METHOD STATEMENT FOR

CIVIL & MEP WORKS FOR


LANDING GEAR FACILITY

MARCH 25, 2023

REF: VR/CIVIL-MEP/MS-001

METHOD STATEMENT: VR/CIVIL-MEP/MS-001 Page no. 1

TITLE METHOD STATEMENT FOR CIVIL & MEP WORKS FOR LANDING GEAR FACILITY
CONTENTS

1 SCOPE....................................................................................................................................................4
2 DESCRIPTION......................................................................................................................................4
2.1 LIMITATIONS................................................................................................................................4
3 REFERENCES.......................................................................................................................................4
4 HEALTH AND SAFETY HAZARDS...................................................................................................4
4.1 HEALTH AND SAFETY PROVISIONS.......................................................................................4
5 RESPONSIBILITIES.............................................................................................................................5
6 METHOD EMPLOYED / PROCEDURE..............................................................................................7
6.1 BLOCKWALL WORKS.................................................................................................................7
6.1.1 Material Requirements..............................................................................................................7
6.1.2 Equipment Requirements..........................................................................................................7
6.1.3 Procedure..................................................................................................................................7
6.2 DRYWALL WORKS....................................................................................................................10
6.3 TOILETRY WORKS.....................................................................................................................11
6.3.1 Material Requirements............................................................................................................11
6.3.2 Steps of Works........................................................................................................................11
6.3.2.1 Preliminary Preparation......................................................................................................11
6.3.2.2 Marketting, Lay-Out And Installation................................................................................12
6.4 GYPSUM CEILING TILING........................................................................................................12
6.4.1 Material Requirements............................................................................................................12
6.4.2 Equipment Requirements........................................................................................................12
6.4.3 Procedure................................................................................................................................13
6.5 PLASTERING...............................................................................................................................14
6.6 FLOOR & WALL TILING WORKS............................................................................................15
6.6.1 Material Requirements............................................................................................................15
6.6.2 Equipment Requirements........................................................................................................15
6.7 CARPET TILING..........................................................................................................................17

METHOD STATEMENT: VR/CIVIL-MEP/MS-001 Page no. 2

TITLE METHOD STATEMENT FOR CIVIL & MEP WORKS FOR LANDING GEAR FACILITY
Prepared By: Reviewed By: Approved By:
Signature JM

Name Jovin Mathew

Designation QA
CLIENT/CONSULTANT COMMENTS:
☐ Code A – Approved ☐ Code C – Rejected (Revise & Resubmit)
☐ Code B – Approved with Comments ☐ Code D – For Information
Remarks:

METHOD STATEMENT: VR/CIVIL-MEP/MS-001 Page no. 3

TITLE METHOD STATEMENT FOR CIVIL & MEP WORKS FOR LANDING GEAR FACILITY
1 SCOPE
The method statement describes the step-by-step procedure for Civil engineering works to be done on Landing Gear
Facility.

2 DESCRIPTION
This method statement describes the works involving the Civil engineering areas.
2.1 LIMITATIONS

● Any work not provided in the MS is out of scope


● The COSHH and MSDS shall apply for paint.
● All work shall be carried out as directed by a supervising officer or a qualified specialist.
● This method statement is only a guide and shall be adapted to suit local products, standards, legislation, or
other local requirements.

3 REFERENCES
To ensure the correct application of paint, please refer to the following documents of each product component:
● MSDS (Material Safety Data Sheet)
● COSHH (Control of Substances Hazardous to Health)

4 HEALTH AND SAFETY HAZARDS


Specific safety measures have to be followed as applicable. All safety measures are covered separately in the Risk
Assessment.
4.1 HEALTH AND SAFETY PROVISIONS

 All the safe practices will be adopted during the tiling work construction.
 Special work permits, wherever required, shall be obtained before commencing work.
 All necessary personal protective equipment PPE must be used.
 Proper access for the labor and equipment shall be provided for the works.
 All machinery shall be checked for maintenance records.
 The site shall be cleaned from all the debris, steel waste, nails etc.
 Toolbox talks to be conducted prior to commencement of works.
 Close supervision on safety requirement shall be provided.

