You are on page 1of 8

Case Study

Contractors’ Claims in an EPC and Turnkey Contract:


Lessons Learned from a Hydropower Project
Sushmit Sharma Bhattarai 1; Krishna P. Kisi, Ph.D., M.ASCE 2; and Rujan Kayastha 3

Abstract: This study focuses on the contractor’s claims on a hydropower project contracted under an international engineering procurement
Downloaded from ascelibrary.org by The University of Manchester on 12/14/23. Copyright ASCE. For personal use only; all rights reserved.

and construction (EPC) and turnkey contract in Nepal. The contractor faced challenges from the mobilization phase and submitted multiple
claims to the employer for time extensions and additional overhead costs. This study identified 80 claims for a time extension and additional
overhead costs. Through content analysis, this study grouped these claims under six categories: natural disaster, strike, unforeseen risk,
material shortage, payment, and the COVID-19 pandemic. First, the study analyzed the claim type, outcome, and decision criteria of the
claims. Next, the analysis presented decisions based on general conditions of contract (GCC) and the particular conditions of contract (PCC)
clauses. The study found that the employer granted a time extension to most of the claims under natural disaster under force majeure and
rejected most of the claims under the other five groups. Finally, the study presents findings and lessons learned from the case study, including
the relevant GCC and PCC clauses used in claims resolution. The findings and lessons learned from this case study could help employers and
international EPC contractors who want to build hydropower projects in Nepal. DOI: 10.1061/JLADAH.LADR-915. © 2022 American
Society of Civil Engineers.
Author keywords: Claim; Project management; Engineering procurement and construction (EPC); Hydropower project; Silver Book.

Introduction eliminate the risk of project failure; project delays and cost over-
runs can have severe effects on the employer. Although the EPC
The construction sector is one of the fastest growing fields today, method leaves additional uncertainties, which could make EPC
and it is defined as complex and high risk, and involves a variety of projects risky, especially for contractors (Oztas and Okmen
stakeholders, including employers, consultants, and contractors. 2004), it can help achieve early builder involvement, cost savings,
Similarly, the industry is notable for the high number of claims that and shorter project durations than the traditional way (Hale et al.
arise regularly because of its unique qualities. Claims—a right 2009). This does not happen on all EPC projects. As discussed
granted to the party who is entitled to recompense for damages suf- subsequently, this study collected and analyzed the contractor’s
fered by the other party (Simon 1979)—are one of the issues that claims on a hydropower project under an international EPC con-
a construction project may encounter and can result in a variety tract in Nepal that took more than twice the anticipated project
of consequences such as payment delays, time extensions, and duration to build.
suspension. In 2010, Nepal implemented the first EPC approach for the con-
Because of the complexity of the construction project and the struction of the Upper Trishuli-3A hydropower project (Pun 2014).
variety of claims connected with many stakeholders, choosing a Hale et al. (2009) suggested that the EPC approach treated the con-
suitable contracting method can help project stakeholders over- tractor as a single entity responsible for the design, procurement,
come obstacles (Schramm et al. 2010). Because of this, the tradi- and construction to achieve superior performance in areas such as
tional design-bid-build method has been replaced by several new early builder involvement, innovation, cost savings, schedule re-
and better ways to get projects done, such as construction manage- duction, and improved quality. In 2014, another EPC contract
ment (CM), design-build (DB), and engineering procurement and was executed to construct a 111-MW hydropower project in Nepal,
construction (EPC) (Wang and Liu 2021). observing that the progress of Upper Trishuli-3A was better than
EPC contractors, both new and experienced, who opt for lump- any other design-bid-build contract. However, several challenges
sum or fixed-price agreements have more inherent risks (Thweatt were faced during the execution of the project, and the contractor
and Long 2017). Although the employer may use lump-sum or made multiple claims. This study thus focuses on the contractor’s
fixed-price contracts to transfer risks to the contractor, this does not claims on this second EPC hydropower project.
Since the mobilization of the contractor at the site, the contractor
1
Graduate Assistant, Dept. of Engineering Technology, Texas State faced challenges such as riot and disorder by the local public and
Univ., San Marcos, TX 78666. Email: hsy4@txstate.edu landslide blockage on the access road. The contractor submitted
2
Assistant Professor, Dept. of Engineering Technology, Texas State notice letters and later submitted claims against the employer. Most
Univ., San Marcos, TX 78666 (corresponding author). ORCID: https:// of the claims were related to extension of time (EoT). This study
orcid.org/0000-0003-1850-5747. Email: kpkisi@txstate.edu examined the contractor’s notice of letter and the employer’s repre-
3
Graduate Assistant, Dept. of Engineering Technology, Texas State sentative’s contractual correspondence on the project. This study also
Univ., San Marcos, TX 78666. Email: r_k162@txstate.edu
gathered contractor letters and minutes of meetings held throughout
Note. This manuscript was submitted on June 30, 2022; approved on
October 28, 2022; published online on December 29, 2022. Discussion per- construction from the years 2014 to 2020.
iod open until May 29, 2023; separate discussions must be submitted for Numerous studies can be found on construction claims and
individual papers. This paper is part of the Journal of Legal Affairs and claims in hydropower projects. Similarly, contractual issues and
Dispute Resolution in Engineering and Construction, © ASCE, ISSN causes of delays in hydropower projects have been identified by
1943-4162. several researchers. However, none of the studies have explored

© ASCE 05022011-1 J. Leg. Aff. Dispute Resolut. Eng. Constr.

