Contract No.

ADB-301A-2018
Design, Supply, Installation, Testing & Commissioning of 500kV D/C Quad Bundle Transmission Line Nokhar S/s-Lahore North S/S-Lahore HVDC Switching/Convertor Station
(Job# 4185)

DAILY PROGRESS REPORT


December 27, 2021

Section-1 Section-2
Cumulative as of Today
Nokhar S/S-Lahore North S/S Lahore North S/S - HVDC Converter Station
Activity
Qty %
Total Daily Progress This Day This Month To Date Total Daily Progress This Day This Month To Date Grand Total
Completed Completed

1 2 3 4 5 6 7 8 9 10 11 12=2+7 13=6+11 14=(13/12)*100


Validation of Route, Detailed Survey, Preparation of Validation of Route, Detailed Survey, Preparation of
VALIDATION OF ROUTE 44.34 km Plan & Profile Drawings & Structure List Completed 44.34 km 68.07 km Plan & Profile Drawings & Structure List Completed 68.07 km 112.41 km 112.41 km 100

SOIL INVESTIGATION 35 Completed 35 45 Completed (BH# 48 Terminated) 44 80 79 100

TOWER STAKING 132 59 81 205 58 74 337 155 45.99

T#106 to 109 and T#122 to T#130 released for


TOWER RELEASE 132
construction 13 59 81 205 70 74 337 155 45.99

EXCAVATION 132 25 25 205 T#107 Completed 1 18 20 337 45 13.35

T#57 L1 & 3 Concreted (Shahbaz) T#106 L2&4 Concreted (Daya Ram Sb)

T# 17 L3 Concreted (Asad) T#61 L2&4 Concreted.(Jehanzeb)


CONVENTIONAL
FOUNDATION
132 T#71 L2&4 Cancelled due to failure of Course 0.75 22.5 22.5 205 1.5 19.25 19.5 337 42 12.46
T#170 L2&4 Concreted (Saqlain)
Aggregate Sieve analysis ( Tayab)
T#96 L1&3 Cancelled due to incomplete preparation
(Naqash)

PILE FOUNDATION

PILE CAP

BACKFILLING 132 T#66 Completed T#67,86,58&15 is in progress. 1 9 9 205 T#60 Completed & T#144,59 is in progress 1 9 9 337 18 5.34

TOWER ERECTION 0

STRINGING 44.34 km 68.07 km 0

T#18 L2&4 , T#86 L4 formopening carried out. T#61 L1&3 & T#143 L1&3 formopening carried out.

Water sample collected from near T#125 & 130 (Naqash) T#72 & 76 (Tayab)
,

747231713.xlsx
Contract No. ADB-301A-2018
Design, Supply, Installation, Testing & Commissioning of 500kV D/C Quad Bundle Transmission Line Nokhar S/s-Lahore North S/S-Lahore HVDC Switching/Convertor Station
(Job# 4185)

DAILY PROGRESS REPORT


December 26, 2021

Section-1 Section-2
Cumulative as of Today
Nokhar S/S-Lahore North S/S Lahore North S/S - HVDC Converter Station
Activity
Qty %
Total Daily Progress This Day This Month To Date Total Daily Progress This Day This Month To Date Grand Total
Completed Completed

1 2 3 4 5 6 7 8 9 10 11 12=2+7 13=6+11 14=(13/12)*100


Validation of Route, Detailed Survey, Preparation of Validation of Route, Detailed Survey, Preparation of
VALIDATION OF ROUTE 44.34 km Plan & Profile Drawings & Structure List Completed 44.34 km 68.07 km Plan & Profile Drawings & Structure List Completed 68.07 km 112.41 km 112.41 km 100

SOIL INVESTIGATION 35 Completed 35 45 Completed (BH# 48 Terminated) 44 80 79 100

TOWER STAKING 132 59 81 205 58 74 337 155 45.99

TOWER RELEASE 132 46 68 205 70 74 337 142 42.14

EXCAVATION 132 T#17,57,96 Completed 3 25 25 205 T#142 Completed 1 17 19 337 44 13.06

T#18 L2 & 4 Concreted (Shahbaz) T#143 L1&3 Concreted (Jehanzeb)

CONVENTIONAL T# 86 L4 concreted (Waseem) T#61 L1&3 Concreted.(Saqlain)


FOUNDATION
132 0.75 21.75 21.75 205 1 17.75 18 337 39.75 11.80

T&P Inspection of SCA Crew carried out


PILE FOUNDATION

PILE CAP

BACKFILLING 132 T#66,67 is in progress. 8 8 205 T#105 Completed 1 8 8 337 16 4.75

TOWER ERECTION 0

STRINGING 44.34 km 68.07 km 0

T#18 L1&3 , T#71 L1&3, T#86 L2 formopening carried out. T#169 L1&3,T#106 L2&4 & T#143 L1&3 , formopening carried out.

747231713.xlsx
Contract No. ADB-301A-2018
Design, Supply, Installation, Testing & Commissioning of 500kV D/C Quad Bundle Transmission Line Nokhar S/s-Lahore North S/S-Lahore HVDC Switching/Convertor Station
(Job# 4185)

DAILY PROGRESS REPORT


December 25, 2021

Section-1 Section-2
Cumulative as of Today
Nokhar S/S-Lahore North S/S Lahore North S/S - HVDC Converter Station
Activity
Qty %
Total Daily Progress This Day This Month To Date Total Daily Progress This Day This Month To Date Grand Total
Completed Completed

1 2 3 4 5 6 7 8 9 10 11 12=2+7 13=6+11 14=(13/12)*100


Validation of Route, Detailed Survey, Preparation of Validation of Route, Detailed Survey, Preparation of
VALIDATION OF ROUTE 44.34 km Plan & Profile Drawings & Structure List Completed 44.34 km 68.07 km Plan & Profile Drawings & Structure List Completed 68.07 km 112.41 km 112.41 km 100

SOIL INVESTIGATION 35 Completed 35 45 Completed (BH# 48 Terminated) 44 80 79 100

TOWER STAKING 132 59 81 205 58 74 337 155 45.99

TOWER RELEASE 132 46 68 205 56 60 337 128 37.98

EXCAVATION 132 T#71,18 Completed 2 22 22 205 16 18 337 40 11.87

T#18 L1 & 3 concreted (Waseem) T#143 2&4 Concreted (Jehanzeb)

CONVENTIONAL T# 58 L4 concreted (Shahbaz) T#169 L1&3 Concreted.(Saqlain)


FOUNDATION
132 1.5 21 21 205 1.5 16.75 17 337 38 11.28
T# 71 L1&3 Concreted (Tayab) T#106 L1&3 Concreted (Daya Ram)

T# 86 L2 Concreted (Naqash)

PILE FOUNDATION

PILE CAP

BACKFILLING 132 T#88 Completed T#66,67 is in progress. 1 8 8 205 T#141 Completed 1 7 7 337 15 4.45

TOWER ERECTION 0

STRINGING 44.34 km 68.07 km 0

T#16 L2&4 , T#58 L2, T#86 L3 formopening carried out. T#59 L2&4 , T#144 L2&4 , formopening carried out.