METHOD STATEMENT: VR/CIVIL-MEP/MS-001 Page no. 4

TITLE METHOD STATEMENT FOR CIVIL & MEP WORKS FOR LANDING GEAR FACILITY
5 RESPONSIBILITIES
Project Manager
• Project Manager shall be responsible for overall project execution, he will coordinate with client and head
office, progress monitoring, attending review meeting, resource management, overall, he will be responsible for timely
completion of project in accordance to all contractual requirements.
• The tiling works activities are carried out according to specifications and drawings.
• Work progress is carried out according to the planned program and all the equipment required to execute the
works are available as per the project planning and are in good condition.
• Coordination with the Consultant, Project Engineer, Site Engineer, Safety Engineer and Subcontractors for
the safe and proper execution of the work.
• Specific attention is paid to all safety measures and quality control in coordination with Safety Engineer and
QC Engineer and in line with HSE plan and Quality plan.
Project Engineer should ensure:
• The tiling works activities are carried out according to the specifications, drawings and approved method
statement.
• Provision of all necessary information and distribution of responsibilities to his construction team in
consultation with construction manager.
• The work progress is monitored in accordance with the required program and reports the same to the
Construction Manager.
• Coordination with the Safety Engineer to ensure that the works are carried out in a safe working atmosphere.
• Coordination with the QC Engineer for tests to be carried out and initiate RFI for the inspection for the
finished works.
• The implementation of any request that might be raised by the Consultant.
• Efficient daily progress has been obtained from all the equipment and manpower engaged in the work and
check the same against the daily report received from the site engineer.
• The passage of all the revised information to the Site Engineer and ensure that it’s being carried out properly.
• Coordination with the surveyor and plan the survey works in advance as per the work sequence.
• Allocation of manpower, materials and equipments in consultation with construction manager also monitoring
their timely supply at construction location.
Site Engineer should ensure:

METHOD STATEMENT: VR/CIVIL-MEP/MS-001 Page no. 5

TITLE METHOD STATEMENT FOR CIVIL & MEP WORKS FOR LANDING GEAR FACILITY
• Preparing daily progress report / site report.
• Engagement of manpower and machineries in work as required.
• Verifying line, level etc.
• Supervising every individual activity.
• Initiating RFI to the Project Engineer and other necessary inspecting records.
Surveyor:
The surveyor shall be responsible for checking levels, alignment, etc.
QA/QC Engineer should ensure:
• The carrying out of the works as per the specifications and the related quality procedures.
• Inspection of the completed works and requesting for the Consultant’s approval.
• Maintenance of complete inspection and test records for any further reference.
• Raising and closing internal NCR if any.
• Documentation in accordance to approved PQP / ITP.
Safety Officer should ensure:
• The implementation of all safety measures in accordance with the HSE plan and that the whole work force is
aware of its proper implementation.
• The implementation of safety measures is adequate to maintain a safe working environment on the site and
supervising whether each worker is using necessary PPE.
• Inspection of all the site activities and training personnel in accident prevention and its proper reporting to the
Project Manager and the Consultant.
• The site is maintained in a clean and tidy manner.
Forman should ensure:
• The carrying out of the work and the proper distribution of all the available resources in coordination with the
Site Engineering on a daily basis.
• Daily reports of the works are achieved and coordinated the future planning with the site Engineer.
• Incorporate all the QC and Safety requirements as requested by the concerned Engineer.
• Meeting with any type of unforeseen incident or requirement and reporting the same to the Site Engineer
immediately.

