Professional Documents
Culture Documents
Okafor Ee Report
Okafor Ee Report
1.0 Introduction
1.1 SIWES
the campus. The experience gotten by the students during the SIWES program
would enable them quickly fit into the industry upon graduation.
design, AutoCAD, and other relevant software such as Plant design management
1
day to day activities at ZES were recorded in the log book.
SHELL (SPDC) .KSA electrical services is a one man company owned by Engr
Emmanuel Okoro an electrical engineer. The company has the total numbers of 8
(eight) employees and 3 (three) contract staff, which are all professional in the
field of electrical and fire alarm. The company head office is located at KM.1
Ughelli Patani Road, Opposite Cosco Filling Station, Okuokoko, Warri, Delta
State.
equipment), safety materials, and electrical integrity testing such as continuity test,
insulation test and polarity test, as well as fire alarm devices installation to
2
CONTINUITY TEST: This is to ensure integrity of the live, neutral and earth
INSULATION TEST: this test is to ensure that there is a high resistance between
live and neutral conductors and these conductors and earth conductors, a low
resistance will result in current leakage and energy waste which could deteriorate
POLARITY TEST: this is to ensure that all switches and circuit breakers are
3
4
Chapter two
Description of attachment
KSA's history
(SPDC) .KSA electrical services is a one man company owned by Engr Emmanuel
Okoro, an electrical engineer. The company has the total numbers of 8 (eight)
employees and 3 (three) contract staff, which are all professional in the field of
electrical and fire alarm. The company head office is located at KM.1 Ughelli
Patani Road, Opposite Cosco Filling Station, Okuokoko, Warri, Delta State.
And has branches at SHELL Residential Area, Aba Road, Port Harcourt and
Vision
Mission
"To provide world class engineering services in the oil and gas industry."
Quality Policy
5
2.1.2 KSA's Departments
The various departments in KSA and their functions with respect to project
execution are:
Technical Departments
studies.
project including arranging for site visits, liaison with the customers to inform
them about the progress of their projects. Management of all capital projects.
materials needed by the other departments and keeps stock of what is available
training, short- term courses and seminars, overseas rotational training etc, to
6
2.1.2 Fire alarm department
department with the total numbers of four (4) staff. This department is directly in
installation, such as fire extinguishers, fire call point etc. this department is also in
department with the total numbers of four (4) staff. Electrical department is
materials such as cables, lighting fittings and power equipment such as industrial
Since its inception, KSA has executed more than 100 projects of
• Installation and maintenance of FM200 smoke detector and fire alarm panel
at SPDC west
7
• Conceptual design for the Cawthorne Gas injection/supply project for Shell.
Troubleshooting: this is the process of tracing to rectify fault that the cause is
unknown .i.e. if some lighting in a circuit are not lighting while others in the same
circuit are working, first you test the lighting point of the once that are not working
to see if there is supply, if there is current in both live and neutral conductors you
will know that the neutral has cut off at a point, and it is known as short circuit.
Electrical wiring: this is the networking system or arrangement of cables for the
(1) CONDUIT WIRING: this is the process whereby electric cables are
(2) CLEAT WIRING: this is a system of wiring done in an industry with the
installations to verify that the system will operate efficiently and safely. The tests
electrical engineer.
8
THE FOLLOWING TESTS ARE AN ESSENTIAL PART OF THE
PROCESSINGS
(1) DEAD TEST: - this is the process of testing completed installations without
power supply. The aim is to test the continuity to ensure integrity of the
live, neutral and the earth conductors without bridging (short circuit).
Testing the insulation to ensure that there is a high resistance between live
and neutral and earth conductors. Testing polarity to ensure all switches and
(2) LIVE TEST this is the process of testing completed installation with power
supply. The aim is to know the load that is connected to each circuit, each
phase and entire 415v that is supplied. During this test we also test for earth
9
Chapter three
Usually, a typical project begins in the process group with the conceptual or
basic design. The process group develops the initial block diagrams, evaluates all
the options, and proposes the best alternative for the project.
Other disciplines (Electrical group inclusive) will then work on what the process
To ensure that the system designed is safe for both personnel and equipment.
To achieve the above objectives, the following activities are usually carried
10
Carry out electrical equipment sizing and selection.
electrical equipment.
Deliverables are documents produced by a group with respect to the scope of the
Supplementary Drawing
Data sheets
Cable schedules
Installation details
Specifications
11
AutoCAD
Microsoft Excel
Microsoft Word
Chalmlite
Multisim
Engineering design practices. The projects executed at KSA ensured that Engineers
worked in teams, hence, I was taught to be a team player, and a good one at that. I
This is one of the starting point for the electrical group activities.
cables, distribution boards etc. I learnt how to compute a load list, which is
usually a Microsoft Excel document showing all intended loads, their tag
numbers, current, voltage and power ratings, efficiencies, power factors, and
service duty.
12
There were many instances where I was required to develop one or single line
diagrams. The electrical load list came in very handy in such instances.