Steel Sample of #10 Collected from CET Store. Steel Sample of #6,8,10 Collected from CET Store.
,

747231713.xlsx
Contract No. ADB-301A-2018
Design, Supply, Installation, Testing & Commissioning of 500kV D/C Quad Bundle Transmission Line Nokhar S/s-Lahore North S/S-Lahore HVDC Switching/Convertor Station
(Job# 4185)

DAILY PROGRESS REPORT


December 24, 2021
Contractor: M/s. CET
Section-1 Section-2
Cumulative as of Today
Nokhar S/S-Lahore North S/S Lahore North S/S - HVDC Converter Station
Activity
Qty %
Total Daily Progress This Day This Month To Date Total Daily Progress This Day This Month To Date Grand Total
Completed Completed

1 2 3 4 5 6 7 8 9 10 11 12=2+7 13=6+11 14=(13/12)*100


Validation of Route, Detailed Survey, Preparation of Validation of Route, Detailed Survey, Preparation of
VALIDATION OF ROUTE 44.34 km Plan & Profile Drawings & Structure List Completed 44.34 km 68.07 km Plan & Profile Drawings & Structure List Completed 68.07 km 112.41 km 112.41 km 100

SOIL INVESTIGATION 35 Completed 35 45 Completed (BH# 48 Terminated) 44 80 79 100

T#106 to 109 and T#122 to 130 staked in the field


TOWER STAKING 132
(Naqash)
11 59 81 205 58 74 337 155 45.99

T#97,98 and T#99/100 to 105 Released for


TOWER RELEASE 132
construction. 8 46 68 205 56 60 337 128 37.98

EXCAVATION 132 20 20 205 T#143 & 106 Completed 2 16 18 337 38 11.28

T#16 L2 & 4 concreted (Shahbaz)

TOWER FOUNDATION 132 T# 58 L2 concreted (Waseem) 1.5 19.5 19.5 205 T#59 L2&4 Completed.(Jehanzeb) 0.5 15.25 15.5 337 35 10.39
T# 86 L3 Concreted (Tayab)

T# 70 L1&3 Concreted (Saqlain)

BACKFILLING T#66,67,88 is in progress. 7 7 T#104 Completed 1 6 6 13

TOWER ERECTION 0

STRINGING 0

T#16 L1&3 , T#58 L3, T#86 L1 formopening carried out. T#105 L1&3 , T#144 L1&3 , T59 L1&3 formopening carried out.

747231713.xlsx
Contract No. ADB-301A-2018
Design, Supply, Installation, Testing & Commissioning of 500kV D/C Quad Bundle Transmission Line Nokhar S/s-Lahore North S/S-Lahore HVDC Switching/Convertor Station
(Job# 4185)

DAILY PROGRESS REPORT


December 23, 2021
Contractor: M/s. CET
Section-1 Section-2
Cumulative as of Today
Nokhar S/S-Lahore North S/S Lahore North S/S - HVDC Converter Station
Activity
Qty %
Total Daily Progress This Day This Month To Date Total Daily Progress This Day This Month To Date Grand Total
Completed Completed

1 2 3 4 5 6 7 8 9 10 11 12=2+7 13=6+11 14=(13/12)*100


Validation of Route, Detailed Survey, Preparation of Validation of Route, Detailed Survey, Preparation of
VALIDATION OF ROUTE 44.34 km Plan & Profile Drawings & Structure List Completed 44.34 km 68.07 km Plan & Profile Drawings & Structure List Completed 68.07 km 112.41 km 112.41 km 100

SOIL INVESTIGATION 35 Completed 35 45 Completed (BH# 48 Terminated) 44 80 79 100

TOWER STAKING 133 T#97 to 105 staked in the field (Naqash) 9 48 70 205 58 74 338 144 42.60

TOWER RELEASE 133 38 60 205 56 60 338 120 35.50

EXCAVATION 133 T#16,86 Completed 2 20 20 205 14 16 338 36 10.65

T#16 L1 & 3 concreted (Waseem) T#105 L1&3 Concreted (Saqlain)

TOWER FOUNDATION 133 T# 58 L3 concreted (Shahbaz) 1 18 18 205 T#59 L1&3 Completed.(Jehanzeb) 1.5 14.75 15 338 33 9.76
T# 86 L1 Concreted (Shahbaz/Naqash) T#144 L2&4 Concreted (Tayab)

BACKFILLING T#90 Completed & T#66,67 & 52 is in progress. 1 7 7 T#58, 60, 141 is in progress 5 5 12

TOWER ERECTION 0

STRINGING 0

T#58 L1 , T#14 L2 & L4 formopening carried out. T#105 L2&4 , T#169 L4 formopening carried out.

747231713.xlsx
Contract No. ADB-301A-2018
Design, Supply, Installation, Testing & Commissioning of 500kV D/C Quad Bundle Transmission Line Nokhar S/s-Lahore North S/S-Lahore HVDC Switching/Convertor Station
(Job# 4185)

DAILY PROGRESS REPORT


December 22, 2021
Contractor: M/s. CET
Section-1 Section-2
Cumulative as of Today
Nokhar S/S-Lahore North S/S Lahore North S/S - HVDC Converter Station
Activity
Qty %
Total Daily Progress This Day This Month To Date Total Daily Progress This Day This Month To Date Grand Total
Completed Completed

1 2 3 4 5 6 7 8 9 10 11 12=2+7 13=6+11 14=(13/12)*100


Validation of Route, Detailed Survey, Preparation of Validation of Route, Detailed Survey, Preparation of
VALIDATION OF ROUTE 44.34 km Plan & Profile Drawings & Structure List Completed 44.34 km 68.07 km Plan & Profile Drawings & Structure List Completed 68.07 km 112.41 km 112.41 km 100

SOIL INVESTIGATION 35 Completed 35 45 Completed (BH# 48 Terminated) 44 80 79 100

TOWER STAKING 133 39 61 205 58 74 338 135 39.94

T#57 to T#63 & T#69 to 80 released for construction. T#190 to T#199 released for construction.
TOWER RELEASE 133 (20/12/2021) 23 38 60 205 T#63 to 74 & 87 to 90 & 105 to 107 released for 29 56 60 338 120 35.50
T#93 to 96 released for construction.(21/12/2021) construction.(20/12/2021)

EXCAVATION 133 T#58 Completed 1 18 18 205 T#144 Completed 1 14 16 338 34 10.06

T#169 L4 Concreted (Tayab)

T#14 L2 & 4 concreted (Waseem) T#105 L2&4 Concreted (Saqlain)


T#59 Cancelled due to non availability of Cement.
TOWER FOUNDATION 133 T# 58 L1 concreted (Shahbaz) 0.75 17 17 205 1.25 13.25 13.5 338 30.5 9.02
(Jehanzeb)

T# 70 L1 & L3 Cancelled due to unspecified size of T#144 L1&3 Concreted (Naqash)


Coarse Aggregate (Shahbaz)

BACKFILLING T#52 Completed & T#66,67 & 90 is in progress. 1 6 6 T#58 is in progress & T#140 Completed 1 5 5 11

TOWER ERECTION 0

STRINGING 0

T#70 L2&4 , T#14 L1 & L3 formopening carried out. T#141 L1&3 formopening carried out.