J. Leg. Aff. Dispute Resolut. Eng. Constr., 2023, 15(2): 05022011


the claims of the hydropower projects under the EPC contract in FIDIC Suite of Contracts
Nepal. This study focuses on a case study to fill the gap in the lit-
The FIDIC contract suite is produced by the International Feder-
erature on claims on international hydropower EPC projects. This
ation of Consulting Engineers. The FIDIC Silver Book, about EPC
study informs international contractors before bidding on hydro-
and turnkey projects contracts, is used when the contractor not only
power projects in Nepal about the potential types of claims, accep-
takes most of the risk in design and construction but also has to
tance and rejection decisions, and International Federation of
hand over the project to the employer in a fully operational state
Consulting Engineers (FIDIC) clauses referenced in the decisions.
(Shnookal and Charrett 2010). Hosie (2007) states that the FIDIC
Silver Book is followed in response to the recognition of the need
Description of the Case Study for standardized contract forms when the contract’s final price cer-
tainty and, in many cases, the completion date certainty is of ex-
The project studied and analyzed in this case study is one of the treme importance.
largest hydropower projects in Nepal. It is a 111-MW hydropower FIDIC contracts are logical and coherent, with a logical arrange-
Downloaded from ascelibrary.org by The University of Manchester on 12/14/23. Copyright ASCE. For personal use only; all rights reserved.

project. The employer invited sealed bids for prequalification ment of clauses that have been drafted by independent consulting
from national and international bidders who were interested in engineers and lawyers with experience in the drafting and manage-
undertaking the engineering, procurement, and construction of ment of international construction contracts. FIDIC contracts in-
the project. Eleven out of 20 submitted bidders were selected clude project management procedures essential for the efficient
as prequalified bidders and invited to submit financial competi- execution of the work. A FIDIC contract is not just about docu-
tive bidding. Most of the bidders were from China, India, and menting the contractual entitlements and risk shifting between the
Republic of Korea. The bidding evaluation was conducted as parties; it also provides the framework of the relationship between
per the procedures of the Federal Democratic Republic of Nepal the parties as it occurs on site.
and the employer, as set forth in the bidding documents to the General conditions of contract (GCCs) clauses that are relevant
lowest bidders. to this research study and risk allocation to the employer and the
The project was awarded under an EPC contract to one of contractor are listed in Table 1. Project-specific amendments to
the renowned Chinese contractors after bid evaluation in January FIDIC GCCs are detailed in the project particular conditions of
2014. The employer contracted EPC and turnkey projects with the contract (PCCs). This ensures that any changes that are made to the
Chinese contractor under the FIDIC Silver Book (FIDIC 1999) to standard conditions are obvious and transparent. Insisting on this
carry out civil and hydromechanical works worth USD 97.64 million process maintains the integrity of the FIDIC GCCs and reduces the
including all taxes. As detailed in the FIDIC Silver Book, the em- time for assessing tender documents. It also minimizes the possibil-
ployer hired an international consultant as the employer’s repre- ity that a tenderer might be unaware of a project-specific amend-
sentative. The employer’s representative’s duty was to review the ment that significantly increases the contractor’s risks.
notice of letter submitted by the contractor and take action as and Some provisions in the FIDIC GCCs are incompatible with the
when required. Nepalese governing law of contract and site conditions. Therefore,
The project duration was set to 1,275 days (3 years and EPC projects built in Nepal need PCCs to change the FIDIC GCCs
6 months) from the commencement date of January 2014. The so they are in line with Nepalese law and meet project needs (Dulal
project was expected to be completed in July 2017 according to and Shrestha 2021).
the contractor’s submitted schedule. However, multiple unexpected
events such as an earthquake in Nepal occurred during the con- FIDIC and EPC Contract in Hydropower Project
struction of the project, causing significant delays in completion.
The project has not been completed yet and the current status shows Due to the complexity of the project and the requirements for timely
civil and hydromechanical works at headworks are 95% completed, completion to meet the electricity demand, hydropower projects
whereas concrete lining works of the tunnel are 80% completed.
The project is scheduled to open in April 2023 as per the unaudited
financial report published by the company on October 17, 2022 Table 1. FIDIC general conditions and risk allocation
(RGHPCL 2022). Risk allocation
FIDIC silver
book clause General conditions Employer Contractor
Literature Review 4.1 Contractor’s general obligation — X
4.10 Site data X X
Megaprojects, such as large hydropower projects, are complicated, 4.12 Unforeseeable difficulties — X
with many risks that employers attempt to transfer to contractors 4.13 Rights-of-way and facilities — X
using the EPC contract. In such circumstances, the EPC module 4.14 Avoidance of interference — X
developed as the ideal contemporary method of contracting for em- 4.15 Access route — X
ployers because, with the EPC module, the risks of project man- 4.16 Transport of goods — X
4.23 Contractor’s operations on site — X
agement and many other risks are transferred from the employer to
7.6 Remedial work — X
the contractor (Singh 2000). The EPC approach is becoming more 8.4 Extension of time for completion X —
widely used in international markets (Guo et al. 2010). 8.5 Delay caused by authorities X —
Due to the abundance of water resources in Nepal, hydropower 11.4 Failure to remedy defects — X
projects are one of the country’s major infrastructures, with both do- 14.1 Contract price — X
mestic and foreign investors involved in their construction (Prajapati 14.2 Advance payment X X
2015). In Nepal, large hydropower projects are developed by public 14.3 Application of interim payments — X
entities and generally use the FIDIC suite of contracts, most notably 14.8 Delayed payment X —
the FIDIC Silver Book. The following section provides some rel- 19.2 Notice of force majeure X X
evant information in the literature pertaining to this contracting 19.4 Consequences of force majeure X —
20.1 Contractor’s claims X —
method.

© ASCE 05022011-2 J. Leg. Aff. Dispute Resolut. Eng. Constr.

