Advance 244

Chennai Metro Phase 2 Corridor 3


Project: S-01327A Page 1/3

Start End
on: 10.10.2023 at: 04:50:54 on: 11.10.2023 at: 00:18:13

Time:
Advance: 01:16:45 Ring building: 01:04:01 Stop: 17:06:34 Total: 19:27:19

Cutting wheel:
Average value Minimum Maximum
Speed [rpm] 1.96 0.00 2.29 Rotation left 56.3 [%]
Torque [MNm] 2.323 0.000 3.870 Rotation right 43.7 [%]
Working pressure [bar] 119 1 198

Advance:
Average value [kN] Average value [bar] Minimum [bar] Maximum [bar]
2,029 89 58 110
3,418 112 3 171
5,911 155 62 185
2,455 81 31 105

Force [kN]

Start [mm] End [mm]


524 2,015
530 2,031
506 2,006
509 1,995

Delta [mm] Delta [mm]


Average value Average value
Force [kN] 13,811 Hitch [kN] 54
Speed [mm/min] 18.7 Roll [mm/m] 0.8
Penetration [mm/rev] -1 9.7 Longitudinal tilt [mm/m] -17.1
Specific energy [MJ/m³] 43 Pump [bar] 170

Cutting wheel displacement:


Average value [kN] Average value [bar] Minimum [bar] Maximum [bar]
961 113 46 228
1,433 158 71 265
1,610 170 88 256

Force [kN]

Start [mm] End [mm]


801 804
813 813
798 798

Delta [mm] Delta [mm]


Contact force [kN] 4,003
Tilt moment [kNm] 763

Torque support:
Start [mm] End [mm]
Position [mm] Position [mm] Position [mm] Position [mm]
107 109 107 108
Advance 244
Chennai Metro Phase 2 Corridor 3
Project: S-01327A Page 2/3

Start End
on: 10.10.2023 at: 04:50:54 on: 11.10.2023 at: 00:18:13

Grout injection:
Average value [bar] Minimum [bar] Maximum [bar] A [l] B [l]
2.1 0.0 22.4 1,901 103
0.0 0.0 0.0 0 0
2.5 0.1 25.0 1,728 108
1.6 0.0 8.2 2,152 156

5,781 366
Pressure [bar]
Historical
Advance 235 236 237 238 239 240 241 242 243
Volume A [l] 5,074 5,377 4,945 5,241 4,073 4,062 5,180 5,180 4,931
Volume B [l] 448 450 436 436 246 362 399 404 404
11.3 : 1 11.9 : 1 11.3 : 1 12.0 : 1 16.6 : 1 11.2 : 1 13.0 : 1 12.8 : 1 12.2 : 1
Mixing proportion
8.1 [%] 7.7 [%] 8.1 [%] 7.7 [%] 5.7 [%] 8.2 [%] 7.2 [%] 7.2 [%] 7.6 [%]

Earth pressure:
Average value [bar] Minimum [bar] Maximum [bar]

1.73 1.44 2.09


1.91 1.65 2.27
4.86 3.61 5.97
1.74 1.40 2.10
2.54 1.75 3.39
1.70 1.33 2.05

Pressure [bar]

Screw conveyor:
Average value Average value
Speed [rpm] 2.7 Earth pressure front [bar] 0.2
Torque [kNm] 19 Earth pressure center [bar] 1.1
Working pressure [bar] 49 Earth pressure rear [bar] 0.0

Material transport:
[ t/ h ] [t] Advance 235 236 237 238 239 240 241 242 243
Belt scale 90 108 [t] 0 109 106 134 98 107 113 113 107
Back-up belt conveyor current [%] 32

Tailskin articulation:
Start [mm] End [mm]
52 58
63 71
48 55
30 34

Delta [mm] Delta [mm]


Average value
Tensile force [kN] 1,870
Pressure [bar] 66

Lubrication:
[g] [g]
Seal outside FA1-8 1,867 Erector pinion 1
Screw conveyor F1-2 772 Erector bearing 0
Bearing ball F3 204 Erector bearing 0
Rotary coupling FD1 520
EP2 [kg] 4
Labyrinth seal CA1-4 8,539 CONDAT [kg] 9
Advance 244
Chennai Metro Phase 2 Corridor 3
Project: S-01327A Page 3/3

Start End
on: 10.10.2023 at: 04:50:54 on: 11.10.2023 at: 00:18:13

Foam installation:
Minimum [bar] Flow air [l/min] Volume liquid [l]
Average value [bar] Maximum [bar] Flow liquid [l/min] FER

Line 01 2.70 1.80 5.75 227 17.4 1,532 5.4


Line 02 1.81 0.16 3.34 226 17.3 1,523 5.3
Line 03 2.68 1.39 4.20 226 16.9 1,499 5.3
Line 04 3.76 0.63 4.60 229 17.1 1,503 5.5

Foam total [%] 100 [ l/min ] [l]


Water total [l] 10,157 Bentonite 0 5,343
Polymer pump [l] 194 Bentonite pump current [%] 0
Average value [bar] [ l/min ] [l]
Polymer pump 0.0 0 1

Temperature:
Average value [°C]
Hydraulic tank 47
Gearbox oil 45
Leakage oil drive 33

Gearbox oil:
Average value [bar] Minimum [bar] Maximum [bar]
Pump 18.3 15.2 23.8

Gas measuring:
Average value Minimum Maximum
Methane gas (CH4) [% LEL] 6.8 6.6 7.2
Methane gas (CH4) [% LEL] -0.6 -0.7 -0.6
Carbon monoxide (CO) [ppm] 0 0 5
Oxygen (O2) [%] 20.4 20.3 20.5
Carbon dioxide (CO2) [Vol%] 0.002 0.002 0.002

Ventilation [m³/s] 5
Ventilation [m³/s] 1

Tailskin sealing compound:

Front Strokes Rear Strokes


01 76 01 74
02 74 02 74
03 74 03 74
04 74 04 74
05 72 05 74
06 74 06 76

444 446

Pump [kg]: 171


Average value [bar] 4