Water Sample Collected From Near T#195 (Tayab)


,

747231713.xlsx
Contract No. ADB-301A-2018
Design, Supply, Installation, Testing & Commissioning of 500kV D/C Quad Bundle Transmission Line Nokhar S/s-Lahore North S/S-Lahore HVDC Switching/Convertor Station
(Job# 4185)

DAILY PROGRESS REPORT


December 21, 2021
Contractor: M/s. CET
Section-1 Section-2
Cumulative as of Today
Nokhar S/S-Lahore North S/S Lahore North S/S - HVDC Converter Station
Activity
Qty %
Total Daily Progress This Day This Month To Date Total Daily Progress This Day This Month To Date Grand Total
Completed Completed

1 2 3 4 5 6 7 8 9 10 11 12=2+7 13=6+11 14=(13/12)*100


Validation of Route, Detailed Survey, Preparation of Validation of Route, Detailed Survey, Preparation of
VALIDATION OF ROUTE 44.34 km Plan & Profile Drawings & Structure List Completed 44.34 km 68.07 km Plan & Profile Drawings & Structure List Completed 68.07 km 112.41 km 112.41 km 100

SOIL INVESTIGATION 35 Completed 35 45 Completed (BH# 48 Terminated) 44 80 79 100

TOWER STAKING 133 39 61 205 T#190 to 199 staked in the field (Naqash) 10 58 74 338 135 39.94

TOWER RELEASE 133 15 37 205 27 31 338 68 20.12

EXCAVATION 133 T#14 Completed 1 17 17 205 T#59 Completed 1 13 15 338 32 9.47

T#14 L1 & 3 concreted (Shahbaz)

TOWER FOUNDATION 133 T# 70 L2 & L4 concreted (Asad ) 1.5 16.25 16.25 205 12 12.25 338 28.5 8.43
T# 88 L2 & L4 concreted (Waseem)

BACKFILLING T#52,T#66,67 & 90 is in progress. 5 5 T#58 & 140 is in progress 4 4 9

TOWER ERECTION 0

STRINGING 0

T#15 L2&4 , 88 L1 & L3 formopening carried out. T#060 L1& L3, T#141 L2&4 formopening carried out.

Water Sample Collected From Near T#68 & 72 (Saqlain)


,

Steel Samples Collected with NTDC(HVDC) from CET Store.(Waseem) Steel Samples #3 (2 Samples), #4 (3 samples) and #6 (3 samples) collected from CET Store.(Tayab)

747231713.xlsx
Contract No. ADB-301A-2018
Design, Supply, Installation, Testing & Commissioning of 500kV D/C Quad Bundle Transmission Line Nokhar S/s-Lahore North S/S-Lahore HVDC Switching/Convertor Station
(Job# 4185)

DAILY PROGRESS REPORT


December 20, 2021
Contractor: M/s. CET
Section-1 Section-2
Cumulative as of Today
Nokhar S/S-Lahore North S/S Lahore North S/S - HVDC Converter Station
Activity
Qty %
Total Daily Progress This Day This Month To Date Total Daily Progress This Day This Month To Date Grand Total
Completed Completed

1 2 3 4 5 6 7 8 9 10 11 12=2+7 13=6+11 14=(13/12)*100


Validation of Route, Detailed Survey, Preparation of Validation of Route, Detailed Survey, Preparation of
VALIDATION OF ROUTE 44.34 km Plan & Profile Drawings & Structure List Completed 44.34 km 68.07 km Plan & Profile Drawings & Structure List Completed 68.07 km 112.41 km 112.41 km 100

SOIL INVESTIGATION 35 Completed 35 45 Completed (BH# 48 Terminated) 44 80 79 100

TOWER STAKING 133 39 61 205 48 64 338 125 36.98

TOWER RELEASE 133 15 37 205 27 31 338 68 20.12

EXCAVATION 133 T#88 Completed 1 16 16 205 T#105 Completed 1 12 14 338 30 8.88

T#15 L2 & 4 concreted (Asad) T#141 L1 & L3 Concreted (Tayab)

TOWER FOUNDATION 133 T# 56 L2 & L4 concreted (Waseem) 1.5 14.75 14.75 205 T#60 L1 & L3 Concreted (Saqlain) 1 12 12.25 338 27 7.99
T#169 L4 Not carried out due to Route change
T# 88 L1 & L3 concreted (Shahbaz)
(Naqash)

BACKFILLING T#52, T#66 is in progress. 5 5 T#58 & 140 is in progress 4 4 9

TOWER ERECTION 0

STRINGING 0

T#15 L1&3 , 56 L1 & L3 formopening carried out. T#104 L2& L4, T#169 L2 formopening carried out.

Water Sample Collected From Near T#005 (Jahanzeb), T#149(Tayab), T#169 &180 (Naqash)
,

747231713.xlsx
Contract No. ADB-301A-2018
Design, Supply, Installation, Testing & Commissioning of 500kV D/C Quad Bundle Transmission Line Nokhar S/s-Lahore North S/S-Lahore HVDC Switching/Convertor Station
(Job# 4185)

DAILY PROGRESS REPORT


December 19, 2021
Contractor: M/s. CET
Section-1 Section-2
Cumulative as of Today
Nokhar S/S-Lahore North S/S Lahore North S/S - HVDC Converter Station
Activity
Qty %
Total Daily Progress This Day This Month To Date Total Daily Progress This Day This Month To Date Grand Total
Completed Completed

1 2 3 4 5 6 7 8 9 10 11 12=2+7 13=6+11 14=(13/12)*100


Validation of Route, Detailed Survey, Preparation of Validation of Route, Detailed Survey, Preparation of
VALIDATION OF ROUTE 44.34 km Plan & Profile Drawings & Structure List Completed 44.34 km 68.07 km Plan & Profile Drawings & Structure List Completed 68.07 km 112.41 km 112.41 km 100

SOIL INVESTIGATION 35 Completed 35 45 Completed (BH# 48 Terminated) 44 80 79 100

TOWER STAKING 133 39 61 205 T#87 to 90 & 105 to107 staked in the field (Naqash) 7 48 64 338 125 36.98

TOWER RELEASE 133 15 37 205 27 31 338 68 20.12

EXCAVATION 133 T#15 & 56 Completed 2 15 15 205 T#141 Completed 1 11 13 338 28 8.28

T#104 L2 & L4 Concreted (Saqlain)

T#15 L1 & 3 concreted (Asad) T#141 L2 & L4 Concreted (Jahanzeb)

TOWER FOUNDATION 133 T# 56 L1 & L3 concreted (Waseem) 1 13.25 13.25 205 1.25 11 11.25 338 24.5 7.25
T#169 L2 Concreted (Tayab)

BACKFILLING T#12 Completed &T#52, T#66 is in progress. 1 5 5 T# 58 is in progress & 136 Completed 1 4 4 9

TOWER ERECTION 0

STRINGING 0

T#13 L2 , 67 L1 & L3 , T#67 L1 &L3 formopening carried out. T#140 L2& L4, 60 L2&L4 formopening carried out.

747231713.xlsx
Contract No. ADB-301A-2018
Design, Supply, Installation, Testing & Commissioning of 500kV D/C Quad Bundle Transmission Line Nokhar S/s-Lahore North S/S-Lahore HVDC Switching/Convertor Station
(Job# 4185)

DAILY PROGRESS REPORT


December 18, 2021
Contractor: M/s. CET
Section-1 Section-2
Cumulative as of Today
Nokhar S/S-Lahore North S/S Lahore North S/S - HVDC Converter Station
Activity
Qty %
Total Daily Progress This Day This Month To Date Total Daily Progress This Day This Month To Date Grand Total
Completed Completed

1 2 3 4 5 6 7 8 9 10 11 12=2+7 13=6+11 14=(13/12)*100


Validation of Route, Detailed Survey, Preparation of Validation of Route, Detailed Survey, Preparation of
VALIDATION OF ROUTE 44.34 km Plan & Profile Drawings & Structure List Completed 44.34 km 68.07 km Plan & Profile Drawings & Structure List Completed 68.07 km 112.41 km 112.41 km 100

SOIL INVESTIGATION 35 Completed 35 45 Completed (BH# 48 Terminated) 44 80 79 100

TOWER STAKING 133 T#57 to T# 63 staked in the field (Asad) 7 39 61 205 41 57 338 118 34.91

TOWER RELEASE 133 15 37 205 27 31 338 68 20.12

EXCAVATION 133 13 13 205 10 12 338 25 7.40

T#13 L2 concreted (Waseem)

TOWER FOUNDATION 133 T# 90 L1 & L3 concreted (Saqlain) 1 12.25 12.25 205 0.5 9.75 10 338 22.25 6.58
T#60 L2 & L4 concreted (Jahanzeb)

T#56 concrete cancelled by CET.