J. Leg. Aff. Dispute Resolut. Eng. Constr., 2023, 15(2): 05022011


need a fixed completion date, a fixed completion price, no or limited Methodology
technology risk, output guarantees, and liquidated damages for both
delay and performance and security from the contractor, and restric- This study used a case study approach to identify, explain, and
tions on the ability of the contractor to claim an EoT and additional explore the real phenomenon of the claims. Conducting case stud-
cost (DLA Piper 2011). Chu (1979) pointed out that hydropower ies is beneficial because it provides empirical inquiry appropriate
building projects involve many different types of work and the in- to determining the how and why of phenomena and contributes to
stallation of many different types of structural elements. Chu also understanding phenomena in a holistic and real-life context (Yin
pointed out that underground work often poses a much higher con- 2018).
struction risk. Creswell (2014) defined case study research as a qualitative ap-
The literature also shows that there are EPC hydropower proj- proach in which the investigator explores a real-life, contemporary
ects executed successfully. For example, the 300-MW Chamera bounded system (a case) or multiple bound systems (cases) over
Hydroelectric Project in India that was implemented on a turnkey time, through detailed, in-depth data collection involving multiple
Downloaded from ascelibrary.org by The University of Manchester on 12/14/23. Copyright ASCE. For personal use only; all rights reserved.

contract was successfully commissioned due to continuous and sources of information, and reports a case description and case
frank communication between the employer and the contractor themes. It places considerable emphasis on process, context, and dis-
and the positive attitude of both sides (Jamwal and Hariharan covery over outcomes, a specific variable, or confirmation (McLeod
2004). and Laws 2004).
In this case study, the authors used a content analysis method to
identify claims and group them based on the similarity of claims.
Project Risks in the EPC Contract Content analysis is a research approach for describing the evident
Good contracts assign risk to the party who can best manage it. content of communication in an objective, systematic, and quanti-
Within the overall scheme of intended risk allocation, particularly tative manner (Berelson 1971). Mayring (2021) explained that
in respect of design risk, FIDIC contracts aim to be fair and equi- qualitative content analysis can be achieved for recorded commu-
table by allocating risks to the party best able to control, deal with, nication, i.e., transcripts of interviews or discourses, protocols of
and manage them. The FIDIC 1999 edition somewhat reduced the observation, video tapes, or written documents in general.
contractor’s exposure to certain risks. For example, the definition All notice of letters and correspondences between the contractor
of events comprising force majeure was widened to include situa- and the employer were organized in a spreadsheet and qualitative
tions where the contractor can recover time and money for force content analysis was performed on all the correspondences. The
majeure. claims were then analyzed based on the duration of resolution and
Kayastha (2014) reviewed three different cases of hydropower reason for the decisions with reference to FIDIC clauses and con-
projects that were constructed under the FIDIC (1999) Red Book tract documents.
contract in Nepal and highlighted the causes of delay in those proj-
ects, which were site possession, local disruption, unforeseeable
condition, change in scope, and variation. Content Analysis of the Case Study
The concept of implementing a hydropower project under an
EPC and turnkey contract in Nepal has emerged favorably to con- All notices of contracts submitted by the contractor and answers
trol the time, cost, and quality of the project, provide single-point from the employer to contractual communication over the time
responsibility, and mitigate delay (Dhungel 2013). Adhikari (2014), frame of 2014 to 2020 were evaluated. Those letters were sorted in
on the other hand, said that the first EPC hydropower project built in Microsoft Excel, and the phrase “notice of claim” was extracted
Nepal went over the contract’s time limit. from all of the letters provided by the contractor and responded
According to Shen et al. (2017), the main causes of contractor to by the employer’s representative. The study found out 80
claims in international EPC projects are external risks (sociopoliti- “notice of claim” instances submitted by the contractor and ana-
cal risks, economic risks, and natural hazards), employers’ organi- lyzed subsequent correspondence between the employer and the
zational behavior (untimely payment, change orders, and inefficient contractor.
processing), and project definition in the contract (unclear scope of Although there were 80 notices of claim, the claims were gen-
works and unclear technical specification); these causes outrun the erally related to specific categories. Hence, the claims were grouped
contract period. into six categories, such as natural disaster, strike, unforeseen risk,
In summary, several studies have been published regarding the material shortage, payment issue, and COVID-19 pandemic. These
risks associated with standard conditions of EPC contracts. Bakr categories, along with the number of claims, are shown in Fig. 1.
et al. (2008) proposed a structured risk management process to as- The numbers in Fig. 1 represent the frequency of claims under each
sess various risks in the EPC contract environment. Charoenngam category.
and Yeh (1999) identified typical construction risks and described
the comparison between FIDIC and the Taiwanese government
conditions of contracting for hydropower construction projects. Results and Discussion
Wang and Chou (2003) found that a lot of disagreements can be
caused by the lack of related contract clauses, unclear terms, or In this case study, the contractor submitted 57 natural disaster claims,
questions about how risk should be shared. 10 strike claims, six unforeseen risk claims, three material shortage
There are also several studies examining time disputes in con- claims, three payment issue claims, and one COVID-19 pandemic
struction contracts. Iyer et al. (2008) identified the critical clauses claim.
that lead to disputes in construction contracts through extensive case Of those 80 claims, only three were accepted and awarded EoT.
study research. Picha et al. (2015) mentioned that unclear specifi- According to data collected and conversation with the project’s
cations or misunderstanding of a contractor’s liability toward the representative, the contractor has accepted all the rejections from
employer likely lead to disputes. This study examines the contractor the employer. The contractor has not issued any letters for disputes
claims on the 111-MW hydropower project built in Nepal. nor asked for an alternative dispute resolution process.

© ASCE 05022011-3 J. Leg. Aff. Dispute Resolut. Eng. Constr.