METHOD STATEMENT: VR/CIVIL-MEP/MS-001 Page no. 6

TITLE METHOD STATEMENT FOR CIVIL & MEP WORKS FOR LANDING GEAR FACILITY
6 METHOD EMPLOYED / PROCEDURE
6.1 BLOCKWALL WORKS

6.1.1 Material Requirements


 Solid and hollow blocks are various size
 Sand (3/16 washed black sand)
 Spacers, steel, framework and supports for steel reinforcement bars
 Binding wire
 Sweet water
 Polythene sheets
 Ready mix concrete
 Form releasing agent
 Scaffoldings
 Wooden planks
 Cement
 Dam proof materials
 Approved Grout material
6.1.2 Equipment Requirements
 Mason’s tools
 Expansion joints
 Polysulphide sealant
 Concrete transit mixer
 Carpentry tools
 Steel fixers tools
 Surveying Instruments
 Light projectors
 Water tank and pumps
 Stand-by generator

METHOD STATEMENT: VR/CIVIL-MEP/MS-001 Page no. 7

TITLE METHOD STATEMENT FOR CIVIL & MEP WORKS FOR LANDING GEAR FACILITY
6.1.3 Procedure
Preparation
 Ensure all permissions and consents are obtained.
 Ensure approval of this method statement, all materials submittal in relation to this activity, all related
drawings are done prior to work.
 Prepare any necessary toolbox talks.
 Discuss the method statement and related responsibilities with the site team.
 Make sure all related materials are procured and expected deliveries are appropriate.
 Ensure an efficient and safe storage area for the materials to be used.
 Ensure the availability of all safety equipments is required.
 Coordinate with the mechanical, electrical, and plumbing sub-contractor.
Pre-Construction
 Survey the work area for any pre-existing safety hazards and render harmless if possible.
 Ensure relevant toolbox talks are given to all operatives involved in the works.
 Ensure work will be carried out in accordance with the program.
 All necessary required equipment, tools, and materials shall be arranged well in advance before starting
works.
 Ensure a sufficient number of trained labourers for the job.
 Ensure all underground sources are in place.
 Ensure to store all approved blocks on raised platforms and properly cover it to protect it from moisture.
 Ensure to soak all ceramic wall blocks in water for 24 hours before usage. Solid & hollow blocks shall be
soaked in water before fixing (as and when applicable depending on the type of solid & hollow blocks).
 Ensure all blocks to be used are as per the size required and free from any defaults. Blocks type, size,
pattern and colour shall be as per the Consultant’s/Client’s selection. Blocks shall be as shown on the
schedule of finishes and as selected by the Consultant/Client.
Construction

Block works
 Raise a site inspection with the consultant prior to laying blocks for the toilet rooms.

METHOD STATEMENT: VR/CIVIL-MEP/MS-001 Page no. 8

TITLE METHOD STATEMENT FOR CIVIL & MEP WORKS FOR LANDING GEAR FACILITY
 Layout marked clearly on the floor, including doors, windows, and other building services to ensure correct
bonding, minimum cutting tolerance, and the average thickness of the vertical wall and horizontal joints.
 Spread the mortar on the Damp proofed ground where the masonry block wall is to be erected.
 Reference blocks (solid) shall be laid to obtain the line and level of the block work to the approval of the
consultant.
 Check the first line for plumb and alignment before proceeding with the second row of masonry blocks.
 The joints of block work shall be a minimum of 10 to a maximum of 20 mm in thickness.
 In a day’s work, the maximum block work height laid shall be 1200 mm (1.2m). The block work shall be
carried out in a uniform manner and shall be plumbed vertically.
Control joints shall be provided in the form of reinforced concrete columns at mid-span in all walls longer than
6m, if applicable. Reinforced concrete bond beams will be provided in all walls more than 3.5m high at mid-
wall height or at lintel level.
 Walls temporarily left at different levels shall not be stepped more than 1 m in height. Any wall left at
different levels must be raked back.
 The surface of the walls and partitions prepared for rendering shall have the joints raked out to a depth of
20mm from the face of the wall to form a key to the plaster.
 Install expanded steel mesh joint reinforcement in every third layer.
 Partitions shall be bonded to main walls by toothing at every third course to a depth of not less than
100mm.
 Cavity walls shall be built by raising both skins of the block work at a similar rate and incorporating
approved wall ties at 900 mm horizontal centers and 600 mm vertical centers spaced diagonally. Cavities
shall be kept clean of mortar droppings.
 The topmost courses of walls and partitions terminating against soffits of beams and slabs shall be built
with solid blocks of appropriate size leaving a gap of 10 to 15 mm, which shall be packed with
mortar/bitumen impregnated building board strips for normal walls.
 Fire rated concrete block wall construction shall be built in accordance with the relevant section of the
Schedule of Architectural Finishes.
 All door and window openings shall have solid block around their periphery.
 Curing by water to the faces of the block work shall be applied for 3 days.