BACKFILLING T#12, 52 & T#66 is in progress. 4 4 T# 58 is in progress 3 3 7

TOWER ERECTION 0

STRINGING 0

T#13 L4 & 67 L2 & L4 formopening carried out. T#140 L1& L3, 104 L1&L3 formopening carried out.

T&P Re-Inspection of Norang Crew carried out (Naqash).

747231713.xlsx
Contract No. ADB-301A-2018
Design, Supply, Installation, Testing & Commissioning of 500kV D/C Quad Bundle Transmission Line Nokhar S/s-Lahore North S/S-Lahore HVDC Switching/Convertor Station
(Job# 4185)

DAILY PROGRESS REPORT


December 17, 2021
Contractor: M/s. CET
Section-1 Section-2
Cumulative as of Today
Nokhar S/S-Lahore North S/S Lahore North S/S - HVDC Converter Station
Activity
Qty %
Total Daily Progress This Day This Month To Date Total Daily Progress This Day This Month To Date Grand Total
Completed Completed

1 2 3 4 5 6 7 8 9 10 11 12=2+7 13=6+11 14=(13/12)*100


Validation of Route, Detailed Survey, Preparation of Validation of Route, Detailed Survey, Preparation of
VALIDATION OF ROUTE 44.34 km Plan & Profile Drawings & Structure List Completed 44.34 km 68.07 km Plan & Profile Drawings & Structure List Completed 68.07 km 112.41 km 112.41 km 100

SOIL INVESTIGATION 35 Completed 35 45 Completed (BH# 48 Terminated) 44 80 79 100

TOWER STAKING 133 T#69 to T#80 staked in the field (Asad) 12 32 54 205 41 57 338 111 32.84

TOWER RELEASE 133 15 37 205 27 31 338 68 20.12

EXCAVATION 133 13 13 205 T# 104 & 169 completed 2 10 12 338 25 7.40

T# 140 L2 & L4 concreted

T#13 L4 concreted (Waseem) (Jehanzeb,Saqlain)

TOWER FOUNDATION 133 T# 67 L1 & L3 concreted (Asad) 0.75 11.25 11.25 205 T# 104 L1 & L3 concreted (Tayyab) 1 9.25 9.5 338 20.75 6.14
T#60 L2 & L4 Pre-Concrete

Inspection carried out (Naqash)

BACKFILLING T#89 completed. T#12 & T#66 is in progress. 1 4 4 T# 97 completed and 58 is in progress 1 3 3 7

TOWER ERECTION 0

STRINGING 0

T#13 L3 & 52 L2 & L4 formopening carried out. T#58 L4 formopening carried out.

747231713.xlsx
Contract No. ADB-301A-2018
Design, Supply, Installation, Testing & Commissioning of 500kV D/C Quad Bundle Transmission Line Nokhar S/s-Lahore North S/S-Lahore HVDC Switching/Convertor Station
(Job# 4185)

DAILY PROGRESS REPORT


December 16, 2021
Contractor: M/s. CET
Section-1 Section-2
Cumulative as of Today
Nokhar S/S-Lahore North S/S Lahore North S/S - HVDC Converter Station
Activity
Qty %
Total Daily Progress This Day This Month To Date Total Daily Progress This Day This Month To Date Grand Total
Completed Completed

1 2 3 4 5 6 7 8 9 10 11 12=2+7 13=6+11 14=(13/12)*100


Validation of Route, Detailed Survey, Preparation of Validation of Route, Detailed Survey, Preparation of
VALIDATION OF ROUTE 44.34 km Plan & Profile Drawings & Structure List Completed 44.34 km 68.07 km Plan & Profile Drawings & Structure List Completed 68.07 km 112.41 km 112.41 km 100

SOIL INVESTIGATION 35 Completed 35 45 Completed (BH# 48 Terminated) 44 80 79 100

TOWER STAKING 133 20 42 205 T#63 to T#74 staked in the field (Naqash) 12 41 57 338 99 29.29

TOWER RELEASE 133 15 37 205 27 31 338 68 20.12

EXCAVATION 133 T# 67 & 90 completed. 2 13 13 205 T#140 & 104 completed 2 8 10 338 23 6.80

T#13 L3 concreted (Shahbaz) T# 140 L1 & L3 concreted (Jehanzeb)

TOWER FOUNDATION 133 T# 67 L2 & L4 concreted (Asad) 1.75 10.5 10.5 205 0.5 8.25 8.5 338 19 5.62
T# 52 L2 & L4 concreted (Waseem)

T# 90 L2 & L4 concreted (Daya Ram)

BACKFILLING T#53 & 92 completed. T#66 & T#89 is in progress. 2 3 3 T# 135 completed and 58 is in progress 1 2 2 5

TOWER ERECTION 0

STRINGING 0

T#13 L1 & 52 L1 & L3 formopening carried out.

747231713.xlsx
Contract No. ADB-301A-2018
Design, Supply, Installation, Testing & Commissioning of 500kV D/C Quad Bundle Transmission Line Nokhar S/s-Lahore North S/S-Lahore HVDC Switching/Convertor Station
(Job# 4185)

DAILY PROGRESS REPORT


December 15, 2021
Contractor: M/s. CET
Section-1 Section-2
Cumulative as of Today
Nokhar S/S-Lahore North S/S Lahore North S/S - HVDC Converter Station
Activity
Qty %
Total Daily Progress This Day This Month To Date Total Daily Progress This Day This Month To Date Grand Total
Completed Completed

1 2 3 4 5 6 7 8 9 10 11 12=2+7 13=6+11 14=(13/12)*100


Validation of Route, Detailed Survey, Preparation of Validation of Route, Detailed Survey, Preparation of
VALIDATION OF ROUTE 44.34 km Plan & Profile Drawings & Structure List Completed 44.34 km 68.07 km Plan & Profile Drawings & Structure List Completed 68.07 km 112.41 km 112.41 km 100

SOIL INVESTIGATION 35 Completed 35 45 Completed (BH# 48 Terminated) 44 80 79 100

TOWER STAKING 133 20 42 205 29 45 338 87 25.74

TOWER RELEASE 133 15 37 205 27 31 338 68 20.12

EXCAVATION 133 T# 52 & 13 completed. 2 11 11 205 6 8 338 19 5.62

T#13 L1 concreted (Shahbaz, Waseem)

TOWER FOUNDATION 133 T# 52 L1 & L3 concreted (Asad) 0.75 8.75 8.75 205 T# 58 L4 concreted (Jehanzeb, Tayyab) 0.25 7.75 8 338 16.75 4.96

BACKFILLING T#11, 54 & T#92 is in progress. 1 1 T#58, 135 is in progress 1 1 2

TOWER ERECTION 0

STRINGING 0

T#66 L2 & L4 & 89 L2 & L4 formopening carried out. T#58 L2,97 L2 & L4 and 136 L1 & L4 formopening carried out.

