5 3.500 3/8" 0.17 184.56 Kg
Total 3/8" 557.25 Kg
Total1/2" 976.99 Kg
Detailed Cost Estimate
Religious Building
SR. NOS of Nos of MEASUREMENTS
DESCRIPTION QUANTITY UNIT
No bars beam LENGTH DIA UNIT/WT
Steel 40 Grade Roof beam 1st Floor
Providing laying Steel 40 grade
completet as directed by Engineer ft/KG
Incharge
1 Roof Beam Long Wall 8 3 126.000 1/2" 0.30 914.46 Kg
2 Roof Beam Long Wall Stirrups 241 3 3.500 3/8" 0.17 430.44 Kg
3 Roof Beam Short Wall 8 2 35.500 1/2" 0.30 171.76 Kg
4 Roof Beam Short Wall Stirrups 72 2 3.500 3/8" 0.17 85.73 Kg
5 Roof Beam Room 8 5 16.17 1/2" 0.30 195.59 Kg
6 Roof Beam Room Stirrups 62 5 3.500 3/8" 0.17 184.56 Kg
Total 3/8" 700.73 Kg
Total1/2" 1,281.81 Kg
Detailed Cost Estimate
Religious Building
SR. NOS of MEASUREMENTS UNIT
DESCRIPTION nos QUANTITY
No bars LENGTH DIA UNIT/WT
Steel 40 Grade Slab Ground Floor
Providing laying Steel 40 grade
completet as directed by Engineer ft/KG
Incharge
1 Basement Slab 1 Main Bar 83 1 32.330 1/2" 0.30 811.46 Kg
2 Basement Slab 1 Distt Bar 67 1 42.670 1/2" 0.30 864.53 Kg
3 Ground Floor Slab 2 Main Bar 245 1 35.500 1/2" 0.30 2,630.12 Kg
4 Ground Slab 2 Distt Bar 72 1 138.000 1/2" 0.30 3,004.65 Kg
Total 1/2" 7,310.76 Kg
Detailed Cost Estimate
Religious Building
SR. NOS of MEASUREMENTS UNIT
DESCRIPTION nos QUANTITY
No bars LENGTH DIA UNIT/WT
Steel 40 Grade Slab Ist Floor
1 Ground Floor Slab 2 Main Bar 245 1 35.500 1/2" 0.30 2,630.12 Kg
2 Ground Slab 2 Distt Bar 72 1 138.000 1/2" 0.30 3,004.65 Kg
Total 1/2" 5,634.77 Kg
Detailed Cost Estimate
Religious Building
MEASUREMENTS
SR.
DESCRIPTION NO. QUANTITY UNIT
No LENGTH BREADTH HEIGHT
upto NGL
Brick Work
Providing and laying Brick masonry for
walls any Thickness in Superstructure at
any height/floor set in cement sand
mortar 1:6 including making openings etc
as shown on drawings i/c cost of all
materials, scaffolding, labour, curing,
cleaning, raking out joints etc, all as per
drawings, specifications, complete and as
per instructions of Engineer incharge.
1 Roof Beam Beam Long Wall 3 120.000 0.75 8.50 2,295.00 Cft
Plaster
Providing, mixing and applying 1/2" thick
cement sand plaster in (1:6) cement,
sand (as per approved source of
manufacturers list) mortar on internal
surfaces of straight or curved walls etc at
any height including chipping of concrete
surfaces, scaffolding, curing, grooves,
chicken mesh at concrete-masonary
joints etc all as per drawings,
specifications. Complete and as per
instruction of Engineer In charge.
Plaster: Sft
1 Long Walll Room Inner & Outer Sides 4 120.000 _ 13.00 6,240.00 Sft
3 Short Walll Room Inner & Outer Sides 4 62.330 _ 13.00 3,241.16 Sft
Plaster: Sft
1 Long Walll Room Inner & Outer Sides 4 120.000 _ 11.00 5,280.00 Sft
2 Short Walll Room Inner & Outer Sides 4 62.330 _ 11.00 2,742.52 Sft
3 Partition Wall 10 16.170 _ 11.00 1,778.70 Sft
4 Door D-2 6 3.500 _ 8.50 178.50 Sft
5 Window W-1 7 6.000 _ 8.50 357.00 Sft
Total Qty of Wall 10,336.72 Sft
D-1,D-2,D-3,W-1,W-2,V-1 535.50 Sft
Net Qty 9,801.22 Sft
Detailed Cost Estimate
Religious Building
SR. MEASUREMENTS
DESCRIPTION NO. QUANTITY UNIT
No Area BREADTH HEIGHT
Slab Plaster Ground Floor
Providing, mixing and applying 1/2" thick
cement sand plaster in (1:4) cement,
sand (as per approved source of
manufacturers list) mortar on ceilings &
slab etc at any height including chipping
of concrete surfaces, scaffolding, curing,
grooves, chicken mesh at concrete-
masonary joints etc all as per drawings,
specifications and as per instruction of
Engineer In charge.
Plaster: Sft
1 Total area of slab Basement 1 1314.860 _ _ 1,314.86 Sft
Total area of slab Ground Floor 1 4331.000 _ _ 4,331.00 Sft
Total Qty of Slab 5,928.15 Sft
Detailed Cost Estimate
Religious Building
SR. MEASUREMENTS
DESCRIPTION NO. QUANTITY UNIT
No Area BREADTH HEIGHT
Slab Plaster 1st Floor
Providing, mixing and applying 1/2" thick
cement
Plaster: sand plaster in (1:4) cement, Sft
1 Total area of slab 1 4331.000 _ _ 4,331.00 Sft
Total Qty of Slab 4,547.55 Sft
Detailed Cost Estimate
Religious Building
MEASUREMENTS
SR.
DESCRIPTION NO. QUANTITY UNIT
No LENGTH BREADTH HEIGHT
Terrazzo Flooring
Providing and laying 3/4" thick Terrazzo
Flooring in grey cement (1:2) in pannels
not exceeding 16 Sft including grinding,
rubbing and polishing complete mixed
with pigment and marble chips of
approved size, chemically polished,
complete etc as directed and as per
instructions of Engineer Incharge..
(including the cost of 1/4" thick 1-1/2"
wide Marble Divider Strips in panels)
Marble Skirting
Providing and laying 1/2" thick (as per
approved source of manufacturers list)
Marble Skirting of approved shade of
approved size 24" long and 4" wide or
otherwise,as shown on drawings on walls
including grouting complete and as per
instructions of Engineer Incharge
1 Long Walll Room Inner & Outer Sides 4 120.000 _ 13.00 6,240.00 Sft
Long Walll Boundary Wall Inner & Outer
2 2 120.000 _ 8.50 2,040.00 Sft
Sides
3 Short Walll Room Inner & Outer Sides 4 62.330 _ 13.00 3,241.16 Sft
1 Long Walll Room Inner & Outer Sides 4 120.000 _ 11.00 5,280.00 Sft
2 Short Walll Room Inner & Outer Sides 4 62.330 _ 11.00 2,742.52 Sft
3 Partition Wall 10 16.170 _ 11.00 1,778.70 Sft
5.05 #REF!
Septic Tank
5.06 #REF!
" 1 1.00 Job
Septic Tank