METHOD STATEMENT: VR/CIVIL-MEP/MS-001 Page no. 9

TITLE METHOD STATEMENT FOR CIVIL & MEP WORKS FOR LANDING GEAR FACILITY
 Wall ties between steel columns should be done as follow:
For Side Walls
Lay down the first line of Masonry blocks in the open area between the steel columns from the interior side of
the building in respect to the steel columns.
 Ensure to leave the area in front of the steel columns empty of blocks to erect the stiffener column at a later
stage.
 When the sub-level of the concrete lintel has been reached, install a flexible sheet in front of the steel
column, overlap reinforcement steel bars with the existing vertical dowels according to specifications, erect
a one-side shutter for the stiffener column, and pour the concrete in the column according to specifications
and construction drawings. Allow for curing as per specifications.
For End Walls
 Ensure to weld a U shape steel reinforcement bar to the steel column and overlap it with the reinforcement
of the lentils if any.

6.2 DRYWALL WORKS

 Drywalls and accessories should be brought to the job site soon prior to installation to minimize the chance
of damage.
 Gypsum sheets should be handled and stored in an upright position, with special attention paid to
protecting the edges from harm.
 Drywalls should be stacked in a damp-free enclosed location in neat, balanced stacks off the ground/floor.
This will keep the board edges and surfaces from slipping and deteriorating.
 If kept in an open area the gypsum sheets should be wrapped with plastic or tarpaulin to protect them from
direct sunlight.
 The building walls should be properly checked prior to the gypsum board installation to ensure that the
framing is plumb, level, and square and that the other trades have completed their ‘rough-ins.
 The stud and batten layout follow the lining spacing requirements listed in the frame spacing as shown in
the approved drawings. The plasterboard will be finished to the recommended level of finish once the
installation is complete.

METHOD STATEMENT: VR/CIVIL-MEP/MS-001 Page no. 10

TITLE METHOD STATEMENT FOR CIVIL & MEP WORKS FOR LANDING GEAR FACILITY
 Check that the steel framing has been constructed and erected as per the manufacturer’s specifications
and drawings before applying plasterboard to it. The steel frame’s contact surfaces are clean, dry, and free
of contamination such as oil, grease, and dirt.
 Steel furring channels are attached to the underside of joists at right angles with clips or fasteners.
 Anchor clips are used to secure steel furring to a concrete slab ceiling during false ceiling execution.
Furring channels should be spaced according to the thickness of the sheet specified in the Frame Spacing.
 Plan the installation carefully. Sheets should be laid out in a way that ensures maximum coverage while
minimizing butt joints and waste. Plasterboard is typically installed horizontally in residential construction
and is critical if a Level of type finish of 3, 4, or 5 is desired (or as per project specifications). If the sheeting
is to cover the entire wall and wall partition, it can be fixed vertically.
 Install metal wall framing in strict accordance with manufacturer’s instructions. Determine and mark the wall
position and make allowance for openings. Determine and mark the wall position and make allowance for
openings. Fix track channel along centre line of floor and ceiling at 600mm centers with suitable fixings.
 Cut stud to a neat fit into the height of the required wall height. Locate the first stud into the track channel,
twist it into position and fix it to the abutting wall at 600mm centres. Locate the next stud at 600mm centres
to a friction fit within the track channel sections.
 In splicing the studs due to height requirement, two stud members are boxed with minimum overlapping of
600mm. In case of designed partition height higher than the plasterboard length, additional track channel
fixed horizontally to support an infill panel is required.
6.3 TOILETRY WORKS

