Professional Documents
Culture Documents
RA 1 of 24
1 a) Excavation 3/44 6.17 6.17 5.00 0.19 1000 Cft 3569.30 679
b) Rehandling / Backfilling & Compaction 3/13a,3/24 (b) (ii) 0.04 1000 Cft 2019.60 77
2 Concrete
a) P.C.C 3000 psi (1:2:4) 6 / 5 (f) 1.00 1.00 0.75 0.01 100 Cft 18886.55 142
b) P.C.C 2000 psi (1:3:6) 6 / 5 (h) 6.17 6.17 0.50 0.19 100 Cft 16282.30 3,096
c) R.C.C 3000 psi (1:2:4) 6 / 6 (a) (i) (3) 4.75 4.75 0.50 11.28 Cft 303.50 3,411
Deduct Cover 0.33 0.33 0.50 0.04 Cft
Net 11.24 Cft
3 Deformed steel (Grade 40) 6/9 (b) 0.25 100 Kg 10479.15 2,672
4 9" Thick brick masonary 1:3 CS mortar 7/4/ (i) 19.00 0.75 4.50 0.64 100 Cft 18741.90 12,018
5 12'' dia Non Return Valve 23/30 (g) 1.00 No. 25556.05 25,556
6 Tail Piece with flanges 12" dia 2Nos 23 / 28 (b) (i) 82.00 Kg. 100.90 8,274
7 Mechanical Joint / Gabault Joint Quotation 2.00 No. 2556.00 5,112
8 Cement Plaster (1:3) 11/8 ( b ) 38.00 - 4.50 1.71 100 Sft 1577.35 2,697
-
9 6" (150 mm) thick R.C.C. manhole cover 21/17 1.00 No. 3821.05 3,821
with 3"x3"x¼" (75x75x6mm) angle iron
frame, 22" i/d as per standard drawing
STD/PD No. 7 of 1977, complete in all
respects.
Total Cost for G-I 67,554.71
1 a) Excavation 3/44 6.17 6.17 5.00 0.19 1000 Cft 3569.30 679
b) Rehandling / Backfilling & Compaction 3/13a,3/24 (b) (ii) 0.04 1000 Cft 2019.60 77
2 Concrete
a) P.C.C 3000 psi (1:2:4) 6 / 5 (f) 1.00 1.00 0.75 0.01 100 Cft 18886.55 142
b) P.C.C 2000 psi (1:3:6) 6 / 5 (h) 6.17 6.17 0.50 0.19 100 Cft 16282.30 3,096
c) R.C.C 3000 psi (1:2:4) 6 / 6 (a) (i) (3) 4.75 4.75 0.50 11.28 Cft 303.50 3,411
Deduct Cover 0.33 0.33 0.50 0.04 Cft
Net 11.24 Cft
3 Deformed steel (Grade 40) 6/9 (b) 0.25 100 Kg 10479.15 2,672
4 9" Thick brick masonary 1:3 CS mortar 7/4/ (i) 19.00 0.75 4.50 0.64 100 Cft 18741.90 12,018
5 10'' dia Non Return Valve 23/30 (f) 1.00 No. 20584.70 20,585
6 Tail Piece with flanges 10" dia 2Nos 23 / 28 (b) (ii) 82.00 Kg. 100.90 8,274
7 Mechanical Joint / Gabault Joint Quotation 2.00 No. 2130.00 4,260
8 Cement Plaster (1:3) 11/8 ( b ) 38.00 - 4.50 1.71 100 Sft 1577.35 2,697
-
9 6" (150 mm) thick R.C.C. manhole cover 21/17 1.00 No. 3821.05 3,821
with 3"x3"x¼" (75x75x6mm) angle iron
frame, 22" i/d as per standard drawing
STD/PD No. 7 of 1977, complete in all
respects.