J. Leg. Aff. Dispute Resolut. Eng. Constr., 2023, 15(2): 05022011


Natural Disaster (57)
180 days for the storm, and 450 days for flood damage. Regarding
the cost claim, the employer notified the contractor to recover the
cost from the insurance company.
Strike (10)
As shown in Table 2, there were 40 claims related to avalanches
and landslides. After a number of negotiations between the em-
ployer, the employer’s representative, and the contractor, the con-
Unforseen Risk (6) tractor withdrew these claims. The decision was based on GCC
Clause 4.10 (see Table 1 where risk is allocated to the employer
Claims (80) and the contractor), GCC 4.12 (see Table 1 where risk is allocated
Material Shortage (3) to the contractor), GCC 4.15 (see Table 1 where risk is allocated to
the contractor), and GCC 4.23 (Table 1). Similarly, as shown in
Table 2, road blockage (three claims) was rejected and rockfall
and rock avalanche onto access roads (nine claims) were withdrawn
Downloaded from ascelibrary.org by The University of Manchester on 12/14/23. Copyright ASCE. For personal use only; all rights reserved.

Payment Issue (3)


by the contractor.
The project site was in the higher Himalayan region and the
Covid-19 Pandemic earthquake created major cracks that resulted in rock falls and land-
(1) slides during the monsoon period. The storm in 2015 hit hard at the
construction site. Flood damage was severe. The contractor claimed
Fig. 1. Classification of claims. EoT for all those natural calamities. Considering the impact of the
landslide and the duration of the work stopped under the critical
path of the contractor’s approved schedule, the employer accepted
the EoT claim based on GCC Clauses 8.4, 19.2, 19.4, and 20.1 (see
Natural Disaster Claims
Table 1 for risk allocation) as shown in Table 2.
Table 2 summarizes the natural disaster claims, claim time, claim Regarding the cost claim, the turnkey credentials of the FIDIC
outcome, and decision criteria to resolve the claims. Most of the Silver Book Clause 17.6, “Limitation of Liability,” mention that the
claims under this category were landslides, earthquake, and floods. total liability of the contractor to the employer shall not exceed the
For example, one of the major claims of this project was due to a sum stated in the particular conditions or the contract price stated in
devastating 7.8 M W earthquake that hit central Nepal on April 25, the contract agreement. In this case study, the contractor’s claim for
2015. The effects of the earthquake were found throughout the the EoT was approved but not cost because of their PCC 17.6,
country in major construction projects, including labor shortage and “Limitation of Liability,” which stated, “The total liability of the
safety issues after the earthquake in Nepal (Kisi et al. 2020). In the Contractor to the Employer, under or in connection with the
project, the earthquake damaged structural and nonstructural com- Contract shall not exceed 100% of the Contract Price stated in
ponents of the project and two fatalities and 19 injuries occurred. the Contract Agreement.”
The access road to the project was seriously damaged because
of strong tremors on an unstable steep slope. The cofferdam, con-
structed at the headworks area, was damaged by the flood due to the Strike Claims
landslide. The project was shut down for almost 30 days. Due to not fulfilling the local public demands, such as employment
The contractor claims for EoT and cost compensation under from the employer and the contractor, the locals obstructed the
force majeure as shown in Table 2. While under GCC Clause 19.1 project by creating strikes on the project sites. As shown in Table 3,
(FIDIC 1999) force majeure has to be “an exceptional event or cir- there were seven claims related to disruption or suspension of works
cumstance,” it must be beyond the reasonable control of the party. arising out of riot and disorder by local people.
Most other standard form contracts allocate the time risk to the em- All the claims related to strikes in this project were rejected.
ployer but leave the cost impact neutral. It took 3 weeks to resolve, and the decision was based on GCC
Considering those events as force majeure, the employer’s rep- Clauses 4.14, 8.4, and 19.4 (see Table 1 for the risk allocation).
resentative accepted most of the natural disaster claims and awarded As a sample of the correspondence, the employer’s decision letters
the EoT. The contractor received 365 days for the earthquake, stated, “It is reported from our Site engineers that activities of the

Table 2. Natural disaster claims


No of
Description claims Claim type Outcome Decision criteria
Avalanche and landslide blockage on public 40 Time Negotiated and withdrawn FIDIC Clauses 4.10, 4.12, 4.15, 4.23
highway, headworks camp and fuel depot, tunnel
portals of aeration and access tunnels valve chamber
at access roads, powerhouse camp
Road blockage, bridge collapse of main highway 3 Time Rejected FIDIC Clause 4.12
Devastating earthquake of April 25, 2015 1 Time and cost Extension of time granted for FIDIC Clauses 8.4, 19.2, 19.4, 20.1
365 days but no additional cost
Storm on March 23, 2015 1 Time and cost Extension of time granted for FIDIC Clauses 19.2, 19.4, 20.1
180 days but no additional cost
Rockfall and rock avalanche onto access roads, 9 Time Withdrawn FIDIC Clauses 4.10, 4.15, 4.23, 7.6
intake slope
Flood damage to foundation of bridge and 3 Time and cost Extension of time granted for FIDIC Clauses 8.4, 8.5, 19.4, 20.1
cofferdam washed away, 2018 450 days but no additional cost

© ASCE 05022011-4 J. Leg. Aff. Dispute Resolut. Eng. Constr.

J. Leg. Aff. Dispute Resolut. Eng. Constr., 2023, 15(2): 05022011


Table 3. Strike claims
Description No of claims Claim type Outcome Decision criteria
Disruption or suspension of works arising out of riot 7 Time Rejected FIDIC Clauses 4.14, 8.4, 19.4
and disorder by local people at the project district
National strike called by political party 1 Time Rejected Contractor’s daily record and
Road congestion due to riots of local drivers 1 Time Rejected FIDIC Clause 4.14
Strike of truck drivers in Nepal 1 Time Rejected

Contractor were not significantly hampered due to the strike called However, the employer’s representative rejected those claims regard-
by local people, and we appreciate the effort of the Contractor re- ing GCC Clause 4.12, PCC Subclause 7.9, and GCC Clause 4.16.
garding his patience and good coordination with the local people. PCC Subclause 7.9, “Sufficient Stock of Materials,” in the con-
Downloaded from ascelibrary.org by The University of Manchester on 12/14/23. Copyright ASCE. For personal use only; all rights reserved.

