Professional Documents
Culture Documents
TABLE OF CONTENTS
11.0 PROCEDURE
___________________________________________________________________________________________________________
_
CASTLE INFRASTRUCTURE
CONTRACTING W.L.L MANATEQ JAMES CUBITT
The purpose of this method of statement is to ensure that works are done according to
the approved shop drawing, standards and contract specifications
2.0 SCOPE
The method of statement covers the work to be done, equipment and materials to use,
sampling and testing to be carried out for Concrete Works at Birkat Al Awamer Logistic
Park
3.0 REFERENCES
4.0 RESPONSIBILITIES
1. Project Manager is responsible for the total execution of work with his team to ensure all
activities in his scope are carried out in compliance with approved shop drawings and
specifications.
2. Project Engineer is directly supervises site team and has the full control over labour and
equipment and to obtain all permits and approvals.
3. QA/QC Engineer is responsible to control the site quality during the work progress.
4. Safety Officer is responsible for safety related matters during the work progress and
strictly complies with the approved HSE plan.
5. Surveyor is responsible to establish benchmarks, contours at both the location of dumping
and loading. He is responsible for preparation of quantities every monthly or bi weekly.
6. Concrete Technician is monitoring concrete slump and temperature, preparation of
concrete pour record, ensures that the concrete delivery tickets corresponds to the mix
design, preparation of concrete cubes and stack properly. Reports to QC Engineer in case
of non-conformance with concrete.
7. Steel Fixers responsibility is to execute the rebar works as per the
instructions from supervisor.
8. Carpenters responsibility is to make shuttering and form works as per the instructions from
supervisor.
6.0 EQUIPMENT
Equipment’s to be used at the job site shall include, but not limited to the following:
7.0 MATERIALS
All site staff shall wear the appropriate Personal Protective Equipment (PPE) and, as a
minimum, all staff will wear a hard hat, hi-visibility vest, and safety boots/shoes.
Additional PPE, such as coveralls, safety harness, safety gloves, etc. will be provided if
specifically required.
Before the commencement of the activities, all necessary permits to work will be
obtained.
Safety induction for all works shall be confirmed and internal permits shall be ensured
prior to starting any site activity.
Mitigation measures identified in the JSA will be in place, prior to commencement with
works on site.
Safety toolbox talks will be carried at all work locations, as per approved HSE Plan.
Any access to the trench deeper more than 1.2 meters shall be considered a confined
space and confined space procedure shall be applied and followed and all involved
people shall attend confined space training and hold a valid confined space certificate.
___________________________________________________________________________________________________________
_
CASTLE INFRASTRUCTURE
CONTRACTING W.L.L MANATEQ JAMES CUBITT
___________________________________________________________________________________________________________
_
CASTLE INFRASTRUCTURE
CONTRACTING W.L.L MANATEQ JAMES CUBITT
Hard Hat
Hi-visibility vest
Safety Glass
Safety Shoes
Safety gloves
Cover All / Overall
Dust Mask
Other PPE as required
11.0 PROCEDURE:-
11.2 Formworks
Formwork erected and installed will be rigid, water tight and dimensionally
stable.
Formworks release agent material will be applied prior casting to ensure good
surfaced finish of concrete.
Before placing concrete, all dirt, debris and other foreign matter shall be
removed.
___________________________________________________________________________________________________________
_
CASTLE INFRASTRUCTURE
CONTRACTING W.L.L MANATEQ JAMES CUBITT
___________________________________________________________________________________________________________
_
CASTLE INFRASTRUCTURE
CONTRACTING W.L.L MANATEQ JAMES CUBITT
___________________________________________________________________________________________________________
_