EXHIBIT 2

Vendor Data Requirement Specification (VDRS)

[ON COMPANY LETTERHEAD]

Cover Letter No. ______________________ Date: XXXXXXXXX

FROM: TO: DCS Controller


Created by: Company/Organization:

Position: Address:

Phone: Name:

Position:

Phone:

Incoming Document No./ not numbered

No. Document number Rev. Document description Status Type

PO number–<VDDR ID>–
1 0 Wiring diagrams PDF
<Sequence number.>
PO Number (Order
Number)–<VDDR ID
(Vendor Drawings and Data
2 0 General layout drawings. PDF
Requirements Identification
Document)>–<Order
Number.>
PO Number (Order
Number)–<VDDR ID
(Vendor Drawings and Data
3 0 etc. PDF
Requirements Identification
Document)>–<Order
Number.>

Status: ISSUED FOR INFORMATION

Status of attached documents

AFC/IFC-Approved/Issued for Construction IFD – Issued for Design ENQ – Issued for Request
IFR – Issued for Review IFAd – Issued for Adaptation IFI – Issued for Information
IFR – Issued for Approval CERT – Certified in the final version CAN – Cancelled
IFS – Issued for Use

Handed over by: Signature: Date:

NOTE:
Please note that in accordance with the agreed Purchase Order, all supplier data (drawings, diagrams, etc.) for PO XXXXXX must be submitted to
the Document Control Department along with the submission form (a sample template is shown above). All submitted supplier data documents must
contain the customer number in accordance with the instructions below.
Vendor Data Requirement Specification (VDRS)

Overview/review Certified Comments


Name Q-ty
Description Q-ty
*Deadline (See the **Deadline
(See the note)
note)
PLANNING
1.01 Document designation and list 1E
1.02 Delivery schedule in the form of a Gantt chart 1E
1.03 Mobilization and Construction Gantt Chart 1E
1.04 Company Quality Assurance Plan 1E
1.05 Work Plans and Project Procedures 1E
1.06 Project Security Plan 1E
1.07 Mobilization Plan – Personnel, Equipment and 1E
Materials
1.08 Vaccination and medical plan – staff 1E
1.09 Monthly Progress reports 1E
1.10 Weekly work progress report 1E
COMMERCIAL INFORMATION
2.01 Company registration 1E
2.02 Insurance data 1E
2.03 Bank guarantee 1E
2.04 Bank details (for non-cash payments) 1E
2.05 Copies of orders without sub-supplier prices 1E
2.06 Tax Resident Confirmation Certificate 1E
2.07 Commercial offer (list of materials) in Excel format 1E
EQUIPMENT DATA
3.01 Descriptive literature / catalog data 1E English and Russian
3.02 Technical specifications and equipment data sheets 1E English and Russian
3.03 Operating characteristic / Operating characteristic 1E English and Russian
curve
3.04 Surface treatment data sheet 1E English and Russian
PRODUCTION PROCESS INFORMATION
4.01 Metallurgical testing program 1E English and Russian
4.02 Process regulations development criteria 1E English and Russian
4.03 Mass balance 1E English and Russian
4.04 Basis for design. 1E English and Russian
4.05 Description of production process 1E English and Russian
4.06 Description of management principles 1E English and Russian
4.07 First fill information 1E English and Russian
DRAWINGS
5.01 General layout drawings 1E English and Russian
5.02 Detailed engineering drawings 1E English and Russian
5.03 Foundation Load diagrams 1E English and Russian
5.04 Location of the foundation slab and extra strong 1E English and Russian
fastening bolts
5.05 Marking plans / assembly drawings 1E English and Russian
5.06 Detailed drawings 1E English and Russian
5.07 Pipeline isometric plans 1E English and Russian
5.08 Process charts 1E English and Russian
5.09 Process flow and tools charts with equipment List 1E English and Russian
5.10 Diagrams of pneumatic and/or hydraulic systems 1E English and Russian
5.11 Lubrication diagrams 1E English and Russian
5.12 Layout drawings 1E English and Russian
5.13 Installation drawings 1E English and Russian
5.14 List of bolts 1E English and Russian
5.15 3D Model 1E English and Russian
CALCULATIONS AND ANALYSIS
6.01 Design calculations – Structural elements 1E English and Russian
6.02 Design calculations – Production process 1E English and Russian
6.03 Design calculations – Heat output 1E English and Russian
6.04 Design calculations – Mechanical part 1E English and Russian
6.05 Design calculations – Electrical part 1E English and Russian
6.06 Design calculations – Civil engineering part 1E English and Russian
6.07 Finite Element Analysis (FEA) 1E English and Russian
6.08 Liquid Film Analysis 1E English and Russian
6.09 Seismicity analysis 1E English and Russian
6.10 System Analysis 1E English and Russian
6.11 Mill loading trajectory analysis 1E English and Russian
6.12 Power factor study 1E English and Russian
6.13 Error calculation 1E English and Russian
6.14 Ground loop resistance calculations 1E English and Russian
6.15 Grounding calculations 1E English and Russian
6.16 Lighting analysis 1E English and Russian
6.17 Acoustic analysis 1E English and Russian
6.18 Corrosion analysis 1E English and Russian
6.19 Design calculations – pipeline 1E English and Russian
ELECTRICAL AND CONTROL EQUIPMENT
7.01 List of electric motors 1E English and Russian
7.02 List of instrumentation 1E English and Russian
7.03 Instrumentation calibration certificates 1E English and Russian
7.04 Operating characteristics of electric motors 1E English and Russian
7.05 Single-line wiring diagrams – high voltage 1E English and Russian
7.06 Single-line wiring diagrams – low voltage 1E English and Russian
7.07 electrical equipment and instrumentation layout 1E English and Russian
drawings
7.08 Key wiring diagrams 1E English and Russian
7.09 Electrical termination diagrams 1E English and Russian
7.10 Cable diagrams 1E English and Russian
7.11 PLC logic diagrams and flow charts 1E English and Russian
7.12 Instrumentation circuit diagrams 1E English and Russian
7.13 Logic diagrams 1E English and Russian
7.14 Input/output diagram 1E English and Russian
7.15 PLC program and related drawings 1E English and Russian
7.16 Supervisory Control and Data Acquisition 1E English and Russian
software and licenses (SCADA)
7.17 General control panel layout drawing 1E English and Russian