Total Cost for G-I 61,731.36
1 a) Excavation 3/44 6.17 6.17 5.00 0.19 1000 Cft 3569.30 679
b) Rehandling / Backfilling & 3/13a,3/24 (b) (ii) 0.04 1000 Cft 2019.60 77
Compaction
2 Concrete
a) P.C.C 3000 psi (1:2:4) 6 / 5 (f) 1.00 1.00 0.75 0.01 100 Cft 1886.55 14
b) P.C.C 2000 psi (1:3:6) 6 / 5 (h) 6.17 6.17 0.50 0.19 100 Cft 16282.30 3,096
c) R.C.C 3000 psi (1:2:4) 6 / 6 (a) (i) (3) 4.75 4.75 0.50 11.28 Cft 303.50 3,411
Deduct Cover 0.33 0.33 0.50 0.04 Cft
Net 11.24 Cft
3 Deformed steel (Grade 40) 6/9 (b) 0.25 100 Kg 10479.15 2,672
4 9" Thick brick masonary 1:3 CS 7/4/ (i) 19.00 0.75 4.50 0.64 100 Cft 18741.90 12,018
mortar
5 8'' dia Non Return Valve 23/30 (e) 1.00 No. 15253.55 15,254
6 Tail Piece with flanges 23 / 28 (b) (ii) 68.00 Kg. 100.90 6,861
8 Cement Plaster (1:3) 11/8 ( b ) 38.00 - 4.50 1.71 100 Sft 1577.35 2,697
9 6" (150 mm) thick R.C.C. manhole 21/17 1.00 No. 3821.05 3,821
cover with 3"x3"x¼" (75x75x6mm)
angle iron frame, 22" i/d as per
standard drawing STD/PD No. 7 of
1977, complete in all respects.
Total Cost for G-I 53,724.11
Total Cost for G-II 56,141.70
Total Cost for G-III 56,114.84
Appendix-II
RA 4 of 24
3 Deformed steel (Grade 40) 6/9 (b) 0.25 100 Kg 10479.15 2,672
4 9" Thick brick masonary 1:3 CS mortar 7/4/ (i) 19.00 0.75 4.50 0.64 100 Cft 18741.90 12,018
5 6'' dia Non Return Valve 23/30 (d) 1.00 No. 9131.00 9,131
6 Tail Piece with flanges 23 / 28 (b) (i) 57.00 Kg. 107.00 6,099
7 Mechanical Joint / Gabault Joint Tender Rates 2.00 No. 1278.00 2,556
8 C.S Plaster (1:3) 11/8 ( b ) 38.00 - 4.50 1.71 100 Sft 1577.35 2,697
9 6" (150 mm) thick R.C.C. manhole cover 21/17 1.00 No. 3821.05 3,821
with 3"x3"x¼" (75x75x6mm) angle iron
frame, 22" i/d as per standard drawing
STD/PD No. 7 of 1977, complete in all
respects.
Total Cost for G-I 46,398.86
Total Cost for G-II 48,486.81
Appendix-II
RA 4 of 24
uPVC 45 Bend
8" dia 10" dia 12" dia
Labour + Jointing
2 Material (2+3 % of
Material Cost) 394 393.75 1470 1470 2257.5 2257.5
Contractors profit,
3 Overheads & I/Tax
@ 20% of Total
1575 5880 9030
uPVC 90 Bend
8" dia 10" dia 12" dia
Labour + Jointing
2 Material (2+3 % of
Material Cost) 394 393.75 1470 1470 2257.5 2257.5
Labour + Jointing
2 Material (2+3 % of
Material Cost) 82.1 82.1 204.3 204.3 299.25 299.25
uPVC Tees
8"x6" 10"x6" 8"x4" 10"x8" 10"x4"
Labour + Jointing
2 Material (2+3 % of
Material Cost) 735 735 2043.65 2043.65 498.75 498.75 2405.1 2405.1 2043.65 2043.65
Contractors profit,
3 Overheads & I/Tax @
20% of above total 2940 8174.6 1995 9620.4 8174.6
uPVC Tees
12"x6" 12"x8" 6"x4" 12"x10"
Labour + Jointing
2 Material (2+3 % of
Material Cost) 2492 2492 3043.7 3043.7 259.9 259.9 4071.45 4071.45
Contractors profit,
3
Overheads & I/Tax @