747231713.xlsx
Contract No. ADB-301A-2018
Design, Supply, Installation, Testing & Commissioning of 500kV D/C Quad Bundle Transmission Line Nokhar S/s-Lahore North S/S-Lahore HVDC Switching/Convertor Station
(Job# 4185)

DAILY PROGRESS REPORT


December 14, 2021
Contractor: M/s. CET
Section-1 Section-2
Cumulative as of Today
Nokhar S/S-Lahore North S/S Lahore North S/S - HVDC Converter Station
Activity
Qty %
Total Daily Progress This Day This Month To Date Total Daily Progress This Day This Month To Date Grand Total
Completed Completed

1 2 3 4 5 6 7 8 9 10 11 12=2+7 13=6+11 14=(13/12)*100


Validation of Route, Detailed Survey, Preparation of Validation of Route, Detailed Survey, Preparation of
VALIDATION OF ROUTE 44.34 km Plan & Profile Drawings & Structure List Completed 44.34 km 68.07 km Plan & Profile Drawings & Structure List Completed 68.07 km 112.41 km 112.41 km 100

SOIL INVESTIGATION 35 Completed 35 45 Completed (BH# 48 Terminated) 44 80 79 100

TOWER STAKING 133 20 42 205 29 45 338 87 25.74

TOWER RELEASE 133 T#43 to T#52 released for construction. 10 15 37 205 27 31 338 68 20.12

EXCAVATION 133 T# 52 is in progress. 9 9 205 6 8 338 17 5.03

T#97 L2 & L4 concreted (Naqash)

T#66 L2 & L4 concreted (Asad) T#136 L1 & L4 concreted Daya Ram, Jehanzeb)

TOWER FOUNDATION 133 T#89 L2 & L4 concreted (Waseem) 1 8 8 205 T# 58 L2 concreted (Tayyab) 1.25 7.5 7.75 338 15.75 4.66

BACKFILLING T#11, 54 & T#92 is in progress. 1 1 T#58 is in progress 1 1 2

TOWER ERECTION 0

STRINGING 0

T#53 L2 & L4 formopening carried out.

T#13 L1 concrete could not be carried out due to un availability of crush and sand from approved crushing T#137, 138, 115, 116 joint visit of NTDC Rep. from GM Office/NESPAK/CET carried out for shifting of tower
plant of Margala (Shahbaz) locations (Daya Ram)
,

747231713.xlsx
Contract No. ADB-301A-2018
Design, Supply, Installation, Testing & Commissioning of 500kV D/C Quad Bundle Transmission Line Nokhar S/s-Lahore North S/S-Lahore HVDC Switching/Convertor Station
(Job# 4185)

DAILY PROGRESS REPORT


December 13, 2021
Contractor: M/s. CET
Section-1 Section-2
Cumulative as of Today
Nokhar S/S-Lahore North S/S Lahore North S/S - HVDC Converter Station
Activity
Qty %
Total Daily Progress This Day This Month To Date Total Daily Progress This Day This Month To Date Grand Total
Completed Completed

1 2 3 4 5 6 7 8 9 10 11 12=2+7 13=6+11 14=(13/12)*100


Validation of Route, Detailed Survey, Preparation of Validation of Route, Detailed Survey, Preparation of
VALIDATION OF ROUTE 44.34 km Plan & Profile Drawings & Structure List Completed 44.34 km 68.07 km Plan & Profile Drawings & Structure List Completed 68.07 km 112.41 km 112.41 km 100

SOIL INVESTIGATION 35 Completed 35 45 Completed (BH# 48 Terminated) 44 80 79 100

TOWER STAKING 133 T#43 to T#52 staked in the field (Asad). 20 42 205 29 45 338 87 25.74

TOWER RELEASE 133 5 27 205 27 31 338 58 17.16

EXCAVATION 133 9 9 205 6 8 338 17 5.03

T# 97 L2 & L4 concreting could not

T#53 L2 & L4 concreted (Waseem) carried out due to non preparation.

TOWER FOUNDATION 133 0.5 7 7 205 Tayyab, Naqash) 6.25 6.5 338 13.5 3.99

T#135, T#99 & T#100 is in progress (completed up to


BACKFILLING T#10 completed and 54 & T#92 is in progress. 1 1 1 NSL). 1 1 2

TOWER ERECTION 0

STRINGING 0

T#12 L2 & L4, T#53 L1 & L3, T#89 L1 & L3 formopening carried out. T#139 L1 & L3 and T# 58 L1 formopening carried out .

747231713.xlsx
Contract No. ADB-301A-2018
Design, Supply, Installation, Testing & Commissioning of 500kV D/C Quad Bundle Transmission Line Nokhar S/s-Lahore North S/S-Lahore HVDC Switching/Convertor Station
(Job# 4185)

DAILY PROGRESS REPORT


December 12, 2021
Contractor: M/s. CET
Section-1 Section-2
Cumulative as of Today
Nokhar S/S-Lahore North S/S Lahore North S/S - HVDC Converter Station
Activity
Qty %
Total Daily Progress This Day This Month To Date Total Daily Progress This Day This Month To Date Grand Total
Completed Completed

1 2 3 4 5 6 7 8 9 10 11 12=2+7 13=6+11 14=(13/12)*100


Validation of Route, Detailed Survey, Preparation of Validation of Route, Detailed Survey, Preparation of
VALIDATION OF ROUTE 44.34 km Plan & Profile Drawings & Structure List Completed 44.34 km 68.07 km Plan & Profile Drawings & Structure List Completed 68.07 km 112.41 km 112.41 km 100

SOIL INVESTIGATION 35 Completed 35 45 Completed (BH# 48 Terminated) 44 80 79 100

TOWER STAKING 133 20 42 205 29 45 338 87 25.74

TOWER RELEASE 133 5 27 205 27 31 338 58 17.16

EXCAVATION 133 T#67 completed 1 9 9 205 6 8 338 17 5.03

T#12 L2 & L4 concreted (Asad) T# 139 L2 & L4 concreted (Naqash)

T#53 L1 & L3 concreted (Shahbaz)

TOWER FOUNDATION 133 T#89 L1 & L3 concreted (Daya Ram, Asad) 1.5 6.5 6.5 205 T#58 L1 concreted (Tayab) 0.75 6.25 6.5 338 13 3.85

BACKFILLING T#10, 54 and 92 is in progress. T#134 completed and T#99 & T#100 is in progress. 1 1 1 1

TOWER ERECTION 0

STRINGING 0

T#97 L1 & L3 and T# 58 L3 formopening carried out

747231713.xlsx
Contract No. ADB-301A-2018
Design, Supply, Installation, Testing & Commissioning of 500kV D/C Quad Bundle Transmission Line Nokhar S/s-Lahore North S/S-Lahore HVDC Switching/Convertor Station
(Job# 4185)

DAILY PROGRESS REPORT


December 11, 2021
Contractor: M/s. CET
Section-1 Section-2
Cumulative as of Today
Nokhar S/S-Lahore North S/S Lahore North S/S - HVDC Converter Station
Activity
Qty %
Total Daily Progress This Day This Month To Date Total Daily Progress This Day This Month To Date Grand Total
Completed Completed