The Contractor is requested to maintain the detailed contemporary tract clearly stated, “Due to climatic and geological conditions dur-
records of the event which is preventing the Contractor from com- ing the wet season the Contractor may encounter problems with
plying with his obligation under the Contract.” From this response, access to the Site. Therefore, having regard to Nepal being land-
it is noted that although the strike happened, the contractor’s work locked, the remoteness of the Site, and climatic and geological
continued without affecting the contractor’s schedule. conditions, the Contractor shall at all times plan and arrange for
There were other strikes called by different parties, such as sufficient stock of major materials, which include, but are not lim-
equipment operators, but the employer argued that the strike did ited to, cement, explosives, detonators, reinforcing steel bars, rock
not directly hamper the project activities and thus was rejected. support materials, fuel, to provide uninterrupted operations. Fail-
ure to provide sufficient stock at Site or shortage of materials shall
be in no case the reasons of a claim for extension of time.” This
Unforeseen Risk Claims
PCC contract clause clearly shifted the risk of material shortages to
Unforeseen geological conditions and problems such as cracks at the Contractor and gave the employer an easy way to deny these
the underground powerhouse, a sinkhole at the tailrace, unfavorable contractor’s claims.
rock in the tailrace tunnel, sand layer in headworks, geological col-
lapse in the surge shaft, and cavities occurred on the project site.
Payment Claims
The contractor submitted claims under these circumstances, but the
employer rejected these claims by referring to GCC clauses as The contractor submitted three claims for payment issues related
shown in Table 4. to delays in interim payment, delay in release of advance payment,
For example, the employer denied claims regarding an unfore- insurance for an extended period, and value-added tax (VAT) as
seen sand layer accumulated at headworks based on the responsibil- shown in Table 6.
ities and risks allocated to the contractor under GCC Clauses 4.12, The outcome and decision criteria are summarized in Table 6.
4.13, 4.15, and 7.6 (see Table 1 for risk allocation). GCC Clause Based on GCC Clause 14.3, “Application for Interim Payment,” the
4.12 states that the contractor shall be deemed to have obtained employer responded to the contractor that they did not submit the
all necessary information as to risks, contingencies, and other cir- requirement as stated in the clause, such as using the form approved
cumstances that may influence or affect the work. It also mentions by the employer. The contractor waived the delayed disbursement
that the cost should not be adjusted in these situations. GCC Clause of the interim payment of milestone by stating, “Considering the
4.13 emphasizes the contractor being the party to take responsibility mutual understanding and cooperative support to the other party, the
and risk associated with the rights-of-way and facilities. Contractor would waive the claims on the financial charges and
costs against IPS No.2, and only keep records of delayed time of
38 days.” Similarly, the contractor also waived for delayed disburse-
Material Shortage Claims
ment of advanced payment by stating, “we would waive Claim on
The contractor claimed material shortages due to unavailability of financial charges and costs against Delayed Advanced Payment.”
materials delayed the progress of the work as detailed in Table 5. The employer established a standard structure for payment forms,

Table 4. Unforeseen risk claims


No of Claim
Description claims type Outcome Decision criteria
Cracks treatment at downstream sidewall at powerhouse 1 Time Rejected FIDIC Clauses 4.1, 4.12, 11.4
Additional works arising from sinkhole treatment above tailrace tunnel 1 Time Rejected FIDIC Clauses 4.1, 4.10, 7.6
Unforeseeable geological conditions at tailrace tunnel 1 Time Rejected FIDIC Clauses 4.12, 4.13, 7.6
Unforeseen sand layer accumulated at headworks 1 Time Withdrawn FIDIC Clauses 4.12, 4.13, 4.15, 7.6
Geological collapse above aeration tunnel of surge shaft 1 Time Rejected FIDIC Clause 4.12
Unforeseeable difficulties arising from huge cavities at tailrace tunnel 1 Time Rejected FIDIC Clause 4.12

Table 5. Material shortage


Description No. of claims Claim type Outcome Decision criteria
Shortage of cement in the market 2 Time Withdrawn FIDIC Clause 4.12, PCC Subclause 7.9
Explosive material issue 1 Time Withdrawn FIDIC Clause 4.16

© ASCE 05022011-5 J. Leg. Aff. Dispute Resolut. Eng. Constr.

J. Leg. Aff. Dispute Resolut. Eng. Constr., 2023, 15(2): 05022011


Table 6. Payment issue
Description No. of claims Claim type Outcome Decision criteria
Delayed disbursement of interim payment 1 Time and cost Waived by contractor FIDIC Clause 14.3
Delayed release of advance payment 1 Time and cost Waived by contractor FIDIC Clause 14.2
Compensation arising from damaged structure 1 Time and cost Rejected FIDIC Clause 14.1

with which the contractor did not adhere, resulting in a delay in This scenario alludes to the observation made by Low et al.
approval. The contractor’s claim for delay was due to their own er- (2008) that the practice of holistic risk management in Chinese
ror, which the contractor eventually waived. firms is indeed low and that formal risk management is not in place.
The compensation claim for the damaged structure was rejected, A similar resemblance was made by Liu et al. (2007), who noted
Downloaded from ascelibrary.org by The University of Manchester on 12/14/23. Copyright ASCE. For personal use only; all rights reserved.