20% of above total 9968 12174.8 1039.6 16285.8
Labour + Jointing
2 Material (2+3 % of
Material Cost) 461 461.05 1797.15 1797.15 2655.4 2655.4
Total
9682.05 37740.15 55763.4
Contractors profit,
3 Overheads & I/Tax 1844.20 7188.60 10621.6
@ 20% of Total
Labour + Jointing
2 Material (2+3 % of
Material Cost) 220.5 220.5 882 882 882 882
Labour + Jointing
Material (2+3 % of
2 Material Cost) 776.85 776.85 1233.75 1233.75 1233.75 1233.75
Contractors profit,
3 Overheads & I/Tax @
20% of above total 3107.4 4935 4935
1 a) Excavation 3/44 6.17 6.17 5.00 0.19 1000 Cft 3569.30 679
b) Rehandling / Backfilling & Compaction 3/13a,3/24 (b) (ii) 0.04 1000 Cft 2019.60 77
2 Concrete
a) P.C.C 3000 psi (1:2:4) 6 / 5 (f) 1.00 1.00 0.75 0.01 100 Cft 18886.55 142
b) P.C.C 2000 psi (1:3:6) 6 / 5 (h) 6.17 6.17 0.50 0.19 100 Cft 16282.30 3,096
c) R.C.C 3000 psi (1:2:4) 6 / 6 (a) (i) (3) 4.75 4.75 0.50 11.28 Cft 303.50 3,411
Deduct Cover 0.33 0.33 0.50 0.04 Cft
Net 11.24 Cft
3 Deformed steel (Grade 40) 6/9 (b) 0.25 100 Kg 10479.15 2,672
4 9" Thick brick masonary 1:3 CS mortar 7/4/ (i) 19.00 0.75 4.50 0.64 100 Cft 18741.90 12,018
5 12'' dia Sluice Valve 23/30 (g) 1.00 No. 25556.05 25,556
6 Tail Piece with flanges 12" dia 2Nos 23 / 28 (b) (i) 82.00 Kg. 100.90 8,274
7 Mechanical Joint / Gabault Joint Ref Appendix I 2.00 No. 2556.00 5,112
(RA11 of 28)
8 Cement Plaster (1:3) 11/8 ( b ) 38.00 - 4.50 1.71 100 Sft 1577.35 2,697
9 6" (150 mm) thick R.C.C. manhole cover 21/17 1.00 No. 3821.05 3,821
with 3"x3"x¼" (75x75x6mm) angle iron
frame, 22" i/d as per standard drawing
STD/PD No. 7 of 1977, complete in all
respects.
Total Cost for G-I 67,554.71
1 a) Excavation 3/44 6.17 6.17 5.00 0.19 1000 Cft 3569.30 679
b) Rehandling / Backfilling & Compaction 3/13a,3/24 (b) (ii) 0.04 1000 Cft 2019.60 77
2 Concrete
a) P.C.C 3000 psi (1:2:4) 6 / 5 (f) 1.00 1.00 0.75 0.01 100 Cft 18886.55 142
b) P.C.C 2000 psi (1:3:6) 6 / 5 (h) 6.17 6.17 0.50 0.19 100 Cft 16282.30 3,096
c) R.C.C 3000 psi (1:2:4) 6 / 6 (a) (i) (3) 4.75 4.75 0.50 11.28 Cft 303.50 3,411
Deduct Cover 0.33 0.33 0.50 0.04 Cft
Net 11.24 Cft
3 Deformed steel (Grade 40) 6/9 (b) 0.25 100 Kg 10479.15 2,672
4 9" Thick brick masonary 1:3 CS mortar 7/4/ (i) 19.00 0.75 4.50 0.64 100 Cft 18741.90 12,018
5 10'' dia Sluice Valve 23/30 (f) 1.00 No. 20584.70 20,585
6 Tail Piece with flanges 23 / 28 (b) (ii) 78.00 Kg. 100.90 7,870
7 Mechanical Joint / Gabault Joint Ref Appendix I 2.00 No. 2130.00 4,260
(RA 11 of 28)
8 Cement Plaster (1:3) 11/8 ( b ) 38.00 4.50 1.71 100 Sft 1577.32 2,697
9 6" (150 mm) thick R.C.C. manhole cover 21/17 1.00 No. 3821.05 3,821
with 3"x3"x¼" (75x75x6mm) angle iron
frame, 22" i/d as per standard drawing
STD/PD No. 7 of 1977, complete in all
respects.