6.3.1 Material Requirements


 Panel Height,
 Beams and Post
 Door
 Door Handle, Shields
 U-profile with hole, plug, washer and counter fit screws
 Head rail, end cap and anti-theft bolt
 Electric drill and screw driverlid and hollow blocks are various size

METHOD STATEMENT: VR/CIVIL-MEP/MS-001 Page no. 11

TITLE METHOD STATEMENT FOR CIVIL & MEP WORKS FOR LANDING GEAR FACILITY
6.3.2 Steps of Works
6.3.2.1 Preliminary Preparation
 Work is to be performed by experienced workers under the direction of a qualified supervisor who is fully
aware of the project requirements. Prior to commence the work make sure that all tools are prepared by
workers and ready for usage. All electric power tools that are to be use for the work should have been
properly checked and colour coded and inspected by HSE department.

6.3.2.2 Marketting, Lay-Out And Installation


 Mark the center line for the U-profiles. Clearance from the floor to the bottom of U-profile +/- 160mm. Copy
the height of the U-profiles on the wall. Mark the holes from the U-profiles. Drill holes and fix the U-profile to
the wall with plugs, washer and screw.
 Drill holes (+/- 28mm) for the legs according to the drawing. Put the panels into the top of the profiles. Put
the front panels onto the partition panels. Adjust the head rail to the front length and fix with screws 4.8 x
50. Apply pre-drill using 4.30mm diameter. Put the plastic end cap on the end of the head rail.
 After putting the doors in place, level all panels so the doors are closing properly.
 Fix the walls with the screws of 3.5mm diameter x 11. Apply pre-drill using the 3.1mm diameter.
 Mix the component A with Component B and pour it into the hole for the legs. Fill until the floor levels and
after 24 hours later, checked if it is properly cured then removed the temporary support.
 Mount the lower (plastic) shield with screws 3.5 x 16. Apply pre-drill with 3.1mm diameter. Mount the upper
(aluminium) shield (with a click) and put the door handles together.
 Mount the anti-theft bolt into the hinge.

6.4 GYPSUM CEILING TILING

6.4.1 Material Requirements


 60x60 gypsum boards
 Thick calcium silicate tiles
 Suspension of framing elements

METHOD STATEMENT: VR/CIVIL-MEP/MS-001 Page no. 12

TITLE METHOD STATEMENT FOR CIVIL & MEP WORKS FOR LANDING GEAR FACILITY
6.4.2 Equipment Requirements
 Drills with bits for concrete and metal
 Screw gun – Power tool that drives all types of gypsum board screws through gypsum board and into
framing or substrate
 Chalk line
 Sprit level
 Metal cutting scissors
 Measuring tape – A steel retractable measuring tape, usually 25 feet in length.
 Gypsum board T-square –Square edge for measuring and cutting gypsum board to length and for cutting
out holes for square outlet boxes and other openings.
 Utility knife – the Standard cutting tool with replaceable/reversible blades for scoring and cutting gypsum
board.
 Hammer – Drives nails through gypsum board into wood framing.
6.4.3 Procedure

 Setting out and marking will be done based on the ceiling height of various areas. The height shall be
marked based on the benchmark provided by main contractor level and will be transferred on all the
corners and chalk lines will be marked.
 The wall angles will be fixed along the marked ceiling line depending on the substrate at 600mm to center
spacing. Before fixing the wall angle the substrate has to receive necessary finishes as per the finish
schedule.
 Fixing of hangers and the position of the hangers will be marked on the soffit of the slab, which has to be
reviewed by main contractor site engineer upon receipt of MEP clearance hangers shall be fixed at a
spacing of 1200mm centres on both the directions where MEP services are clashing with fixing hangers,
additional supplies shall be provided by agreeing with the main contractor on site.
 . Framing members such as Main Runners and Furring Channels of 0.55mm thick shall be placed as
spacing of 1200mm and entries respectively. Heavy recessed fixtures should be independent of the ceiling
framing stems.