stating the claim was a repetition of earthquake damage. Other that the practice and knowledge of risk management in most
claims related to payment were rejected for similar reasons. Chinese construction firms is lower than in their home market and
that holistic risk management is not a priority in their management
strategies.
COVID-19 Pandemic Claim The contract documents can address inherent risks in performing
Although the COVID-19 pandemic affected the project and added EPC and turnkey projects in developing countries. Typically, em-
additional delays, this study does not present any data due to un- ployers seek to transfer all risk to the contractor by modifying PCC
availability of the details. rather than use the fair risk-neutral contract of the FIDIC Silver
Book. Therefore, it is a lesson for future EPC hydropower projects
that the contractor should carefully analyze the differences in the
Lessons Learned clauses, vet the contract carefully, and visualize how those modifi-
cations could impact the cost and time of the project during ex-
A turnkey solution is not as simple as it sounds because of the inevi- ecution. EPC contractors, for example, should review the history of
table complexities of large projects and the decreased contractors’ natural disasters and the project location’s geological and climatic
risk appetite in the global project arena. Contractors prefer projects conditions and account for these risks in the PCCs or contract price.
where they need to carry the least risk and gain the most profit. The following are additional lessons learned from this case
Thus, when negotiating contracts, they seek exclusions from signifi- study:
cant caps on liability. Employers also look for ways to put all the 1. There is a risk of natural disasters and weather interruptions to
risks on the contractors and simultaneously lower the project cost. the work that affects the time and cost of the project. In this case
EPC and turnkey projects are difficult types of contracts from study, the contractor filed the largest number of claims related
the contractor’s perspective because most of the risk is transferred to force majeure. For example, Table 2 shows that the contrac-
to the contractor, as seen in this case study. For example, the con- tor claimed additional time and cost due to disruption from natu-
tractor’s claims, such as strike (Table 3), unforeseen risk (Table 4), ral disasters. The contractor did receive EoT but no additional
and material shortage (Table 5) were rejected, or the contractor had compensation. As shown in Table 2, the EoT was granted for
to withdraw their claims because of the way the contract mentioned 365 days (1 year) regarding the damages due to the earthquake,
the allocation of risk. but the cost was not granted based on the contract’s PCC Clause
After reviewing the literature and the FIDIC Silver Book GCC 17.6, “Limitation of Liability:” The total liability of the Contrac-
clauses of the EPC or turnkey contract, it is clear that the GCC tor to the Employer, under or in connection with the Contract
clauses give a balance of risk to both parties, such as the contractor shall not exceed 100% of the Contract Price stated in the Con-
and the employer, while also guiding the employer on how to alter tract Agreement.” Because the definition of events comprising
the PCC as needed. In this case study, the employer modified PCC force majeure was broadened in FIDIC (1999), where the con-
clauses as per their comfort and transferred most of the risks to the tractor can recover time and money for force majeure, the con-
contractor, including transferring risk to the contractor based on tractor could perform risk analysis to clarify and negotiate with
geological and climate history. the employer for the modification of clauses in the PCC. As
The case study analysis shows that the contractor lost their a lesson learned, the contract document should clearly define
claims due to poor risk analysis, poor evaluation of the GCC of the unusually severe weather and define which party is responsible
FIDIC Silver Book, and project-specific PCC. For example, the out- for that risk because adverse weather conditions may not be se-
comes in Tables 2–6 show that most of the rejected claims reflect vere enough to qualify as force majeure events but may be se-
this poor risk management and the contractor’s poor evaluation of vere enough to stop the work.
GCC and PCC. Most natural disaster claims, such as earthquakes, 2. Strike and local disruption risks are likely to occur in developing
were granted time extensions only under force majeure. However, countries. This situation is challenging and risky in the EPC
the employer rejected many claims under other groups based on the project where a delay is critical to the contractor. In this case
GCC and PCC clauses. As explained previously, the employer trans- study, the contractor faced many challenges due to strikes and
ferred risk to the contractor through PCC. However, the contractor disruption by local people. In this type of situation, addressing
did not emphasize that PCC during bidding or interpreted it differ- the issues proactively by bringing them to the table for resolu-
ently, which led to the rejection of claims. This rejection shows that tion earlier is a better approach, but most important is docu-
the contractor needed to perform proper risk analysis and assess- menting the discussion and resolution with the local people. As
ment. For example, the contractor could perform a risk analysis of shown in Table 3, the contractor claimed for disruption or sus-
the layout and surface geology and propose a baseline report to pension of works caused by riot and disorder by local people
negotiate with the employer. This baseline report could be beneficial but could not provide supportive evidence. According to GCC
for the remeasurement and adjustment of contractual construction Clause 4.14, avoidance of interference, the contractor shall in-
and time. demnify and hold the employer harmless for all damages, losses,

© ASCE 05022011-6 J. Leg. Aff. Dispute Resolut. Eng. Constr.

J. Leg. Aff. Dispute Resolut. Eng. Constr., 2023, 15(2): 05022011


and expenses incurred as a result of any such unnecessary or management (Bakr et al. 2008; Liu et al. 2007), absence of related
improper interference. The contractor could have taken advan- contract clauses and fairness of risk allocation (Wang and Chou
tage of the clause modification in PCC where the contractor 2003), and misunderstanding of the contractor’s liability toward the
could ask for provision or consideration if they could prove that client (Picha et al. 2015) were found in this project as well. There-
those events prevented the contractor from complying with their fore, the findings and lessons learned of this case study could help
obligation under the contract. employers and EPC contractors, especially Chinese contractors, who
3. The unforeseeable risk may significantly impact the project cost want to conduct their international hydropower project in Nepal.
and schedule. Both disputing parties experienced impacts due to Although the study findings are based on the case study in Nepal,
the significant EoT and additional overhead costs. For example, the lessons learned can be helpful to international contractors who
the employer granted 450 days to address the damage caused by want to do EPC hydropower projects in countries that are prone to
the flood and 365 days to deal with the earthquake disruption natural hazards.
(Table 2). These events were not only unforeseen but also sig-
nificant events that delayed the project almost twice the original
Downloaded from ascelibrary.org by The University of Manchester on 12/14/23. Copyright ASCE. For personal use only; all rights reserved.