Total Cost for G-I 61,327.71
Total Cost for G-II 64,087.46
Total Cost for G-III 64,056.79
Appendix-II
RA 15 of 24
1 a) Excavation 3/44 6.17 6.17 5.00 0.19 1000 Cft 3569.30 679
b) Rehandling / Backfilling & Compaction 3/13a,3/24 (b) (ii) 0.04 1000 Cft 2019.60 77
2 Concrete
a) P.C.C 3000 psi (1:2:4) 6 / 5 (f) 1.00 1.00 0.75 0.01 100 Cft 18886.55 142
b) P.C.C 2000 psi (1:3:6) 6 / 5 (h) 6.17 6.17 0.50 0.19 100 Cft 16282.30 3,096
c) R.C.C 3000 psi (1:2:4) 6 / 6 (a) (i) (3) 4.75 4.75 0.50 11.28 Cft 303.50 3,411
Deduct Cover 0.33 0.33 0.50 0.04 Cft
Net 11.24 Cft
3 Deformed steel (Grade 40) 6/9 (b) 0.25 100 Kg 10479.15 2,672
4 9" Thick brick masonary 1:3 CS mortar 7/4/ (i) 19.00 0.75 4.50 0.64 100 Cft 18741.90 12,018
5 8'' dia Sluice Valve 23/30 (e) 1.00 No. 15253.55 15,254
6 Tail Piece with flanges 23 / 28 (b) (ii) 68.00 Kg. 100.90 6,861
7 Mechanical Joint / Gabault Joint Ref Appendix I 2.00 No. 1562.00 3,124
(RA 11 of 28)
8 Cement Plaster (1:3) 11/8 ( b ) 38.00 - 4.50 1.71 100 Sft 1577.35 2,697
9 6" (150 mm) thick R.C.C. manhole cover 21/17 1.00 No. 3821.05 3,821
with 3"x3"x¼" (75x75x6mm) angle iron
frame, 22" i/d as per standard drawing
STD/PD No. 7 of 1977, complete in all
respects.
Total Cost for G-I 53,851.61
Total Cost for G-II 56,274.94
Total Cost for G-III 56,248.01
Appendix-II
RA 16 of 24
1 a) Excavation 3/44 6.17 6.17 5.00 0.19 1000 Cft 3569.30 679
b) Rehandling / Backfilling & 2019.60
3/13a,3/24 (b) (ii) 0.04 1000 Cft 77
Compaction @ 20% of (a)
2 Concrete
a) P.C.C 3000 psi (1:2:4) 6 / 5 (f) 1.00 1.00 0.75 0.01 100 Cft 18886.55 142
b) P.C.C 2000 psi (1:3:6) 6 / 5 (h) 6.17 6.17 0.50 0.19 100 Cft 16282.30 3,096
c) R.C.C 3000 psi (1:2:4) 6 / 6 (a) (i) (3) 4.75 4.75 0.50 11.28 Cft 303.50 3,411
Deduct Cover 0.33 0.33 0.50 0.04 Cft
Net 11.24 Cft
3 Deformed steel (Grade 40) 6/9 (b) 0.25 100 Kg 10479.15 2,672
4 9" Thick brick masonary 1:3 CS mortar 7/4/ (i) 19.00 0.75 4.50 0.64 100 Cft 18741.90 12,018
5 6'' dia Sluice Valve 23/30 (d) 1.00 No. 9131.00 9,131
6 Tail Piece with flanges 23 / 28 (b) (i) 57.00 Kg. 107.00 6,099
8 C.S Plaster (1:3) 11/8 ( b ) 38.00 - 4.50 1.71 100 Sft 1577.35 2,697
9 6" (150 mm) thick R.C.C. manhole 21/17 1.00 No. 3821.05 3,821
cover with 3"x3"x¼" (75x75x6mm) angle
iron frame, 22" i/d as per standard
drawing STD/PD No. 7 of 1977,
complete in all respects.