METHOD STATEMENT: VR/CIVIL-MEP/MS-001 Page no. 13

TITLE METHOD STATEMENT FOR CIVIL & MEP WORKS FOR LANDING GEAR FACILITY
 Upon completion of framework, respective areas shall be offered for main contractor and consultant
inspection. Void closures shall be started by gypsum board installation. Gypsum boards of specified type
shall be applied to the framing using gypsum screws at 200mm. For tile ceiling, the void closure will be
done by placing calcium silicate tiles on the complete grid work.
 Taping and Jointing for Gypsum Board Ceilings

6.5 PLASTERING

 All necessary required equipment’s, tools, materials, i.e., cement, black sand, sweet water, scaffoldings,
wooden planks…etc shall be arranged well in advance before starting plaster works.
 Ensure the mixed plaster is as per specifications.
 Ensure a sufficient number of trained labourers for the job.
 Coordinate with Mechanical and Electrical works to ensure that all services have been installed.
 Ensure all irregularities in the surface to be plastered must be filled with mortar without lime, twenty-four
hours before plastering is commenced.
 Ensure that the areas on which plaster is to be laid out are clean and free of dust, loose mortar, formwork
oi,l and other contaminations, which may affect the adhesion. The concrete surface shall be made smooth
and if any repair is necessary, it shall be done using approved repairing materials. Projecting mortar and
concrete fins and runs shall be removed. All the areas to be plastered shall be sprayed with clean water
before the application of the rush coat.
 All wall chasings by the concerned sub-contractors shall be closed by using cement sand mortar (1:4 Mix)
and metal lath strips before the commencement of plaster works.
 Metal lath strips shall be further used at all junctions of concrete and block work.
Construction
 A rush coat 1 to 6mm thick, shall be applied on the entire surface using cement sand mortar in the
proportion of 1:4 and cured for one day or cement, water, and bonding agent in specified proportion.
 Plaster level spots to the required thickness shall be fixed and approved by the consultant prior to starting
of plaster works.

METHOD STATEMENT: VR/CIVIL-MEP/MS-001 Page no. 14

TITLE METHOD STATEMENT FOR CIVIL & MEP WORKS FOR LANDING GEAR FACILITY
 Necessary and sufficient quantity of cement sand mortar in the proportion of 1:4 for plaster shall be dry
mixed at least three times thoroughly prior to mixing with the correct amount of water and then the mix
should be turned over again until such time as the mass is uniform in color and homogenous.
 Plastering and rendering shall be mixed in mechanical mixing machine.
 The Plaster shall be completely used within thirty minutes of mixing and hardened plaster shall not be
remixed and reused.
 The area under consideration shall be thoroughly wetted and then applied with the plaster mortar in line,
level and plumb. Render shall be floated to a true, even surface. If the surface is to be a smooth finish, then
it shall be further troweled in a manner which forces the sand particles down into the render. All render
surfaces shall be free from rough areas, trowel marks, or other blemishes.
 The prepared mortar shall be applied in coats, compacted and finished to get a leveled, flat surface.
 Where wall corners are found, install a wire mesh with corner bead to it. Apply plaster and finish the wall
corner accordingly.
 Where movement joints in walls are found, install plaster stop beads at both ends of the joint, apply plaster,
and finish the surface accordingly. Fill with sealant in between the plaster beads.
 Curing with sweet water on all plastered surfaces shall be undertaken for four days.
6.6 FLOOR & WALL TILING WORKS

6.6.1 Material Requirements


 Tile adhesive
 Tiles of various sizes
 Plastic Spacers
 Approved Grout material
 Water
6.6.2 Equipment Requirements
 Mason’s tools
 Tiles Lifter
 Tiles Cutter
 Water tank and pumps