7.18 Wiring diagrams 1E English and Russian


7.19 Fire system flow charts 1E English and Russian
7.20 Security system flow charts 1E English and Russian
7.21 Communication system flow charts 1E English and Russian
7.22 Data system flow charts 1E English and Russian
7.23 Functional description / specification of the 1E English and Russian
control system
QUALITY ASSURANCE
8.01 Quality Control Plan 1E English and Russian
8.02 Inspection and Testing Plan 1E English and Russian
8.03 Concrete mix design 1E English and Russian
8.04 Manufacturer Data Quality Report (MDR) 1E English and Russian
8.05 Welding Procedures and Welding Diagram 1E English and Russian
8.06 Welder attestation 1E English and Russian
8.07 Material certificates 1E English and Russian
8.08 Production procedures 1E English and Russian
8.09 Welded joint test certificates 1E English and Russian
8.10 Shop Test Procedures 1E English and Russian
8.11 Criteria for transfer and acceptance using non- 1E English and Russian
destructive testing method
8.12 Scope of factory assembly and testing 1E English and Russian
8.13 Operating Test Procedures 1E English and Russian
8.14 Surface protection procedures 1E English and Russian
8.15 Lifting equipment certification 1E English and Russian
8.16 Permitting documentation of state authorities 1E English and Russian
8.17 Approvals/certificates of conformity 1E English and Russian
8.18 Post weld heat treatment protocols 1E English and Russian
8.19 Qualifications and certificates of the operator 1E English and Russian
conducting non-destructive testing
8.20 Protocols and records of radiographic non- 1E English and Russian
destructive tests
8.21 Hydraulic testing procedures 1E English and Russian
8.22 Hydraulic testing procedures 1E English and Russian
8.23 Manufacturer Acceptance Test Procedure 1E English and Russian
8.24 Manufacturer Acceptance Test Report 1E English and Russian
8.25 Planned Test Certificates 1E English and Russian
8.26 Model Test Certificates 1E English and Russian
8.27 Index for Manufacturer Data Quality Report 1E English and Russian
(MDR)
FACILITY-RELATED REPORTING
9.01 Weekly personnel (workforce) report, incl. statistics 1E English and Russian
9.02 Weekly security reports including statistics 1E English and Russian
9.03 Construction progress/quality report, including 1E English and Russian
construction schedule update
9.04 Construction Inspection and Progress Verification 1E English and Russian
Plans
9.05 Structure tests and non-destructive test reports 1E English and Russian
9.06 Soil Compaction Test Reports 1E English and Russian
9.07 Concrete Sample Test Report 1E English and Russian
9.08 Paint Thickness Test Reports 1E English and Russian
9.09 Hydraulic testing procedures 1E English and Russian
9.10 Non-conformance reports 1E English and Russian
9.11 Concrete mixing procedure 1E English and Russian
9.12 Concrete Pouring Sequence – marked general 1E English and Russian
layout drawings
9.13 Job safety analysis – JSA 1E English and Russian
9.14 Equipment safety data sheets 1E English and Russian
9.15 Pre-start inspection / testing procedures 1E English and Russian
9.16 Permitting documentation of state authorities 1E English and Russian
9.17 Material selection 1E English and Russian
9.18 Commissioning Certificates / testing procedures 1E English and Russian
SHIPMENT
10.01 Requirements and volumes of deliveries and cargoes 1E English and Russian

