Professional Documents
Culture Documents
学生还查看了以下学习集
此学习集的词语(93)
which of the following is the most establishing a sense of urgency that changes needed
appropriate first step in a significant
organizational change?
which of the following data elements is current backlog for required work centers
required to backward schedule work
orders for component parts in a push
production environment
https://quizlet.com/417082781/cpim-part-2-practice-exam-2-flash-cards/ 1/15
2023/11/26 00:49 CPIM part 2 practice exam 2单词卡 | Quizlet
CPIM partmethods
fail safe work 2 practice exam
include which of 2 installing poka -yoke 学习
the following activities
a company uses centralized planning at when the projected available balance for a future given period is
the manufacturing site for distribution negative or below the safety stock level
system replenishment decisions. how is
the reorder point typically established
for this type of planning
a company competes in an industry it can delay start of design and still meet the demand
that serves other manufacturers. their
customers play a significant role in
defining requirements, and most
products have a 7 to 10 year life. what is
the most likely advantage a company in
this industry would realize from having
a fast product and service design
process
https://quizlet.com/417082781/cpim-part-2-practice-exam-2-flash-cards/ 2/15
2023/11/26 00:49 CPIM part 2 practice exam 2单词卡 | Quizlet
CPIM part 2 practice exam 2 determination of the materials needed to make the products
学习in
the master production schedule
objectives of the detailed capacity explanation: The role of planning the materials to build parents
requirements planning process include and sub-assemblies belongs to the material requirements
all the following except planning process, not the capacity planning process
it remains constant
improvement programs in a
manufacturing company have increased
efficiency and utilization have no impact on theoretical capacity
efficiency 10% and utilization 5%. what is
the effect on theoretical capacity
module 3 section g topic 1
https://quizlet.com/417082781/cpim-part-2-practice-exam-2-flash-cards/ 3/15
2023/11/26 00:49 CPIM part 2 practice exam 2单词卡 | Quizlet
based on the information below for a production plan= ending inventory - starting inventory + forecast
make to stock company, what is the demand
production plan
1,000- 1,300 + 1,600=1,300
starting inventory= 1,300
forecasted demand= 1,600 module 2 section e topic 3
desired ending inventory= 1,000
a company has a lag capacity strategy. fully utilizes capacity, so unit cost are lower***
if demand growth is predictable, this
strategy module 1 section H topic 2
standard hours
what is the most appropriate unit of in a job shop, a critical component of cost and control is
measure for capacity requirements managing production to meet the standard hours originally
planning for a job shop assigned to product production
https://quizlet.com/417082781/cpim-part-2-practice-exam-2-flash-cards/ 4/15
2023/11/26 00:49 CPIM part 2 practice exam 2单词卡 | Quizlet
demand management***
distribution replenishment requirements
enter a manufacturer's planning distribution orders have the same level of importance as a
hierarchy at which of the following customer order
levels
module 2 section f topic 1
a company's high volume products are high volume products will be under costed
produced on an automated
manufacturing line, and it's low volume cost reduction efforts will be biased in favor of labor cost
products are produced using a labor reductions
intensive method. The use of a cost
accounting system in which overheads module 1 section g topic 2
are allocated to product cost as a
percentage of direct labor hours will
have which of the following results
which of the following is the most required production rate for each line***
appropriate output of master planning
of resources for a firm that produces to module 2 section A topic 3
forecast using production lines
https://quizlet.com/417082781/cpim-part-2-practice-exam-2-flash-cards/ 5/15
2023/11/26 00:49 CPIM part 2 practice exam 2单词卡 | Quizlet
CPIM part
input/output 2 practice
control exam 2
manages lead actual output 学习
times by adjusting the input of load into
the system on the bases of module 4 section c topic 2
which of the following are prerequisites inventory record, bill of material, and planning factors
for a material requirements planning
system module 3 section d topic 2
an environment using backflush when production against the parent item is reported***
inventory relief, when are perpetual
onhand inventory counts relieved module 3 section c topic 3
The flow of received purchase parts is a supplier delivery performance measurement should be based
from receipt at the dock to on actual receipts at the dock
receiving/inspection and then to
receipt at the stores, at which time the a resource constraint could cause parts to be received at the
quantity received is entered in the dock but not into the stores on schedule
Enterprise resources planning system.
which of the following statements module 4 section c topic 2
about this situation are true
receiving inspection
which of the following is not a part of a
quality at the source effort
module 4 section g topic 1
https://quizlet.com/417082781/cpim-part-2-practice-exam-2-flash-cards/ 6/15
2023/11/26 00:49 CPIM part 2 practice exam 2单词卡 | Quizlet
CPIM
the sales part 2 practice
and operation planningexam 2 business planning horizon 学习
horizon should be at least as long as module 2 section d topic 1
which of the following
forecast
what technique best determines
production and inventory quantities for since the demand for independent demand items is unknown, it
goods and services with independent will need to be forecasted
demand
module 3 section A topic 2
continuous improvement
which of the following is synonymous
with kaizen
kaizen is the Japanese term for improvement
https://quizlet.com/417082781/cpim-part-2-practice-exam-2-flash-cards/ 7/15
2023/11/26 00:49 CPIM part 2 practice exam 2单词卡 | Quizlet
CPIM
a resellerpart 2 practice
of theater exam 2
tickets has an distressed 学习
inventory of two dozen tickets for a distressed goods are products that are damaged or close to
play that is scheduled to start an 8 their expiration date and cannot be sold at full price
hours. which of the following would be module 3 section A topic 2
the most appropriate classification of
the inventory of the tickets
inventory accounting.