METHOD STATEMENT: VR/CIVIL-MEP/MS-001 Page no. 15

TITLE METHOD STATEMENT FOR CIVIL & MEP WORKS FOR LANDING GEAR FACILITY
 Stand-by generator
Wall Tiles

 The plastered surface of the wall shall be scratched slightly (not too deep) when the mortar is set, to form a
key with tile adhesive.
 The vertical surfaces where tiling work is to be done shall be rough plastered in plumb and at right angles.
 All the defects on the wall shall be rectified before the work commences.
 The plastered surface shall be kept wet immediately prior to tiling.
 The top level shall be line marked on the wall as shown/specified.
 Spread the approved adhesive glue on the plastered wall to be tiled. For wall tiles, the back of tiles shall be
covered with neat cement paste or adhesive and then pressed to the roughened wall surface and tapped
gently against the wall with the mallet as per the approved design.
 Extreme care shall be taken while setting the outline and level of the lines.
 Tiles shall be neatly cut around the sockets, switches, pipes, or other obstructions, and, in such locations,
single tiles will be provided.
 Tiles shall be fixed with true horizontal and vertical joints of even width.
 The joints between floor and wall tile edges shall be kept uniform using specified sized PVC tile spacers.
Use 2mm plastic spacers between tiles to create the joints or as per specifications. External corners shall
be protected and provided with approved proprietary rigid PVC tile trims.
 Install the first horizontal line of tiles. The vertical location of this line from the F.F.L. must be carefully
calculated. Since the first line will be the guiding line to lay out the whole tile and will govern due to its
location that no tiles shall be cut for less than half-length as per the required specifications.
 Install the tiles as per the first line, using a plastic hammer to withstand each tile.
 Ensure all horizontal and vertical joints are true straight fine lines.
 Excess adhesive shall be cleaned off from the surface of the tile with a wet cloth/sponge.
 Cure the surface for 12 hours before grouting.
 All joints are to be filled and grouted at least twelve hours after completion with a nonshrink grout tinted to
match the color of the tiles.
Floor Tiles

METHOD STATEMENT: VR/CIVIL-MEP/MS-001 Page no. 16

TITLE METHOD STATEMENT FOR CIVIL & MEP WORKS FOR LANDING GEAR FACILITY
 All the concealed plumbing and electrical conduits shall be carried out and checked by the Consultant
before starting tiling work.
 Ensure the ground to be tiled is clean of any dust or dirt to ensure a good bond with the glue. Wash the
floor slabs to remove dust, dirt, and other deleterious materials.
 F.F.L shall be given on the walls and on floors.
 Tiles shall be laid using approved adhesive glue with continuous straight joints not wider than 2mm to true
lines without lapping and with a minimum cutting.
 To maintain the uniform joint width, plastic spacers of width shall be used.
 Care shall be taken to adequately fill and remove all air pockets from beneath the tiles.
 Tiles shall be neatly cut around the floor trap and, in such location, single tiles will be provided.
 The tile shall be left for drying for about 12 hours to 24 hours.
 Joints shall be left for at least 12 hours before grouted with an approved nonshrink tile grout tinted to match
the color of the tiles and surplus grout shall be removed using a damp cloth. Care shall be taken to ensure
that all the PVC tile spacers are removed prior to grouting.
 Make sure no traffic is allowed in the newly tiled area for the first four days from the completion date of the
tiles. The finished surfaces shall be protected by suitable means.
 Note: The procedure for fixing the “skirting” remains the same as for wall tiles and shall be fixed along with
floor tiles in accordance with approved finishing schedule drawings.
6.7 CARPET TILING

 Ensure the ground to be carpeted is clean of any dust or dirt to ensure a good bond with the adhesive
material.
 Carpet shall be laid using approved adhesive glue.
 The carpet shall be left for drying.

METHOD STATEMENT: VR/CIVIL-MEP/MS-001 Page no. 17

TITLE METHOD STATEMENT FOR CIVIL & MEP WORKS FOR LANDING GEAR FACILITY
END OF THE DOCUMENT