Contract No.

ADB-301A-2018
Design, Supply, Installation, Testing & Commissioning of 500kV D/C Quad Bundle Transmission Line Nokhar S/s-Lahore North S/S-Lahore HVDC Switching/Convertor Station
(Job# 4185)

DAILY PROGRESS REPORT


December 02, 2021
Contractor: M/s. CET
Section-1 Section-2
Cumulative as of Today
Nokhar S/S-Lahore North S/S Lahore North S/S - HVDC Converter Station
Activity
Qty %
Total Daily Progress This Day This Month To Date Total Daily Progress This Day This Month To Date Grand Total
Completed Completed

1 2 3 4 5 6 7 8 9 10 11 12=2+7 13=6+11 14=(13/12)*100


Validation of Route, Detailed Survey, Preparation of Validation of Route, Detailed Survey, Preparation of
VALIDATION OF ROUTE 44.34 km Plan & Profile Drawings & Structure List Completed 44.34 km 68.07 km Plan & Profile Drawings & Structure List Completed 68.07 km 112.41 km 112.41 km 100

SOIL INVESTIGATION 35 Completed 35 45 Completed (BH# 48 Terminated) 44 80 79 100

TOWER STAKING 133 22 205 T#101 to T#104 staked in the field Naqash). 4 4 20 338 42 12.43

TOWER RELEASE 133 22 205 5 338 27 7.99

T#100 Excavation is in progress.


EXCAVATION 133 T#11 & T#92 is in progress. 1 1 205 2 338 3 0.89

Steel and Form work fixing at T#10

and T#92 is in progress T# 134 Leg 1 & Leg 3 concreted.

TOWER FOUNDATION 133 (Asad,Waseem) 0 0 0 205 (Shahbaz, Tayyab) 0.5 0.75 0.75 338 0.75 0.22

BACKFILLING 0

TOWER ERECTION 0

STRINGING 0

Note. Due to non functioning of RTK Receiver, staking of towers started late.
REMARKS

CM Nespak visited T#134 (Section-II)

719601602.xlsx
Contract No. ADB-301A-2018
Design, Supply, Installation, Testing & Commissioning of 500kV D/C Quad Bundle Transmission Line Nokhar S/s-Lahore North S/S-Lahore HVDC Switching/Convertor Station
(Job# 4185)

DAILY PROGRESS REPORT


December 01, 2021
Contractor: M/s. CET
Section-1 Section-2
Cumulative as of Today
Nokhar S/S-Lahore North S/S Lahore North S/S - HVDC Converter Station
Activity
Qty %
Total Daily Progress This Day This Month To Date Total Daily Progress This Day This Month To Date Grand Total
Completed Completed

1 2 3 4 5 6 7 8 9 10 11 12=2+7 13=6+11 14=(13/12)*100


Validation of Route, Detailed Survey, Preparation of Validation of Route, Detailed Survey, Preparation of
VALIDATION OF ROUTE 44.34 km Plan & Profile Drawings & Structure List Completed 44.34 km 68.07 km Plan & Profile Drawings & Structure List Completed 68.07 km 112.41 km 112.41 km 100

SOIL INVESTIGATION 35 Completed 35 45 Completed (BH# 48 Terminated) 44 80 79 100

TOWER STAKING 133 22 205 16 338 38 11.24

TOWER RELEASE 133 22 205 5 338 27 7.99

T#99 & 134 Excavation completed.


EXCAVATION 133 T#10 completed & T#92 is in progress. 1 1 1 205 2 338 3 0.89

Steel and Form work fixing at T#10 T#99 Leg D concreted (Naqash).

and T#92 is in progress T# 134 Leg A preparation for

TOWER FOUNDATION 133 0 0 0 205 concrete completed. 0.25 0.25 0.5 338 0.5 0.15
(Shahbaz, Tayyab)

BACKFILLING 0

TOWER ERECTION 0

STRINGING 0

T&P Inspection of Conventional foundation crew-6 (Astola Crew)and Crew-7 carried out (Asad Shafiq, Waseem 01 no. water sample (for Norang Crew) near to T#168 (owner Mushtaq Ahmed) collected for testing (Daya
Ahmed) Ram).

CM Nespak visited T#54 and T#10 (Section-I)


REMARKS

SDO NTDC HVDC visited T#99 and T# 134