Total Cost for G-I 46,398.86
Total Cost for G-II 48,486.81
Appendix-II
RA 17 of 24
3" diameter 4" diameter 6" diameter 8" diameter 10" diameter 12" diameter
1 Material
Gabault Joint NS No. 1 4750 4750 6000 6000 9750 9750 12750 12750 19750 19750 25000 25000
Labour (2% of
2 95 120 195 255 395 500
Material Cost)
Contractor's
5 Total Cost for G-I 5814.00 7344.00 11934.00 15606.00 24174.00 30600.00
Total Cost for G-II 6075.63 7674.48 12471.03 16308.27 25261.83 31977
Total Cost for G-III 6072.723 7670.808 12465.063 16300.467 25249.743 31961.7
Appendix-II
RA 18 of 24
RATE ANALYSIS
1 a) Excavation 3/44 6.17 6.17 5.00 0.19 1000 Cft 3569.30 679
b) Rehandling / Backfilling & 3/13a,3/24 (b) (ii) 0.04 1000 Cft 2019.60 77
Compaction @ 20% of (a)
2 Concrete
a) P.C.C 3000 psi (1:2:4) 6 / 5 (f) 1.00 1.00 0.75 0.01 100 Cft 18886.55 142
b) P.C.C 2000 psi (1:3:6) 6 / 5 (h) 6.17 6.17 0.50 0.19 100 Cft 16282.30 3,096
c) R.C.C 3000 psi (1:2:4) 6 / 6 (a) (i) (3) 4.75 4.75 0.50 11.28 Cft 303.50 2,886
Deduct Cover 2.13 2.13 0.50 1.77 Cft
Net 9.51 Cft
4 9" Thick brick masonary 1:3 CS 7/4/ (i) 19.00 0.75 4.50 0.64 100 Cft 18741.90 12,018
morter
5 R.C.C Chamber Cover 21/17 1.00 1.00 Per Set 3821.05 1,000
7 Tail Piece with flanges 23 / 28 (b) (i) 57.00 Kg. 100.90 5,751
8 Mechanical Joint / Gabault Joint Ref Appendix I 2.00 No. 11934 23,868
(RA 11 of 28)
9 Plastering (1:3) 11/8 ( b ) 19.00 - 4.50 0.86 100 Sft 1577.35 1,349
1 a) Excavation 3/44 6.17 6.17 5.00 0.19 1000 Cft 3569.30 679
b) Rehandling / Backfilling & 2019.60
3/13a,3/24 (b) (ii) 0.04 1000 Cft 77
Compaction @ 20% of (a)
2 Concrete
a) P.C.C 3000 psi 6 / 5 (f) 1.00 1.00 0.75 0.01 100 Cft 18886.55 142
b) P.C.C 2000 psi 6 / 5 (h) 6.17 6.17 0.50 0.19 100 Cft 16282.30 3,096
c) R.C.C 3000 psi 6 / 6 (3) 4.75 4.75 0.50 11.28 Cft
Deduct Cover 2.13 2.13 0.50 1.77 Cft
Net 6 / 6 (a) (i) (3) 9.51 Cft 303.50 2,886
5 R.C.C Chamber Cover 21/17 1.00 1.00 Per Set 3821.05 3,821
6 6'' Sluice Gate Valve 23/30 (d) 1.00 No. 12862.05 12,862
8 Tail Piece with flanges 23 / 28 (b) (i) 57.00 Kg. 100.90 5,751
9 C.S Plaster (1:3) 11/8 ( b ) 38.00 - 4.50 1.71 100 Sft 1577.35 2,697
1 a) Excavation 3/44 6.17 6.17 5.00 0.42 1000 Cft 3569.30 1,501
b) Rehandling / Backfilling &
3/13a,3/24 (b) (ii) 0.08 1000 Cft 2019.60 170
Compaction @ 20% of (a)
2 Concrete
a) P.C.C 3000 Psi 6 / 5 (f) 1.00 1.00 0.75 0.01 100 Cft 18886.55 142
b) P.C.C 2000 Psi 6 / 5 (h) 6.17 6.17 0.50 0.19 100 Cft 16282.30 3,096
c) R.C.C 3000 Psi 6 / 6 (a) (i) (3) 4.75 4.75 0.50 11.28 Cft 303.50 3,424
Deduct Cover 2.13 2.13 0.50 1.77 Cft
Net 9.51 Cft
5 R.C.C Chamber Cover 21/17 1.00 1.00 Per Set 3821.05 3,821
7 Tail Piece with flanges 23 / 28 (b) (i) 35.00 Kg. 100.90 3,532
8 C.S Plaster (1:3) 11/8 ( b ) 38.00 - 4.50 1.71 100 Sft 1577.35 2,697
2 P.C.C 3000psi (1:2:4) 6 / 5 (f) 1.00 1.00 1.00 0.010 100 Cft 18886.55 189
Small iron work as indication plate 25/9 0.02 1.00 2.00 0.09 100Kg 15071.85 1,396
3 including cutting, drilling, riveting,
handling, assembling and fixing.