project duration. Similarly, the project consisted of different un- Data Availability Statement
derground structures such as tunnels, underground powerhouses,
and foundations of the weir and under the sluice. Because of the All data used during the study are available from the corresponding
multiple subsurface components, there was always the risk of author by request.
uncertainty. As a lesson learned, the FIDIC GCCs such as Clause
4.11, “Sufficiency of the Contract Price,” and Clause 4.12,
“Unforeseeable Difficulties,” that put risks on contractors could Acknowledgments
be modified using PCCs so the contract could be completed
smoothly with minimum claims. The contractor could perform The authors acknowledge the assistance of the project’s employees
risk analysis and negotiate with the employer in GCC Clause and express special thanks to the contract manager for providing
4.14 to benefit both parties. valuable input to this research.

Conclusions References
This case study discussed the claims and relevant FIDIC clauses
in one of Nepal’s most significant hydropower projects executed Works Cited
under the EPC or turnkey contract with the Chinese contractor. Adhikari, P. 2014. “Risk and responsibilities of EPC contract.” Accessed
In this study, literature review, review of claims, and letter corre- July 25, 2022. https://www.nea.org.np/admin/assets/uploads/supportive
spondence between the contractor and the employer showed several _docs/Vidyut-2070-Falgun-24.pdf.
recurring claims in this EPC project. These claims were categorized Bakr, A. F., K. E. Hagla, and A. N. Rawash. 2008. “Heuristic approach
into six groups: natural disaster, strike, unforeseen risk, material for risk assessment modeling: EPCCM application (engineer procure
shortage, payment, and COVID-19 pandemic claims. The contrac- construct contract management).” Alexandria Eng. J. 51 (4): 305–323.
tor primarily sought out EoT and overhead costs. As a result, the https://doi.org/10.1016/j.aej.2012.09.001.
employer approved most claims under natural disasters such as Berelson, B. R. 1971. Content analysis in communication research.
earthquakes for time extension only under force majeure. However, New York: Hafner.
the employer rejected most of the claims under the other five groups Charoenngam, C., and C. Y. Yeh. 1999. “Contractual risk and liability sharing
in hydropower construction.” Int. J. Project. Manage. 17 (1): 29–37.
based on the GCC and PCC clauses. Moreover, the contractor
https://doi.org/10.1016/S0263-7863(97)00064-1.
agreed with the employer’s decisions and has not disputed them
Chu, S. L. 1979. Tunnel engineering. 3rd ed. Taiwan: Technical Press.
further. As mentioned in “Lessons Learned,” the literature also Creswell, J. W. 2014. Research design: Qualitative, quantitative and mixed
supports a lack of risk management among Chinese contractors methods approaches. 4th ed. Thousand Oaks, CA: SAGE.
(Low et al. 2008; Liu et al. 2007). Dhungel, S. K. 2013. “Relevance of EPC contracts in hydropower project.”
Although the project duration in this case study was 3 years and Accessed July 25, 2022. https://www.nea.org.np/admin/assets/uploads
6 months, started in January 2014, the project went through signifi- /supportive_docs/Vidyut%20Halfyearly%20Year%2024%20Issue1%20
cant delay due to the contractor’s EoT and overhead cost claims. new%20.pdf.
The project is scheduled to open in January 2023, about 5 years DLA Piper. 2011. “EPC contracts in the power sector, Asia Pacific proj-
late. Working on the same project for that long, utilizing all their ects update.” Accessed July 13, 2022. https://www.slideshare.net
skilled and unskilled workforce, was not beneficial to the reputed /raghunathanjanarthanan/epc-contractsinthepowersector.
international contractor. The delay was not beneficial to the em- Dulal, T. P., and H. R. Shrestha. 2021. Applying FIDIC contracts in Nepal
ployer either. This project was meant to serve the public by provid- in FIDIC contracts in Asia Pacific: A practical guide to application.
ing electricity, but the delay in its completion has impacted the Edited by D. Charrett, 379–410. London: Informa Law from Routledge.
targeted people. https://doi.org/10.4324/9781003200901.
FIDIC (International Federation of Consulting Engineers). 1999. Condi-
This case study described project delay risks that occurred to
tions of contract for EPC/turnkey projects. 1st ed. Geneva: FIDIC.
the contractor, who was the favored bidder for an EPC and turnkey
Guo, Q., Z. P. Xu, G. F. Zhang, and T. T. Tu. 2010. “Comparative analysis
hydropower project in Nepal. Based on the analyses, the authors between the EPC contract mode and the traditional mode based on the
found that there are primarily natural disasters and strike claims transaction cost theory.” In Proc., IEEE 17th Int. Conf. on Industrial
in the international EPC hydropower project in Nepal. The findings Engineering and Engineering Management, 191–195. New York: IEEE.
also show that the contractor (Chinese) lacked proper risk manage- Hale, D. R., P. P. Shrestha, G. E. Gibson Jr., and G. C. Migliaccio. 2009.
ment and misunderstood the contract clauses. “Empirical comparison of design/build and design/bid/build project de-
The findings from the project aligned with some of the previous livery methods.” J. Constr. Eng. Manage. 135 (Jul): 579–587. https://
study findings that led to claims. For instance, lack of proper risk doi.org/10.1061/(ASCE)CO.1943-7862.0000017.