10.02 Cargo and container loading schemes 1E English and Russian


10.03 Notice Before Sending Final Dispatch Authorization 1E English and Russian

10.04 Inspection and shipment permit 1E English and Russian


10.05 Packing list, including data on type of packaging and 1E English and Russian
quantity
10.06 Shipment procedure 1E English and Russian
10.07 Cargo weight and dimensions 1E English and Russian
10.08 Goods receiving records 1E English and Russian
MAINTENANCE
11.01 Installation, operation and maintenance manuals 1E English and Russian

11.02 Installation drawings and weight 1E English and Russian


11.03 Detailed spare part list 1E English and Russian
11.04 Recommended spare part list 1E English and Russian
11.05 Lubrication Schedule 1E English and Russian
11.06 Material Safety Data Sheets (MSDS) 1E English and Russian
11.07 Special tools list 1E English and Russian
11.08 Installation, Operation & Maintenance Manual 1E English and Russian
Index

* = AFTER OWNER CONFIRMATION IS RECEIVED ** = WEEKS AFTER RETURN OF AGREED DRAWINGS AA = UNDER
(VIA LETTER OF GUARANTEE OR PURCHASE APPROPRIATE
REQUISITION) CONDITIONS
NOTE:
1. See page 8 – «Instructions» for instructions on completing this form: Supplier's obligation form to provide data and drawings
2. Issued at the time of shipment
3. Schedule including design, procurement, manufacturing, inspection, testing, painting, pre-shipment and transportation
4. Certificates and inspection reports must be submitted within five days of completion of testing.
5. The codes indicated in the first column are requirements for technical documentation
6. QTY: Type and Quantity H = Printed copy E = Electronic version «U» = Urgent
7.
Examples for specifying timing:

Agreement (A) Weeks (W)


+/- Q-ty
Dispatch (D) Days (D)

Example: A+5W (5 weeks after signing the contract, purchase order);


D-2W (2 weeks before shipping);
Clarification on Vendor Drawings and Data Requirements