4 Erection and fitting in position 25/11 0.02 1.00 2.00 0.09 100Kg 560.10 52
Preparing surface and painting of small 13/5(f) (i) 1.00 2.00 2.00 No. 26.96 54
5 detached articles not exceeding one sft.
Of painted surface.Prime + 2 coats.
Writing letters or figures, per letter, per 13/12 25.00 Per letter 10.75 269
6 inch height. per inch
height
RATE ANALYSES
1 Small iron work, such as gusset 25/(9+11) 100 Kg 0.44 15,632 6,878
plates, knees, bends, stirrups,
straps, rings, etc. including cutting,
drilling, riveting, handling,
assembling and fixing; but
excluding erection in position.
including erection and fitting in
position, complete in all respects.
1 Material
a Clamp Saddle 90 mm x 3/4'' No. 1.00 567.00 567.00
b Brass Ferrule (Gun metal) No. 1.00 300.00 300.00
c Female Threaded Adaptor 25x3/4" No. 1.00 79.00 79.00
d End cap No. 1.00 1,580.00 1580.00
Material Cost 2526.00
2 Labour
Making connection of 3/4" internal dia of G.I pipe
with watersupply pipe line including excavation of
trench and refilling, complete. L/S 350.00 350.00
Labour Cost 350
Total (Material & Labour) 2876.00
Contractor's Profit & Overheads 20.00% 575.2
Total Cost for one house connection (Rs.) for G-I 3451.00
Total Cost for one house connection (Rs.) for G-II 3606.30
Total Cost for one house connection (Rs.) for G-III 3604.57
1 Material
a Clamp Saddle 110 mm x 3/4'' No. 1.00 468.00 468.00
b Brass Ferrule (Gun metal) No. 1.00 300.00 300.00
c Female Threaded Adaptor 25x3/4" No. 1.00 79.00 79.00
d End cap No. 1.00 1,989.00 1989.00
Material Cost 2836.00
2 Labour
Making connection of 3/4" internal dia of G.I pipe
with watersupply pipe line including excavation of
trench and refilling, complete. L/S 350.00 350.00
Labour Cost 350
Total (Material & Labour) 3186.00
Contractor's Profit & Overheads 20.00% 637.2
Total Cost for one house connection (Rs.) for G-I 3823.00
Total Cost for one house connection (Rs.) for G-II 3995.04
Total Cost for one house connection (Rs.) for G-III 3993.12
Appendix-II
RA 24 of 24
1 Material
a Clamp Saddle 160 mm x 3/4'' No. 1.00 862.00 862.00
b Brass Ferrule (Gun metal) No. 1.00 300.00 300.00
c Female Threaded Adaptor 25x3/4" No. 1.00 79.00 79.00
d End cap No. 1.00 2,310.00 2310.00
Material Cost 3551.00
2 Labour
Making connection of 3/4" internal dia of G.I pipe
with watersupply pipe line including excavation of
trench and refilling, complete. L/S 350.00 350.00
Labour Cost 350
Total (Material & Labour) 3901.00
Contractor's Profit & Overheads 20.00% 780.2
Total Cost for one house connection (Rs.) for G-I 4681.00
Total Cost for one house connection (Rs.) for G-II 4891.65
Total Cost for one house connection (Rs.) for G-III 4889.30