© ASCE 05022011-7 J. Leg. Aff. Dispute Resolut. Eng. Constr.

J. Leg. Aff. Dispute Resolut. Eng. Constr., 2023, 15(2): 05022011


Hosie, J. 2007. Turnkey contracting under the FIDIC Silver Book: What do Prajapati, R. N. 2015. “Delineation of run of river hydropower potential
employers want? What do they get? London: International Federation of of Karnali basin-Nepal using GIS and HEC-HMS.” Eur. J. Adv. Eng.
Consulting Engineers. Technol. 2 (1): 50–54.
Iyer, K. C., N. B. Chaphalkar, and G. A. Joshi. 2008. “Understanding time Pun, S. 2014. “The 60 versus 90 MW battle over Upper Trishuli-3A The
delay disputes in construction contracts.” Int. J. Project Manage. 26 (2): victors and the vanquished classic case of throwing the baby out with the
174–184. https://doi.org/10.1016/j.ijproman.2007.05.002. bathwater!” Hydro Nepal: J. Water Energy Environ. 13 (Aug): 8–15.
Jamwal, S. S., and K. Hariharan. 2004. “Effective management of turnkey https://doi.org/10.3126/hn.v13i0.11381.
execution of Chamera Hydroelectric Project, stage-III—Contractual RGHPCL (Rasuwagadhi Hydropower Company Limited). 2022. “Unaudited
aspects.” Water Energy Int. 61 (1): 48–54. financial statement FY 2022/23.” Accessed December 12, 2022. https://
Kayastha, G. 2014. “Importance of contract administration for timely rghpcl.com.np/images/supportive_docs/RGHPCL_UnauditedFinancial
construction of hydropower projects without disputes.” Hydro Nepal: Statement_079_80_Q1.jpg.
J. Water Energy Environ. 14 (Oct): 49–51. https://doi.org/10.3126/hn Schramm, C., A. Meißner, and G. Weidinger. 2010. “Contracting strategies
.v14i0.11265. in the oil and gas industry.” Pipeline Technol. 2010: 33–36.
Kisi, K. P., K. J. Shrestha, and R. Kayastha. 2020. “Labor shortage and Shen, W., W. Tang, W. Yu, C. F. Duffield, F. K. P. Hui, Y. Wei, and J. Fang.
Downloaded from ascelibrary.org by The University of Manchester on 12/14/23. Copyright ASCE. For personal use only; all rights reserved.

safety issues in postearthquake building construction: Case study.” 2017. “Causes of contractors’ claims in international engineering-
J. Leg. Aff. Dispute Resolut. Eng. Constr. 12 (3): 05020011. https://doi procurement-construction projects.” J. Civ. Eng. Manage. 23 (6): 727–739.
https://doi.org/10.3846/13923730.2017.1281839.
.org/10.1061/(ASCE)LA.1943-4170.0000386.
Shnookal, T., and D. Charrett. 2010. “Standard form contracting; the role
Liu, J., B. Li, B. Lin, and V. Nguyen. 2007. “Key issues and challenges of
for FIDIC contracts domestically and internationally.” In Vol. 30 of
risk management and insurance in China’s construction industry: An
Proc., Society of Construction Law Conf. Sydney, NSW, Australia:
empirical study.” Ind. Manage. Data Syst. 107 (3): 382–396. https://doi
Society of Construction Law Australia.
.org/10.1108/02635570710734280.
Simon, M. 1979. Construction contracts and claims. New York:
Low, S. P., J. Y. Liu, and S. Q. He. 2008. “Management of external risks: McGraw-Hill.
Case study of a Chinese construction firm at infancy stage in Singapore.” Singh, S. 2000. “Dispute in EPC contracts.” Accessed July 28, 2022.
Int. J. Construct. Manage. 8 (2): 1–15. https://doi.org/10.1080/15623599 https://www.legalserviceindia.com/legal/article-3638-dispute-in-epc
.2008.10773112. -contracts.html.
Mayring, P. 2021. Qualitative content analysis a step-by-step guide. Thousand Thweatt, W. T., and R. J. Long. 2017. EPC contract risk analysis associ-
Oaks, CA: SAGE. ated with onshore projects in developing countries. Littleton, CO: Long
McLeod, R., and K. Laws. 2004. “Case study and grounded theory: Sharing International.
some alternative qualitative research methodologies with systems pro- Wang, M.-T., and H.-Y. Chou. 2003. “Risk allocation and risk handling of
fessionals.” In Vol. 78 of Proc., 22nd Int. Conf. of the Systems Dynamics highway projects in Taiwan.” J. Manage. Eng. 19 (2): 60–68. https://doi
Society, 1–25. Oxford, UK: Keble College. .org/10.1061/(ASCE)0742-597X(2003)19:2(60).
Oztas, A., and O. Okmen. 2004. “Risk analysis in fixed-price design–build Wang, S., and X. Liu. 2021. “Development of EPC model in Chinese
construction projects.” Build. Environ. 39 (2): 229–237. https://doi.org public projects: Evolutionary game among stakeholders.” J. Asian Archit.
/10.1016/j.buildenv.2003.08.018. Build. Eng. 21 (5): 2095–2113. https://doi.org/10.1080/13467581.2021
Picha, J., A. Tomek, and H. Löwitt. 2015. “Application of EPC contracts .1971681.
in international power projects.” Procedia Eng. 123 (Aug): 397–404. Yin, R. K. 2018. Case study research and applications: Design and methods.
https://doi.org/10.1016/j.proeng.2015.10.061. 6th ed. Thousand Oaks, CA: SAGE.

© ASCE 05022011-8 J. Leg. Aff. Dispute Resolut. Eng. Constr.

J. Leg. Aff. Dispute Resolut. Eng. Constr., 2023, 15(2): 05022011

You might also like