1 2 3 4 5 6 7 8 9 10 11 12=2+7 13=6+11 14=(13/12)*100


Validation of Route, Detailed Survey, Preparation of Validation of Route, Detailed Survey, Preparation of
VALIDATION OF ROUTE 44.34 km Plan & Profile Drawings & Structure List Completed 44.34 km 68.07 km Plan & Profile Drawings & Structure List Completed 68.07 km 112.41 km 112.41 km 100

SOIL INVESTIGATION 35 Completed 35 45 Completed (BH# 48 Terminated) 44 80 79 100

TOWER STAKING 133 T#16 to T#25 staked in the field. 10 20 42 205 29 45 338 87 25.74

TOWER RELEASE 133 5 27 205 27 31 338 58 17.16

EXCAVATION 133 T#12, 53 and 89 completed 3 8 8 205 T#58 and 139 completed. 2 6 8 338 16 4.73

T#12 L1 & L3 concreted (Asad) T# 139 L1 & L3 concreted (Naqash)

T#66 L1 & L3 concreted (Shahbaz)

TOWER FOUNDATION 133 1 5 5 205 T#58 L3 concreted (Tayab) 0.75 5.5 5.75 338 10.75 3.18

BACKFILLING T#99, T#134 & T#135 is in progress. 0

TOWER ERECTION 0

STRINGING 0

T#54 L1 & L3 and T#92 L2 & L4 formopening carried out.

T&P Inspection of 8th crew carried out (Daya Ram).


,

747231713.xlsx
Contract No. ADB-301A-2018
Design, Supply, Installation, Testing & Commissioning of 500kV D/C Quad Bundle Transmission Line Nokhar S/s-Lahore North S/S-Lahore HVDC Switching/Convertor Station
(Job# 4185)

DAILY PROGRESS REPORT


December 10, 2021
Contractor: M/s. CET
Section-1 Section-2
Cumulative as of Today
Nokhar S/S-Lahore North S/S Lahore North S/S - HVDC Converter Station
Activity
Qty %
Total Daily Progress This Day This Month To Date Total Daily Progress This Day This Month To Date Grand Total
Completed Completed

1 2 3 4 5 6 7 8 9 10 11 12=2+7 13=6+11 14=(13/12)*100


Validation of Route, Detailed Survey, Preparation of Validation of Route, Detailed Survey, Preparation of
VALIDATION OF ROUTE 44.34 km Plan & Profile Drawings & Structure List Completed 44.34 km 68.07 km Plan & Profile Drawings & Structure List Completed 68.07 km 112.41 km 112.41 km 100

SOIL INVESTIGATION 35 Completed 35 45 Completed (BH# 48 Terminated) 44 80 79 100

TOWER STAKING 133 10 32 205 T#141 to T#153 staked in the field (Naqash) 13 29 45 338 77 22.78

TOWER RELEASE 133 5 27 205 27 31 338 58 17.16

EXCAVATION 133 5 5 205 4 6 338 11 3.25

T#54 L1 & L3 concreted (Asad) T# 97 Leg 1 & Leg 3 concreted

T#92 L2 & L4 concreted (Shahbaz) (Tayyab)


T#58 L1 & L3 Pre-Concrete Inspection is in progress
TOWER FOUNDATION 133 1 4 4 205
Daya Ram) 0.5 4.75 5 338 9 2.66

BACKFILLING 134 & T#135 is in progress. 0

TOWER ERECTION 0

STRINGING 0

747231713.xlsx
Contract No. ADB-301A-2018
Design, Supply, Installation, Testing & Commissioning of 500kV D/C Quad Bundle Transmission Line Nokhar S/s-Lahore North S/S-Lahore HVDC Switching/Convertor Station
(Job# 4185)

DAILY PROGRESS REPORT


December 09, 2021
Contractor: M/s. CET
Section-1 Section-2
Cumulative as of Today
Nokhar S/S-Lahore North S/S Lahore North S/S - HVDC Converter Station
Activity
Qty %
Total Daily Progress This Day This Month To Date Total Daily Progress This Day This Month To Date Grand Total
Completed Completed

1 2 3 4 5 6 7 8 9 10 11 12=2+7 13=6+11 14=(13/12)*100


Validation of Route, Detailed Survey, Preparation of Validation of Route, Detailed Survey, Preparation of
VALIDATION OF ROUTE 44.34 km Plan & Profile Drawings & Structure List Completed 44.34 km 68.07 km Plan & Profile Drawings & Structure List Completed 68.07 km 112.41 km 112.41 km 100

SOIL INVESTIGATION 35 Completed 35 45 Completed (BH# 48 Terminated) 44 80 79 100

TOWER STAKING 133 10 32 205 27 43 338 75 22.19

TOWER RELEASE 133 5 27 205 27 31 338 58 17.16

EXCAVATION 133 T#66 excavation completed. 1 5 5 205 T#97 completed and 136 is in progress 1 4 6 338 11 3.25

Pre concrete inspection of T#66 L1 & T# 136 Leg 2 & Leg 3 concreted

L3 carried out and not found ok. (Tayyab)

TOWER FOUNDATION 133 T#54 L1 & L3 and T#92 L2 & L4 3 3 205 0.5 4.25 4.5 338 7.5 2.22
formwork fixing in progress

BACKFILLING T#100,134 is in progress 0

TOWER ERECTION 0

STRINGING 0

T#11 Leg 2 & 4 formopening carried out (Asad)

T#54 Leg 2 & 4 formopening carried out (Shahbaz)


,

T#92 Leg 3 formopening carried out (Shahbaz)

Note. Staking inspection from T#15 to T#25 cancelled by CET Site Rep.

747231713.xlsx
Contract No. ADB-301A-2018
Design, Supply, Installation, Testing & Commissioning of 500kV D/C Quad Bundle Transmission Line Nokhar S/s-Lahore North S/S-Lahore HVDC Switching/Convertor Station
(Job# 4185)

DAILY PROGRESS REPORT


December 08, 2021
Contractor: M/s. CET
Section-1 Section-2
Cumulative as of Today
Nokhar S/S-Lahore North S/S Lahore North S/S - HVDC Converter Station
Activity
Qty %
Total Daily Progress This Day This Month To Date Total Daily Progress This Day This Month To Date Grand Total
Completed Completed

1 2 3 4 5 6 7 8 9 10 11 12=2+7 13=6+11 14=(13/12)*100


Validation of Route, Detailed Survey, Preparation of Validation of Route, Detailed Survey, Preparation of
VALIDATION OF ROUTE 44.34 km Plan & Profile Drawings & Structure List Completed 44.34 km 68.07 km Plan & Profile Drawings & Structure List Completed 68.07 km 112.41 km 112.41 km 100

SOIL INVESTIGATION 35 Completed 35 45 Completed (BH# 48 Terminated) 44 80 79 100

TOWER STAKING 133 T#93 to T#97 staked in the field (Daya Ram) 5 10 32 205 27 43 338 75 22.19

TOWER RELEASE 133 5 27 205 T#91 to T#98 released for construction. 8 27 31 338 58 17.16

EXCAVATION 133 T#92 excavation completed. 1 4 4 205 3 5 338 9 2.66

T#11 leg 2 &4 concreted (Asad) T# 100 Leg 1 & Leg 3 formopening

T#54 L2 & L4 concreted (Shahbaz). carried out.

