MASONRY WORK

REPORT

Project : Report No. :


DWG No. : Date :
Location : Subcontractor :

Result
No Check List
Accept Reject N/A
1 Material (Grade, Size, Crack etc.)
2 Preparation (Surface Condition, Elevation, Coordination etc.)
3 Placing
4 Embedded and Concealed Item
5 Reinforcement Installation (Anchor, Rebar, Tie etc.)
6 Joint and Filling
7 Openings
8 Insulation
9 Straightness and Flatness
10 Curing
11 Others
Note:

Inspection Result: □ Accept □ Reject


Inspected by Subcontractor Contractor Company

Name

Signature

Date
CEILING WORK
REPORT

Project : Report No. :


DWG No. : Date :
Location : Subcontractor :

Result
No Check List
Accept Reject N/A
1 Material (Damage, Condition by Spec.)
2 Surface Preparation (Free from foreign material, Clean etc.)
3 Support and Frame Installation (Size, Alignment etc.)
4 Panel Installation
5 Leveling
6 Finishing (Fixing, Fitting)
7 Opening/ Trap
8 Others
Note:

Inspection Result: □ Accept □ Reject


Inspected by Subcontractor Contractor Company

Name

Signature

Date
PAINTING WORK
REPORT

Project : Report No. :


DWG No. : Date :
Location : Subcontractor :

Result
No Check List
Accept Reject N/A
1 Material (Condition by Instruction)
2 Temperature / Humidity ( / )
3 Surface Preparation
4 Surface Wet Condition
5 Visual Inspection
6 Dry Film Thickness (If required)
7 Wet Film Thickness (If required)
8 Final Check (Surface Condition etc.)
9 Others
Note:

Inspection Result: □ Accept □ Reject