The purpose of this clarification is to assist the Supplier in the process of preparing and collecting the required technical information package. At the same
time, explanations are given on the information that must be included in each individual document/drawing.
GOVERNING LANGUAGE - Model number and size
All information from the Supplier shall be provided in Russian and - Main overall dimensions and clearances, including gland plate
English, unless otherwise specified in the above VDDR table. location
- Manufacturer's material code
MANUFACTURING CALENDAR SCHEDULE - Classification code for mechanical seals
The gantt or equivalent chart includes: - Strengthening structures under flexible elements and additional
- Engineering part packaging
- Order placement and delivery dates for major castings and - Spare parts list indicating manufacturing material
minor equipment - Operating parameters including mechanical seal chamber
- Testing program pressure
- Preparatory dispatch work and shipment date - Sealing connections for flushing, pumping, cooling and
venting air
DIMENSIONAL DRAWING Quantity for flushing seals, injection, cooling
- Overall dimensions including shaft center and height. Plugged connections must be defined
- Location and dimensions of holes for foundation bolts Cross section of the sealing plate showing flushing, cooling, etc.
- Grouting and layout data - Direction of rotation
- Drive brand, type, power rating and speed - Spring winding direction
- Brand, type and size of coupling connections - Installation Instructions
- Brand, type and size of mechanical seals
- Classification code for mechanical seals PIPING CONJUNCTION DATA
- Seal manufacturer's material code Drawings of the mechanical seal flush, cooling water, steam
- Pipeline Seal Flushing Schemes heating, and rapid cooling piping must be provided, indicating the
- Pump and drive rotation direction following:
- Drain restrictor diaphragm - Applied plan number or letter
- Equipment unit weight: weight of each major component, - List of all connections of the Customer, including information
bare/gross weight, if item weight is exceeded on dimensions, design parameters, flange surfaces and
500 kg or more for foreign use and rigging points finishes.
- Foundation plate mounting lugs, cross elements, grouting and - Flow direction
deaeration holes, jack screws, grounding lugs - Valves, level gauges, outlets, breathers and other fittings
- Place required for maintenance and dismantling - Pipeline supports
- All piping and components - Materials of manufacture, indicating the brand, type, size and
- Measured layout of all connection diagrams of the Customer materials of all external purchased parts, piping and their list.
- List of all connections of the Customer, including information This information can be included in the outline drawing.
on dimensions, design parameters, flange surfaces and
finishes. SPARE PART INFORMATION
- Principal and auxiliary junction boxes with input. Additional list of spare parts is provided for spares not included in
- Acceptable forces and moments for the inlet and outlet pipes the original quotation. It should include recommended parts,
cross-sectional or assembly drawings, part numbers, materials,
LIST OF DRAWINGS OF CROSS SECTIONS AND SPARE prices, and delivery times. Numbers must be assigned to each part,
PARTS in order to determine their interchangeability. Standard finished
- Spare parts list should include diagrams, availability in stock (purchased) products are indicated with the original manufacturer's
or numbers of factory drawings and construction material. numbers.

Piping and Instrumentation Diagram WELDING INSTRUCTIONS


The piping and instrumentation drawing should show the layout of Technical specifications and qualification requirements for
equipment with all process components, including piping and welding work are provided for each welding seam or for a group of
instrumentation, that make up the described process cycle. welding seams for parts containing process fluids, including
pipelines.
The following must be specified as a mandatory minimum:
- System configurations and connections DESIGN DATA ON THE NAMEPLATE
- Piping dimensions, insulation technology and flow direction The nameplate must contain the following information:
arrows - Buyer assigned item number
- Valves; control valves with dimensions - Seller assigned size and model number
- Protective elements; safety fittings, emergency shutdown - Serial number of the pump
devices with settings - Performance (cubic meters per hour)
- Engineering connection to utility networks - Pump discharge head, m
- Monitoring and metering instrument with identification - Pressure of hydrostatic test of pump casing, bar
numbers - Speed and umber of rotations per minute
- Equipment design characteristics of in a separate unit, i.e., - Bearing identification numbers assigned by the manufacturer
identification number, description, design pressure/temperature
and rated load capacity

COMPLETED SPECIFICATIONS/DATA SHEETS PAINTING/PROTECTION/INSULATION DATA


- Completed pump data sheet Including:
- Completed drive data sheet - Instructions for surface cleaning and sandblasting
- Completed noise load data sheet - Materials used along with names of paint manufacturers
- Completed weight management data sheet, if applicable - Number of top coats, color and thickness of each dry coat
Protective coating:
MECHANICAL SEAL DRAWING - Hot dip zinc galvanizing of all main parts, bolts, nuts, etc.
Including: - Data on zinc galvanizing of all main parts, bolts, nuts, etc.
- Data on plastic coating of all main parts, bolts, nuts, etc. - Including parameters such as: pressure drop, efficiency,
Insulation: required suction lift of the pump, braking horsepower for
- Instructions for specified insulation must be provided. If there all operating modes indicated in the data sheets
are no confirmed installed insulation instructions, then
recommended insulation instructions should be provided. E Vibration Data
- Vibration data
GENERAL INFORMATION ON LUBRICANTS
A list must be submitted with the following information (minimum F As-built documentation
requirement): - As-built documentation
- Types, brand name, specifications, fisrt fill data, lubrication - As-built gaps
intervals and quantity required per lot/unit of equipment to - Rotor balancing data for multistage pumps
keep the entire unit running. - Material certificates
The above must also be submitted if the lubricants are specified in - Hydrostatic test certificates
the purchase order/contract. - Non-destructive test results