TOWER FOUNDATION 133 1.25 3 3 205 3.75 4 338 7 2.07


T#92 Leg-3 concreted (tayyab)

BACKFILLING 0

TOWER ERECTION 0

STRINGING 0

T#11 Leg 1 & 3 formopening carried out (Asad)

747231713.xlsx
Contract No. ADB-301A-2018
Design, Supply, Installation, Testing & Commissioning of 500kV D/C Quad Bundle Transmission Line Nokhar S/s-Lahore North S/S-Lahore HVDC Switching/Convertor Station
(Job# 4185)

DAILY PROGRESS REPORT


December 07, 2021
Contractor: M/s. CET
Section-1 Section-2
Cumulative as of Today
Nokhar S/S-Lahore North S/S Lahore North S/S - HVDC Converter Station
Activity
Qty %
Total Daily Progress This Day This Month To Date Total Daily Progress This Day This Month To Date Grand Total
Completed Completed

1 2 3 4 5 6 7 8 9 10 11 12=2+7 13=6+11 14=(13/12)*100


Validation of Route, Detailed Survey, Preparation of Validation of Route, Detailed Survey, Preparation of
VALIDATION OF ROUTE 44.34 km Plan & Profile Drawings & Structure List Completed 44.34 km 68.07 km Plan & Profile Drawings & Structure List Completed 68.07 km 112.41 km 112.41 km 100

SOIL INVESTIGATION 35 Completed 35 45 Completed (BH# 48 Terminated) 44 80 79 100

TOWER STAKING 133 5 27 205 T#91 to T#98 carried out (Naqash). 8 27 43 338 70 20.71

T#58 to T#62, T#135 to T#140 and T#168 to T#71


TOWER RELEASE 133 T#64 to T#68 released for construction 5 5 27 205
released for construction 15 19 24 338 51 15.09

EXCAVATION 133 T# 11, 54 completed & T#92 is in progress. 2 3 3 205 T#100, 134 completed. 2 3 5 338 8 2.37

T#11 leg 1 &34 concreted (Waseem) T# 100 Leg 1 & Leg 3 concreted.

T#10 L2 & L4, formopening carried (Daya Ram, Rao Naqash))

TOWER FOUNDATION 133 out (Waseem) 0.5 1.75 1.75 205 T#134 Leg 2 & Leg 4 concreted 1 3.75 4 338 5.75 1.70
T#92 Leg-1 formopening (Tayyab Munawar)

carried out (Shahbaz)

BACKFILLING 0

TOWER ERECTION 0

STRINGING 0

T&P Re-Inspection of MTCC Crew-7 carried out (Shahbaz Riaz). T#100 Leg-2 & 4 formopening carried out.

747231713.xlsx
Contract No. ADB-301A-2018
Design, Supply, Installation, Testing & Commissioning of 500kV D/C Quad Bundle Transmission Line Nokhar S/s-Lahore North S/S-Lahore HVDC Switching/Convertor Station
(Job# 4185)

DAILY PROGRESS REPORT


December 06, 2021
Contractor: M/s. CET
Section-1 Section-2
Cumulative as of Today
Nokhar S/S-Lahore North S/S Lahore North S/S - HVDC Converter Station
Activity
Qty %
Total Daily Progress This Day This Month To Date Total Daily Progress This Day This Month To Date Grand Total
Completed Completed

1 2 3 4 5 6 7 8 9 10 11 12=2+7 13=6+11 14=(13/12)*100


Validation of Route, Detailed Survey, Preparation of Validation of Route, Detailed Survey, Preparation of
VALIDATION OF ROUTE 44.34 km Plan & Profile Drawings & Structure List Completed 44.34 km 68.07 km Plan & Profile Drawings & Structure List Completed 68.07 km 112.41 km 112.41 km 100

SOIL INVESTIGATION 35 Completed 35 45 Completed (BH# 48 Terminated) 44 80 79 100

TOWER STAKING 133 5 27 205 19 35 338 62 18.34

TOWER RELEASE 133 22 205 4 9 338 31 9.17

EXCAVATION 133 T#11 & T#92 is in progress. 1 1 205 1 3 338 4 1.18

T#10 leg 2 & 4 concreted (Waseem) T# 100 Leg 2 & Leg 4 concreted.

T#11, Steel and formwork fixing in (Rao Naqash))

TOWER FOUNDATION 133 progress 0.75 1.25 1.25 205 T#135 Leg 2 & Leg 4 concreted 1 2.75 3 338 4.25 1.26
T#92 Leg-1 concreted (Asad shafiq) (Tayyab Munawar)

BACKFILLING 0

TOWER ERECTION 0

STRINGING 0

T#99 Leg-1 & 3 formopening carried out.

747231713.xlsx
Contract No. ADB-301A-2018
Design, Supply, Installation, Testing & Commissioning of 500kV D/C Quad Bundle Transmission Line Nokhar S/s-Lahore North S/S-Lahore HVDC Switching/Convertor Station
(Job# 4185)

DAILY PROGRESS REPORT


December 05, 2021
Contractor: M/s. CET
Section-1 Section-2
Cumulative as of Today
Nokhar S/S-Lahore North S/S Lahore North S/S - HVDC Converter Station
Activity
Qty %
Total Daily Progress This Day This Month To Date Total Daily Progress This Day This Month To Date Grand Total
Completed Completed

1 2 3 4 5 6 7 8 9 10 11 12=2+7 13=6+11 14=(13/12)*100


Validation of Route, Detailed Survey, Preparation of Validation of Route, Detailed Survey, Preparation of
VALIDATION OF ROUTE 44.34 km Plan & Profile Drawings & Structure List Completed 44.34 km 68.07 km Plan & Profile Drawings & Structure List Completed 68.07 km 112.41 km 112.41 km 100

SOIL INVESTIGATION 35 Completed 35 45 Completed (BH# 48 Terminated) 44 80 79 100

TOWER STAKING 133 5 27 205 19 35 338 62 18.34

TOWER RELEASE 133 22 205 4 9 338 31 9.17

EXCAVATION 133 T#11 & T#92 is in progress. 1 1 205 1 3 338 4 1.18

T#10 leg 1 & 3, Form opening carried T# 99 Leg 1 & Leg 3 concreted.

out. (Daya Ram, Tayyab Munawar)

TOWER FOUNDATION 133 0.5 0.5 205 0.5 1.75 2 338 2.5 0.74

BACKFILLING 0

TOWER ERECTION 0

STRINGING 0

T#10, today's concrete program cancelled by M/s CET Engineers for next day.
,

747231713.xlsx
Contract No. ADB-301A-2018
Design, Supply, Installation, Testing & Commissioning of 500kV D/C Quad Bundle Transmission Line Nokhar S/s-Lahore North S/S-Lahore HVDC Switching/Convertor Station
(Job# 4185)

DAILY PROGRESS REPORT


December 04, 2021
Contractor: M/s. CET
Section-1 Section-2
Cumulative as of Today
Nokhar S/S-Lahore North S/S Lahore North S/S - HVDC Converter Station
Activity
Qty %
Total Daily Progress This Day This Month To Date Total Daily Progress This Day This Month To Date Grand Total
Completed Completed

1 2 3 4 5 6 7 8 9 10 11 12=2+7 13=6+11 14=(13/12)*100


Validation of Route, Detailed Survey, Preparation of Validation of Route, Detailed Survey, Preparation of
VALIDATION OF ROUTE 44.34 km Plan & Profile Drawings & Structure List Completed 44.34 km 68.07 km Plan & Profile Drawings & Structure List Completed 68.07 km 112.41 km 112.41 km 100

SOIL INVESTIGATION 35 Completed 35 45 Completed (BH# 48 Terminated) 44 80 79 100

T#135 to T#140 and T#168 to T# 171 staked in the


TOWER STAKING 133 5 27 205
field (Naqash). 10 19 35 338 62 18.34

TOWER RELEASE 133 22 205 4 9 338 31 9.17

T# 135 Excavation completed.