A change from reporting operations to production activity control.
reporting only parts completed master scheduling.
requires all of the following systems to cost accounting.
be changed except A; Master scheduling***
Module 4, Section C, Topic 3
A company's process design and Review the current work procedures; identify the problem areas;
manufacturing departments are solve problems and develop new methods; implement new
developing a team to run a kaizen methods.
event to improve production methods
and standards. Which of the following Module 4, Section G, Topic 2
lists the steps for the kaizen project in
the correct order?
https://quizlet.com/417082781/cpim-part-2-practice-exam-2-flash-cards/ 8/15
2023/11/26 00:49 CPIM part 2 practice exam 2单词卡 | Quizlet
"The voice of the customer" refers to III. Producing reliable products consistently
identifying customer wants through IV. Conducting in-depth qualitative customer interviews
which two of the following Module 4, Section F, Topic
mechanisms?
Which of the following statements best The chase production planning approach should be used to
characterizes the relationship between facilitate response to demand.
sales and operations planning (S&OP) Module 2, Section D, Topic 3
and lean production?
Which of the following inventory The LIFO method assumes that the newest (last in) item in stock
accounting methods would indicate the is the first sold. In times of rising prices, replacement is at the
lowest inventory value on the balance current price, and this current price is higher than the
sheet in times of steadily rising prices? accounted-for cost for the inventory that did not sell. In a falling
price market, existing inventory is overvalued.
Module 3, Section A, Topic 3
Which of the following capacity I. Load is based on both planned and open orders.
planning (load) report characteristics III. Load distribution is based on actual lead times.
can be attributed to material Module 3, Section G, Topic 1
requirements planning (MRP)?
https://quizlet.com/417082781/cpim-part-2-practice-exam-2-flash-cards/ 9/15
2023/11/26 00:49 CPIM part 2 practice exam 2单词卡 | Quizlet
Using phantom bills of material (BOMs) A phantom BOM will not have any work orders because the
will result in which of the following? requirements will pass straight through the parent item to the
components. Since there are no work orders, the number of
transactions will be less.
https://quizlet.com/417082781/cpim-part-2-practice-exam-2-flash-cards/ 10/15
2023/11/26 00:49 CPIM part 2 practice exam 2单词卡 | Quizlet
CPIM part 2 practice exam 2 Sequence of operations and work centers needed 学习
RATIONALE
Which of the following data elements is
In backward scheduling, the schedule is computed starting with
required to backward schedule work
the due date for the order and working backward to determine
orders for component parts in a push
the required start date and/or due dates for each operation.
production environment?
Thus, the sequence of operations and work centers needed must
be known
I. End-item demand
A forecasting system is required for
III. Replacement part demand
which of the following elements of total
RATIONALE
demand of an item?
End items and replacement parts are normally forecasted.
I. Efficiency
III. Scrap
RATIONALE
The actual cost of an order can be
Efficiency can affect actual cost because the actual production
different from the standard cost
time will be impacted by how much time is actually spent
because of which of the following
producing a product. Scrap creates excess material, labor, and
factors?
overhead costs.
A company uses material requirements independent demand cannot be imploded to identify the parent
planning (MRP) and reorder point. RATIONALE
Which of the following most relates to There is no parent for an item subject to independent demand.
the planner's ability to determine the The demand source of the requirement on the item will be the
source of gross requirements for a part demand order.
having both dependent and
independent demand? For more information, refer to Module 3, Section E, Topic 1
https://quizlet.com/417082781/cpim-part-2-practice-exam-2-flash-cards/ 11/15
2023/11/26 00:49 CPIM part 2 practice exam 2单词卡 | Quizlet
https://quizlet.com/417082781/cpim-part-2-practice-exam-2-flash-cards/ 12/15
2023/11/26 00:49 CPIM part 2 practice exam 2单词卡 | Quizlet
CPIM part 2 practice exam 2 II. Listening to requests from potential customers 学习
IV. Conducting in-depth qualitative customer interviews
RATIONALE
"The voice of the customer" refers to "Listening to the voice of the customer" refers to the information
identifying customer wants through marketing and product design need when creating new
products. The idea is to design new products that reflect what
which two of the following the customer actually wants versus what marketing thinks they
mechanisms? should have.
https://quizlet.com/417082781/cpim-part-2-practice-exam-2-flash-cards/ 13/15
2023/11/26 00:49 CPIM part 2 practice exam 2单词卡 | Quizlet
The customer order backlog is defined all received orders not yet shipped.
as
https://quizlet.com/417082781/cpim-part-2-practice-exam-2-flash-cards/ 14/15
2023/11/26 00:49 CPIM part 2 practice exam 2单词卡 | Quizlet
https://quizlet.com/417082781/cpim-part-2-practice-exam-2-flash-cards/ 15/15