CERTIFICATES G VENDOR DRAWING AND DATA REQUIREMENTS


- Material certificates shall be provided for all pressure - Officially approved dimension drawing and connection list
components, impellers and forged shaft elements - List of drawings of cross sections and spare parts
- Explosion-proof certificates shall be provided for all electrical - Shaft sealing drawing
components, including instrumentation, that are located in - Coupling data
hazardous areas - Piping drawings
A Compliance Statement is provided for prohibited materials (e.g. - Drawings and data for lubrication system components
asbestos) - Schemes of electrical equipment and instrumentation, list of
spare parts
CURVES/TEST DATA - Drawing of the general layout of electrical equipment and
Including: instrumentation with a list of connections
- Hydrostatic test reports, together with hydrotest certificates for
all pressure components not listed in the manufacturer’s H Recommendations on spare parts
reporting data, e.g. pump casings, cooling water jackets or - From the Supplier
coils, etc.
- Final performance test reports. The Supplier shall maintain a EXAMINATIONS, INSPECTIONS AND TESTS
detailed log of all final tests All run-in tests and mechanical To be submitted for consideration and mutual confirmation.
checks shall be performed by the Supplier prior to the Buyer's
inspections. Walk Down Procedure
- Performance dimensions and data, including wear rings and Minimum Requirements:
bushing clearances - All tests shall be carried out during the manufacturing process
- Heat treatment of impellers and shafts, if heat treatment is not and after manufacturing.
indicated in the material certificates - Non-destructive inspection procedure
- Certification and suspension of work for inspections by the
INSTALLATION, OPERATION AND MAINTENANCE Buyer and/or the supervisory authority
MANUAL
Manuals for machinery, installations, and equipment shall be Testing Procedures
translated into Chinese within the scope of the Supplier's Work The list of recommended testing procedures should be submitted
for consideration and confirmation:
The minimum list of sections of the manual should include:
A Installation FINAL AND AS-BUILT DRAWINGS/DOCUMENTATION
- Storing Final and as-built drawings/documentation shall be provided as
- Foundation both the hard copy and in the electronic form (in the PDF format).
- Weight lifting and rigging works The structure of electronic documents must fully match the
- Calibration structure of printed documents. As-built are drawings and
- Alignment documentation with amendments, reflecting the difference
- Recommendations for piping between the actual and estimated parameters, established during
- Disassembling gaps the transfer of the installation after field testing. Serve to prove
compliance with the requirements set out in the Purchase Order.
B Operation
- Commissioning, including pre-commissioning tests and
inspections
- Rules for standard operation
- Recommendations on lubrication
- Troubleshooting
C Dismantling and Mounting
- Rotor in the pump housing
- Slide bearings
- Footstep bearings
- Mechanical sealing
- Thrust rings (if equipped)

D Performance Curves
INSTRUCTIONS ON THE «VENDOR DRAWINGS AND DATA REQUIREMENTS» FORM
1 USER GUIDES FOR THE VENDOR DRAWINGS AND DATA REQUIREMENTS

1.1 The potential contractor shall submit a list of drawings/documents. The list shall show the numbers of drawings/documents with the
expected date of issue.

1.2 Discrepancies in "Planned Dates" between the list from KAZ Minerals and the Supplier's list shall be settled by the parties and must be
resolved prior to issuance of the Purchase Order. The planned dates obtained as a result of approval shall be indicated in the updated
column “PLANNED DATES" and included in the delivery schedule of the purchase requisition.
2 FORM OF DRAWINGS AND DATA

2.1 The text part of all drawings/data submitted for approval shall be provided in English. The text part of all the officially approved
drawings/data shall be provided in English. All dimensional units used must be international (SI). It is allowed to use the National
Standards Institute (ANSI) system units for pipes and valves.

2.2 All drawings and data, including Supplier's standard drawings, must be carefully checked for accuracy, clarity, completeness and
compliance with applicable codes, rules, specifications, etc. before being sent to KAZ Minerals.

2.3 The report must be provided to the Client IN A HARD COPY and electronic format. Drawings must be made using the Intergraph
Microstation or AutoCAD 2000i software. Other documents are expected to be in the Microsoft Word or Excel format. Each drawing
shall be submitted as a separate PDF file, while documents with multiple attachments shall be submitted as a single PDF file, and they
must be uploaded to the document repository.

2.4 Documents must be organized in the correct order, printed out on single sheets of D-size paper, and the print quality must be such that
they can be copied on photocopiers. Note!!! Illegible copies may be rejected.

2.5 Identification numbers and other data affixed by the Supplier on the drawings must match those specified in the Purchase Order. Similar
products may be shown on the same general drawing, provided that their identification numbers are fully legible.