EXCAVATION 133 T#11 & T#92 is in progress. 1 1 205 1 1 3 338 4 1.18

T#10 Leg 1 & 3 concreted T# 135 Leg 1, Leg 3 concreted

(Waseem, Asad). (Tayyab Munawar)

TOWER FOUNDATION 133 0.5 0.5 0.5 205 T#99 leg 1 & 3 could not carried out 0.5 1.25 1.5 338 2 0.59
due to unavailability of grounding

material.

BACKFILLING 0

TOWER ERECTION 0

STRINGING 0

T&P Inspection of 8th crew icould not passed due to shortage of material / non preparation at store (Daya
Ram).
REMARKS

747231713.xlsx
Contract No. ADB-301A-2018
Design, Supply, Installation, Testing & Commissioning of 500kV D/C Quad Bundle Transmission Line Nokhar S/s-Lahore North S/S-Lahore HVDC Switching/Convertor Station
(Job# 4185)

DAILY PROGRESS REPORT


December 03, 2021
Contractor: M/s. CET
Section-1 Section-2
Cumulative as of Today
Nokhar S/S-Lahore North S/S Lahore North S/S - HVDC Converter Station
Activity
Qty %
Total Daily Progress This Day This Month To Date Total Daily Progress This Day This Month To Date Grand Total
Completed Completed

1 2 3 4 5 6 7 8 9 10 11 12=2+7 13=6+11 14=(13/12)*100


Validation of Route, Detailed Survey, Preparation of Validation of Route, Detailed Survey, Preparation of
VALIDATION OF ROUTE 44.34 km Plan & Profile Drawings & Structure List Completed 44.34 km 68.07 km Plan & Profile Drawings & Structure List Completed 68.07 km 112.41 km 112.41 km 100

SOIL INVESTIGATION 35 Completed 35 45 Completed (BH# 48 Terminated) 44 80 79 100

TOWER STAKING 133 T#64 to T# 68 staked in the field (Asad Shafiq) 5 5 27 205 T#58 to T#62 staked in the field (Asad Shafiq). 5 9 25 338 52 15.38

TOWER RELEASE 133 22 205 T#101 to 104 released for construction 4 4 9 338 31 9.17

T#100, 135 Excavation is in progress.


EXCAVATION 133 T#11 & T#92 is in progress. 1 1 205 2 338 3 0.89

Steel and Form work fixing at T#92

is in progress T# 134 Leg 1, Leg 3 & T# 99 leg 4

TOWER FOUNDATION 133 Concreting of T#92 leg-1 could not 0 0 0 205 formopening carried out. 0.75 1 338 1 0.30
carried out due to failure of coarse

aggregate in gradation (Shahbaz, Waseem)

BACKFILLING 0

TOWER ERECTION 0

STRINGING 0

02 nos.water sample near to T#66, 68 (owner Khan Muslman) for MTCC Crew carried out.
REMARKS

CM visited T#92

747231713.xlsx
Contract No. ADB-301A-2018
Design, Supply, Installation, Testing & Commissioning of 500kV D/C Quad Bundle Transmission Line Nokhar S/s-Lahore North S/S-Lahore HVDC Switching/Convertor Station
(Job# 4185)

DAILY PROGRESS REPORT


December 02, 2021
Contractor: M/s. CET
Section-1 Section-2
Cumulative as of Today
Nokhar S/S-Lahore North S/S Lahore North S/S - HVDC Converter Station
Activity
Qty %
Total Daily Progress This Day This Month To Date Total Daily Progress This Day This Month To Date Grand Total
Completed Completed

1 2 3 4 5 6 7 8 9 10 11 12=2+7 13=6+11 14=(13/12)*100


Validation of Route, Detailed Survey, Preparation of Validation of Route, Detailed Survey, Preparation of
VALIDATION OF ROUTE 44.34 km Plan & Profile Drawings & Structure List Completed 44.34 km 68.07 km Plan & Profile Drawings & Structure List Completed 68.07 km 112.41 km 112.41 km 100

SOIL INVESTIGATION 35 Completed 35 45 Completed (BH# 48 Terminated) 44 80 79 100

TOWER STAKING 133 22 205 T#101 to T#104 staked in the field Naqash). 4 4 20 338 42 12.43

TOWER RELEASE 133 22 205 5 338 27 7.99

T#100 Excavation is in progress.


EXCAVATION 133 T#11 & T#92 is in progress. 1 1 205 2 338 3 0.89

Steel and Form work fixing at T#10

and T#92 is in progress T# 134 Leg 1 & Leg 3 concreted.

TOWER FOUNDATION 133 (Asad,Waseem) 0 0 0 205 (Shahbaz, Tayyab) 0.5 0.75 1 338 1 0.30

BACKFILLING 0

TOWER ERECTION 0

STRINGING 0

Note. Due to non functioning of RTK Receiver, staking of towers started late.
REMARKS

CM Nespak visited T#134 (Section-II)

747231713.xlsx
Contract No. ADB-301A-2018
Design, Supply, Installation, Testing & Commissioning of 500kV D/C Quad Bundle Transmission Line Nokhar S/s-Lahore North S/S-Lahore HVDC Switching/Convertor Station
(Job# 4185)

DAILY PROGRESS REPORT


December 01, 2021
Contractor: M/s. CET
Section-1 Section-2
Cumulative as of Today
Nokhar S/S-Lahore North S/S Lahore North S/S - HVDC Converter Station
Activity
Qty %
Total Daily Progress This Day This Month To Date Total Daily Progress This Day This Month To Date Grand Total
Completed Completed

1 2 3 4 5 6 7 8 9 10 11 12=2+7 13=6+11 14=(13/12)*100


Validation of Route, Detailed Survey, Preparation of Validation of Route, Detailed Survey, Preparation of
VALIDATION OF ROUTE 44.34 km Plan & Profile Drawings & Structure List Completed 44.34 km 68.07 km Plan & Profile Drawings & Structure List Completed 68.07 km 112.41 km 112.41 km 100

SOIL INVESTIGATION 35 Completed 35 45 Completed (BH# 48 Terminated) 44 80 79 100

TOWER STAKING 133 22 205 16 338 38 11.24

TOWER RELEASE 133 22 205 5 338 27 7.99

T#99 & 134 Excavation completed.


EXCAVATION 133 T#10 completed & T#92 is in progress. 1 1 1 205 2 338 3 0.89

Steel and Form work fixing at T#10 T#99 Leg D concreted (Naqash).

and T#92 is in progress T# 134 Leg A preparation for

TOWER FOUNDATION 133 0 0 0 205 concrete completed. 0.25 0.25 0.5 338 0.5 0.15
(Shahbaz, Tayyab)

BACKFILLING 0

TOWER ERECTION 0

STRINGING 0

T&P Inspection of Conventional foundation crew-6 (Astola Crew)and Crew-7 carried out (Asad Shafiq, Waseem 01 no. water sample (for Norang Crew) near to T#168 (owner Mushtaq Ahmed) collected for testing (Daya
Ahmed) Ram).

CM Nespak visited T#54 and T#10 (Section-I)


REMARKS

SDO NTDC HVDC visited T#99 and T# 134