A single line diagram is a schematic drawing that uses graphical symbols and
various loads, Generation philosophies, load layouts, busbars and their respective
voltage levels, system protection devices, amongst others. These are well shown on
single line diagrams with standard electrical symbols. I received extensive training
on the use of autoCAD, which is the software used by the electrical group to draw
one line diagrams. Figure 3 below shows a single line diagram which I drew with
the aid of autoCAD for the R.A Club Kitchen, whose load summary is shown in
Figure 3.1
Fig. 3.2
13
3. Equipment sizing and Cable sizing
Areas covered here include Generator sizing, Transformer sizing, circuit breaker
sizing, and cable sizing calculations. I also learnt about the relevant standards and
codes as regards equipment sizing and cable selection, such as the National
(NEMA) codes.
the R.A Club kitchen equipment project. The calculations I carried out are shown
below:
14
CALCULATIONS
FORMULA USED:
GEN. SIZING:
INTERMITTENT LOAD.
TRANSFORMER SIZING:
15
T1 (11\ 33 KV)
RL = 30,000 KVA
T2 (11\6.6 KV)
RL = 414 KVA
T3 SIZE = 500KVA
T4 SIZE = 500KVA
16
T5 SIZE = 750 KVA
CABLE SIZING:
FORMULA USED:
CB SIZE: 1200A
CABLE SIZE:
T1:
CB SIZE: 2000A
CABLE SIZE:
CB SIZE: 700A
17
CABLE SIZE:
T2:
CB SIZE: 40A
CABLE SIZE:
CB SIZE: 70A
CABLE SIZE:
T3:
CB SIZE: 30A
CABLE SIZE:
CB SIZE: 800A
CABLE SIZE:
T4
CB SIZE: 30A
CABLE SIZE:
18
CB SIZE: 800A
CABLE SIZE:
T5 = T6
CB SIZE: 40A
CABLE SIZE:
CB SIZE: 1600A
CABLE SIZE:
These current values are also used for sizing the transformer and generator CBs.
Formula used:
I = P/ ((3*V)
BUS A:
CB = 150A
BUS B:
19
Generator starter motor
CB= 70A
BUS C:
CB: 80A
= 293.2A
CB: 250A
BUS D:
Causeway lighting
CB: 20A
20
HVAC supply
CB: 30A
CB: 150A
BUS E:
UPS
CB: 15A
Warehouse supply 2
CB: 15A
Obstruction lighting
21
Cable size: 1.5 mm2
CB: 15A
CB: 25A
BUS F
P1 = P2
CB: 125A
P3 = P4
CB: 50A
P5 = P6
CB: 125A
22
P7 = P8
CB: 300A
P9:
CB: 15A
CB: 15A
An electrical layout drawing gives a plan view of an area (e.g a Flow station), and
draw layout drawings using auto CAD. I learnt about the various factors to be
I was also trained on how to produce hazardous area drawings using autoCAD. A
23
construction and use of all electrical apparatus. The purpose of these drawings is to
provide assistance in selecting the correct certified equipment for hazardous zones
(as will be clearly noted on the drawing) such as petrochemical plants, refineries,
These drawings are also produced at later electrical design stages for a project. I
was also opportune to see how these drawings were produced and their relevance
to the project. The training I received involved the use of the following
• AutoCAD
AutoCAD
extremely powerful tool. The speed and ease at which a drawing can be prepared
24
preparation. There is virtually no limit to the kind of drawings that can be
prepared using the software. AutoCAD provides a set of entities for use in
string annotations. The effect of every change appears immediately, thus enabling
the designer to take immediate decisions concerning size, aesthetics and taste of
a variety of ways e.g. erasing or moving entities or copying them from repeated
patterns.
information about the drawing can be displayed. The use of layers and assigning
colours to the different layers enhances the appearance of the end product and aids
in detecting errors in the drawing that would otherwise have gone undetected. The
final drawing can then be plotted with a pen plotter or printer plotter. The
importance of this software can be more appreciated in that is saves time and cost
work, thus, ensuring a more professional and accurate output. The activities of the
electrical group to which to which I was attached, involved the extensive use of
AutoCAD.
By virtue of the training I received and exposure, I have acquired the following
25
skills from the SIWES workplace (i.e. KSA):
spreadsheets.
iii. Ability to use chalmlite to carry out lighting design and calculations.
drafting software.
others.
26
Chapter four
4.1 Summary
The purpose of this SIWES program is to bridge the gap between classroom
and the industries so that student will be well prepared for the task ahead after their
Installation works, it has really help me to bridge the gap between the classroom
and the industry, this industrial training really gave me an insight to the task that
Training Report is aimed to picture the various task that is being carried out in the
industry on the field of Electrical Engineering, the skill acquired and the challenges
on the aspect of Innovation and Creation in order to make the world a comfortable
4.2 Recommendation
Also, the ITCC should find a way to liaise with the company that students
27
bus for the students, being an example I spent an average of 500 naira daily
The ITCC should also ensure frequent visit of supervisors to the companies
Students should be posted on time to ensure that there is time to get enough
The main essence of the scheme should be made known to the companies, so
that students are not assigned to tasks that are not of benefit to his/her career
development.
4.4 Conclusion
which included the following: Development of load and single line diagrams,
28
and circuit breaker sizing, preparation of material take- off and bill of
SIWES gave me the opportunity to learn about good work ethics, good
29
References
www.shell.com.ng/aboutshell/at-a-glance.html
Harrison Inspection and Training (Nig) ltd. Electrical Installations and systems.
30
APPENDIX
As Built Drawings
31