2.6 All drawings and other documents provided by the Supplier must clearly contain the following notations: Project Description: []
Project и Project Number: []:
(a) The description reflecting the content must match the description specified in the Supplier's Drawing and Data Obligation forms
attached to the Purchase Requisition form.
(b) Purchase requisition number:
(c) Product number/equipment identification number (if applicable)
(d) Official name of the supplier’s company
(e) Drawing number assigned by the Supplier
(f) The latest revision shall be indicated by a number or letter, and a triangle with a number or letter shall indicate the changes
(g) A brief description of each edition shall be indicated in the table
(h) Bills of materials and spare parts must include standards for the materials
(i) Supplier data that does not correspond to the codes in this form must use the designation “OTN":
3 VERIFICATION PROCEDURE

3.1 The Supplier shall provide officially approved copies of all the drawings listed on the Supplier's Drawing and Data Obligation Form,
having placed in the corner stamp the information provided for in Section 3.7 below: The submitted documentation shall match the Bills
of materials. Note!!! DRAWINGS NOT STAMPED ‘AS «APPROVED»' MUST BE STAMPED 'PRELIMINARY'. They shall be used
for preliminary design purposes only and the Planned Date column shall not be populated for them.

3.2 KAZ Minerals will check general conformity of these drawings with the requirements of the Purchase Order/Contact and return one
copy stamped «FOR USE IN MANUFACTURING», «FOR USE IN MANUFACTURING UPON MODIFYING AS SPECIFIED AND
RE-SUBMITTING WITH THE STAMP «APPROVED»», or «NOT FOR USE IN MANUFACTURING», «MODIFY AS SPECIFIED
AND RE-SUBMIT», or «FOR INFORMATION ONLY».

3.3 The drawings stamped as «FOR USE IN MANUFACTURING UPON RECEIVING THE RETURNED DRAWING STAMPED AS
FOR USE IN MANUFACTURING» or «FOR USE IN MANUFACTURING UPON MODIFYING AS SPECIFIED AND RE-
SUBMITTING WITH THE STAMP «APPROVED»», or «FOR INFORMATION ONLY» – The Supplier must commence
manufacturing. Drawings stamped «For use in manufacturing» do not have to be re-submitted if they have already been officially
approved.

3.4 Drawings received with the stamp «FOR USE IN MANUFACTURING UPON MODIFYING AS SPECIFIED AND RE-SUBMITTING
WITH THE STAMP «APPROVED»» – the Supplier must, within 10 days of the receipt of a drawing or another document returned with
the stamp «FOR USE IN MANUFACTURING UPON MODIFYING AS SPECIFIED AND RE-SUBMITTING WITH THE STAMP
«APPROVED»», make the respective modifications or adjustments and transfer the appropriate quantity stamped as «APPROVED» to
KAZ Minerals. The supplier shall proceed to manufacturing upon the completion of the modifications or adjustments of the drawings.
3.5 Drawings received with the stamp «NOT FOR USE IN MANUFACTURING; MODIFY AS SPECIFIED AND RE-SUBMIT» – the
Supplier must, within 10 days of the receipt of a drawing or another document returned with the stamp «NOT FOR USE IN
MANUFACTURING; MODIFY AS SPECIFIED AND RE-SUBMIT», make the respective modifications or adjustments and re-submit
for review. Where instructions for adjustment of a separate drawing or document entail modifications in other documents or drawings,
the Supplier must also amend all these related documents and at the same time send the adjusted and related documents for re-approval.
It is forbidden to commence manufacturing based on the drawings received with a stamp «NOT FOR USE IN MANUFACTURING;
MODIFY AS SPECIFIED AND RE-SUBMIT».

3.6 All the bills of spare parts, user guides, operating and installation manuals, etc. shall be submitted with the notation «Officially
Approved».

3.7 Certification
The certification stamp must contain the following information:
(a) The signature of the officially authorized Supplier Representative
(b) Company name
(c) Certification date
(d) Designer’s Seal
4 INSTRUCTIONS FOR COURIER DELIVERY

4.1 The submitted drawings and documents of the Supplier must be accompanied with the handover documentation schedule indicating the
number of the Purchase Order, identification numbers, and the list of drawings and documentation.

4.2 All drawings and documentation shall be sent to:

Document Control Section [], KAZ Minerals


To: E-mail:
CC:
E-mail: