Professional Documents
Culture Documents
Document ID CP-117
Security Unrestricted
Revision 7.0
This document is the property of Petroleum Development Oman, LLC. Neither the whole nor any part of this
document may be disclosed to others or reproduced, stored in a retrieval system, or transmitted in any form by
any means (electronic, mechanical, reprographic recording or otherwise) without prior written consent of the
owner.
Revision: 7.0
Petroleum Development Oman LLC Effective: July 2020
i Document Authorisation
Authorised For Issue – July 2020
Document Authorisation
ii Revision History
Revision No. Date Author(s) Scope/Remarks
7.0 July 2020 Jahdamy, Refresh for Eng. Re-org and
Abdullah UEAA recommendations from reviews and audits.
6.0 Oct 2017 Patrick Liesker Refresh, incl. alignment with CP-223
UEP5
5.0 June 2012 Paul Sanders Update to reflect changes in processes and
UEP/5 standards, and to make the document more
accessible.
4.0 January Anton Brouwer/ Update/roll-out
2011 Mike Turberville
4.0 May 2010 Anton Brouwer/ Major Update to reflect improvements in
Mike Turberville processes and standards in Project Delivery
implemented since the last revision
3.0 June 2004 Austin Isaac Alignment with Opportunity Realisation
UEJ1 Process, Minimum Standards and Global
Processes.
2.0 April 1999 Ohi Aikhoje, Incorporates comments from engineers,
OTE4 CFDH’s and recommendations from
external reviews and audits.
1.0 August Paul Hagemeijer, Initial issue.
1998 OME1
Note: Originally conceived as an ERD and then
Jyoti Kumar Das, converted to a Code of Practice under the new
OT1/32 PDO Policy Cascade
Graham Bolam,
UEII
Various Project
Engineers
TABLE OF CONTENTS
i Document Authorisation ................................................................................................................... 3
ii Revision History ................................................................................................................................ 4
iii Related Corporate Management System (CMS) Documents .......................................................... 4
1 Introduction ....................................................................................................................................... 8
1.1 Purpose ......................................................................................................................... 8
1.2 Target audience ............................................................................................................. 8
1.3 When and how should CP-117 be applied? .................................................................. 8
1.4 Related Documents: ...................................................................................................... 9
2 Project delivery organisations within PDO .....................................................................................10
2.1 Project Delivery Accountability .................................................................................... 10
2.1.1 Asset Directorates .................................................................................................... 10
2.1.2 Central Concept Engineering Team ......................................................................... 10
2.1.3 FEED Office ............................................................................................................. 10
2.1.4 Project Delivery ........................................................................................................ 10
2.1.5 Functional Directorate .............................................................................................. 11
2.2 Functional governance & coordination ........................................................................ 12
2.2.1 Facilities Engineering Leadership Team (FELT)...................................................... 12
2.2.2 Enigneering Leardership Integration Team (ELIT) .................................................. 12
2.2.3 Corporate Functional Discipline Heads (CFDH) Forum ........................................... 12
3 Governance and assurance ...........................................................................................................13
3.1 Project Governance ..................................................................................................... 13
3.1.1 Project Controls and Assurance Plan ...................................................................... 13
3.1.2 Assurance activities post-DG4 ................................................................................. 13
3.1.3 Registration and Tracking ........................................................................................ 13
3.1.4 Mandatory Process Safety Design & Engineering Requirements ........................... 13
3.1.5 LFI (Learning From Incidents) Compliance .............................................................. 14
3.2 Front-end loading (FEL) .............................................................................................. 14
3.2.1 Select Phase handover ............................................................................................ 14
3.2.2 Combined FEED & DD ............................................................................................. 14
3.2.3 Front-End Engineering design (FEED) .................................................................... 15
3.3 Project execution planning .......................................................................................... 16
3.4 Risk and opportunity management (GU-717) ............................................................. 16
3.5 Operations readiness .................................................................................................. 17
3.6 Management of change ............................................................................................... 17
4 Project execution activities .............................................................................................................18
4.1 Detailed Design ........................................................................................................... 18
4.2 Construction................................................................................................................. 18
1 Introduction
1.1 Purpose
This code of practice (CoP) is intended to be an instruction manual or “recipe book” for how to manage
projects in PDO.
Compliance with the requirements stated in this CoP Shall be MANDATORY for all project development
and execution activities post DG3. Project teams pre-DG3 shall use this code of practice to ensure
smooth post-DG3 project maturation & execution.
Application of this CoP is intended to:
- Ensure a common way of managing projects within PDO.
- Facilitate internal and external (shareholder) project approvals.
- Enhance project delivery to achieve world-class performance.
This CoP supports the PDO vision:
“To be renowned and respected for the excellence of our people and the value we create for Oman and
all our stakeholders.”
shall require formal approval from the CFDH for Project Management (in accordance with SP-2061 –
Technical Authority System).
the Project Delivery team through Project/Asset interface engineer to support projects from Project
Initiation Note (PIN) until DG-3 at which point a Project manager/Project engineer will be take over
responsibility for delivery. Where possible PD should nominate the Project Manager / Project Egineeer
in the Select phase to ensure their input to ther CSR / BFD and to the PES.
PDA is responsible to execute projects from < $50 mln. PDB is responsible to execute project >$50mln.
Other PD departments are structured in order to support the delivery of these projects.
PD executes a wide range of projects on behalf of the assets and it resourced to be self-sufficient with
a full complement of project engineering delivery staff as necessary to deliver the complete range of
projects.
The PDC department is the primary home for Engineering contracts both in support of project delivery
but also for other contracts including those for CFDHs.
The PDLT organisation chart is shown below:
ELIT has been established as a more hands-on forum which enables FELT to be strategic in nature.
The role of ELIT it to ensure an aligned view and implement actions plan across PDO engineering
department heads (Asset, PD, Function) of the key issues which impact and enable achieving business
performance goals. ELIT should meet as a minimum on a monthly basis and is chaired by UEA who
ensures that issues are escalated to FELT where required.
The ELIT charter is included in appendix 4
ALL Projects in PDO shall ensure that a cross-check has been completed to ensure relevant
LFIs have been identified and implemented. LFIs are stored and accessed through the PDO
Learning Knowledge Base (LKB) system.
Detailed Design
LL Procurement
Procurement
Construction
Pre-commissioning
Commissioning
Start-up
As-built / Close-out
Hand-over
The PEP, risk and opportunity management, and management of change continue to be applied and
updated during the Execute phase, while Operations Readiness becomes increasingly important.
4.2 Construction
Contracting mechanisms vary depending on size and complexity of the work ranging from agreed day
rates to lump sum prices.
Key construction activities include but are not limited to the following:
To construct the facility in a manner that minimises risk to the construction workforce
during construction and ensures a safe and orderly start up on completion Input in
design and confirmation of work scope.
Site establishment including offices, lay down, specialist storage, welfare facilities, local
fabrication areas, workforce accommodation (e.g. onshore camp) supply base and
staging points.
Set up and maintenance of material management system including tracking, receipt,
handling, storage and preservation and installation.
Identification and recruitment of competent contractors and resources and where
applicable the development of local content strategies and plans.
Construction sequencing and planning and resource loading, including levels and
competencies of personnel.
Job hazard analysis and development of construction methodologies e.g. ‘stick build’
versus modularisation strategies.
Development of work packs and inspection and testing plans.
Fabrication of structures, piping and installation of major items of equipment e.g.
vessels, compressors.
Specification and procurement of specialised installation/construction equipment e.g.
heavy lift equipment.
Logistics associated with the mobilisation of personnel, equipment and materials.
Mechanical completion leading on to pre-commissioning of all utility and process
systems. Following pre-commissioning, handover to the CSU team for live
commissioning, start-up and operations.
4.2.4 Pre-commissioning
Pre-commissioning activities undertaken after mechanical completion, but prior to
commissioning, are to prove and validate the functioning of equipment. Such activities could
involve the introduction of fluids into systems, but not hydrocarbons.
Typically, pre-commissioning activities will verify that documentation to support mechanical
completion is in place, and not repeat work carried out to achieve mechanical completion. Such
activities are carried out on a single discipline basis, by system / subsystem, and require
equipment or systems to be energised, but do not require the introduction of process fluids.
Activities include instrument loop checks, panel function tests, energising electrical equipment
and running motors without loads. They are documented on ‘B’ check sheets, which will be
generated and managed through CCMS/Zenator to ensure that asset integrity can be verified
and demonstrated.
At the start of pre-commissioning, CCMS needs to be ready, operational and maintained up to
date and the commissioning PTW system activated.
Normal dump flushing is typically a construction activity but specialist flushing and cleaning,
e.g. chemical and hydraulic cleaning, drying, oxygen freeing etc, falls within the integrated
commissioning team’s responsibility - see SP-2051 - Specification for Flushing, Pressure
Testing, Pickling and Sensitive Leak Testing of Mechanical Equipment and Piping.
4.3.1 Commissioning
These activities are those undertaken after pre-commissioning to dynamically verify
functionality of equipment and to ensure that systems, or facilities forming part of a system, are
in accordance with specified requirements to bring that system into operation.
Typically, commissioning activities undertaken after pre-commissioning will be carried out on a
system basis by a multidiscipline team of engineers and operations staff under simulated
conditions. Commissioning responsibility may necessitate nitrogen and helium testing, which
should normally be executed by specialist contractors and supported by the commissioning
personnel.
The CSU team will start up and operate the non-hydrocarbon systems during commissioning
activities until these systems are fully proven and provisional handover to Operations can be
carried out. For hydrocarbon systems, provisional handover will take place after all pre-
commissioning and commissioning activities have been completed up to the point of
hydrocarbon introduction. The Operations group takes responsibility for the introduction of
hydrocarbons, the start-up activities and operation of hydrocarbon process systems. Co-
ordination between the Operations and CSU teams is essential and particularly so on brown-
field sites. In this instance, a commissioning leader may report to an Asset owner for the
duration of CSU activities.
The CSU sequence shall be developed for the integrated production system during FEED and
detailed design; with clear distinction between non-hydrocarbon systems (e.g. firewater, utility
air, sewage etc) and hydrocarbon systems (e.g. process system, fuel gas, drains/vents etc.).
At some point commissioning requires the introduction of fluids (process or non-process) and
operation of the system. This will be documented using a procedure which shall be compiled
specifically for the project and provide for signature on completion of each step. The procedure
shall form part of the Commissioning Management System to ensure that asset integrity can
be verified and demonstrated.
6 Project Services
Support: UEAP
Project Services will provide resources, processes, systems and tools to enable the PM to deliver:
Robust estimates that allow for the uncertainties of our complex reservoirs and novel
development options in a volatile market.
Realistic achievable plans that still provide challenge to project teams.
Effective controls that manage the work and show where we are and future possibilities.
Valid up to date project management information that allow informed management decisions.
Useful close-out processes that capture the lessons and data for future improvement.
Benchmarking against our peers to demonstrate top quartile performance.
Active project wide risk management and analysis.
Baselined cost and schedule that enables active change management; impact of changes to
be communicated and understood.
Application and consistent use of standards and adherence to PDO business processes.
The CFDH (and TA1) for Project Services is responsible for the setting and maintenance of the
associated standards and processes. Once their competence is proven, the CFDH appoints TA2s who
sign off documents specified as such in DCAF.
o bulk materials;
o labour and engineering services;
o drilling rigs and services;
o other relevant data should also be sought such as:
import restrictions;
duties and taxes applicable;
local content targets etc.; and
o adequate contingency levels, based on the risk profile of the project and
historical performance data, are being used.
All estimates should correspond to the requirements for the ORP stage and the defined accuracy levels,
which are highlighted in the below table.
Project teams should schedule their assurance reviews at least three months in advance with
the UEAP Function.
6.2.2 Project cost estimates build
A capital cost estimate is built up from the following components (see diagram): and use various
type of money, for example: Estimate Date of Money (EDM), Money of the Day (MOD) or Real
Terms (RT).
90:10
Management
Reserve is not
used in PDO.
Equal Chance of cost
50:50 Inflation exceeding or being lower
EPC Premium
10:90 Contingency 90% chance that cost
Base (Market Market Factors will be exceeded
adjusted) Allowances Base
Identified Scope
(incl. Owners
Costs)
The Base Estimate also includes allowances, usually expressed as percentages, to allow for
the ‘known unknowns’ for example design growth that could occur in future phases.
The Base Estimate is recorded in US $ and MOD. Within a Base Estimate some equipment
quotes may be in another currency, these should be converted to US $ using the prescribed
exchange rates. To establish MOD costs the phased estimate is converted with specified
inflation factors. Both exchange rates and inflation factors are confirmed each year by UEAP3
in the Programme Build guidelines.
All estimates including “Updated type 2” shall be subject to a deterministic cost risk assessment
covering the TECOP risks. This exercise is mandatory and is supported by the Function. The
risks and opportunities identified through the TECOP exercise are input to the deterministic
accuracy and contingency tool maintained by the Function.
For updated type ‘2’, ‘3’ & ‘4’ estimates with cost larger than $50mln a Monte Carlo simulation
shall be carried out by the Function, in order to predict the cost probability distribution. A
deterministic TECOP assessment shall also be run in parallel as a check on these probabilistic
results.
6.2.5 Future market & EPC premium
As the Base Estimate is for a specific scope and for a specified duration the costs for
commodities over time may fluctuate because of market movement. To compensate for
fluctuations of volatile markets a future market allowance is introduced to the estimate. Future
market indices are applied to the phased Base Estimate.
The Function monitors published market trends and determines the future market indices to be
used on company estimates. Lastly, an EPC contracting premium is added (if contracting
strategy for the project is EPC lumpsum or risks associated with the project is transferred to
contractor ) that is determined by the Function and FPB. These factors, future market and EPC
premium, are published in the Programme Build guidance note.
6.2.6 Cost analogues and benchmarking
Estimators often use various analogues to establish the costs of estimated items with reference
to a suitable metric (for example weight). Analogue metrics are often referenced to quantities
and unit-of-measurement used for progress management of the plan and schedule.
Benchmarking shall be conducted on the main project scope elements to ascertain the
competitiveness of the project. Wherever possible, benchmarking should be external i.e. in
comparison to other companies (and other industries where relevant).
6.2.7 Estimate data collection
It is key that the company estimating systems are kept live with feedback from ongoing and
completed projects. Many projects are completed by lump sum contractors who are reluctant
to share costs information, therefore the provision of detailed feedback of costs data shall be
included in the tender instructions. The WBS, CTR and C5 contract price breakdown structure
(incl. procurement details) for any project or contract shall be developed in such a way that at
various milestones through the project life actual cost are fed back to the Function to update
their estimate databases for future projects/contracts. This requirement is valid for any EPC,
EP+C, EC, and E or C Contracts, and single purchase orders.
Additionally, ‘quantities tables’ used for the management of progress shall be maintained and
fed back at various quantity updates/milestones to the Function.
Management of resources.
Each is covered in a separate section below.
Project controls provide a series of processes, based on these six focus areas, which assist in executing
a project in the most efficient and economical way. Secondly, but not less importantly, project controls
provide the mechanism to inform management at any point in time during the project about the actual
status of the project, both in cost and time, so that, if required, corrective actions can pro-actively be
prepared and ultimately exercised in a timely fashion.
The Project Controls Plan (PCP) documents the minimum standards of project controls systems and
processes required to manage the project and provide a clear and concise explanation of how project
controls shall be implemented on a project including all key references to applicable project procedures,
standards and guidelines.
6.3.2 Management of cost
Cost control during any phase of a project comprises the setting up of the cost procedures and systems
and the monitoring and the reporting of the actual project expenditure and commitments against the
approved project budget. The early identification and registration of deviations together with the
following of trends enables project management to control the project.
All project activities should be broken down into controllable items. For cost control purposes it is
important that cost estimates shall be carried out in accordance with the approved Cost Breakdown
Structure (CBS).This will ensure that the data can be retrieved for cost control purposes in a systematic
manner.
Regular reporting of the Value of Work Done (VOWD), commitments and assessment of the cost of
work remaining should detect any potential over or under expenditure in good time for proper
management action. Project progress is continuously monitored, in physical and financial terms. In
addition to these primary objectives of cost control throughout the various phases of a project, it should
provide data for:
Capital expenditure phasing reflecting the anticipated progress of the VOWD
Cash flow forecasts, based on the expenditure phasing taking due account of the payment
conditions
A breakdown of the value of the final fixed assets
Future estimating and planning purposes.
Contingency management is a key part of cost control. As change occurs, contingency should be run
down and trended to ensure the correct amount of contingency is maintained. At six-monthly intervals
the remaining project contingency must be re-assessed to ensure there are sufficient project funds
available to pay for the probable outstanding risks.
The cost progress will be measured based on the planned and actual VOWD. The Forecast – Estimate
At Completion (EAC) shall be the Base Cost Forecast plus Contingency Forecast.
PDO uses SAP to hold the financial data of all its projects, including budget, VOWD and forecasts. It is
important that SAP is maintained by the project team to accurately reflect the latest cost status of all
projects, even if the detailed cost control is managed in other systems.
Project reporting shall provide a true and honest reflection of the status of the project at the cut off date
by reporting of all cost and scheduling elements plus the main project highlights and areas of concern
(without unnecessary details) and including forecasts and remedies.
For Medium (>$50mln) and Large (>$200mln) projects, the project team shall issue a progress report
on a monthly basis, including a Project One Pager through the online Project Reporting System (PRS)
tool. The One-Page report shall be specific to the current phase of the project and time & cost actuals
and forecasts shall be based on the P50 dates & budget.
For specific ‘Flagship’ Shell projects, each quarter the Shell Business One templates shall be
completed and loaded into the Shell system.
required. The Function is responsible for appointing a team of suitably experienced personnel and to
prepare a draft ToR. The ESAR leader shall be a certified Project Services TA2.
7 Quality assurance
Support: UEQ
PDO’s requirements for quality management have been defined within:
CP-190 - Quality Management System for Project Delivery: Ensures that quality is applied and
consistently implemented in PDO projects by supporting the ORP to provide a standardised
Governance, Assurance and Delivery process and give direction to Project Management).
GU-711 – Model Project Quality Plan: Details overall Quality Requirements, Project Quality
Management System Structure and Organisation to be applied for a specific Project. Provides minimum
requirements for preparation and implementation of Project Quality Plan (PQP) for all projects.
SP-1171 - Specification for Quality Assurance Requirements for Product and Service: Provides
instructions which combined with the PQP specify the Company’s minimum requirements for Quality
Assurance in all contracts and purchase orders and provides guidelines on the contents and
development of a Contract Quality Plan and Quality Control Plan.
SP-2061 – Technical Authority System: Provides information on Technical Authorities (TA) system
operates by PDO.
However, the existence of a good management system does not in itself guarantee a quality product;
this has to be accomplished via a combination of technical competence and, most importantly,
adherence by all contributors to the system.
The commitment and active involvement of the functional leadership team(s) in developing and
maintaining the project Quality Management System (QMS) is therefore essential for the system to be
effective.
The PM/PE has overall responsibility for quality and its implementation at every stage of the project.
The PM/PE should ensure that the project QMS is reviewed at regular intervals ensuring its continuing
suitability, adequacy and effectiveness.
Where repetitive projects (portfolio of projects) are covered within a single contract scope, a single
QMS/PQP may be developed, underpinned by level 3, 4 documents / deliverables.
Suitability is judged by its ability to sustain current performance.
Adequacy is judged by its ability to deliver the project that satisfies requirements, standards
and regulations.
The review output should include decisions and actions related to the improvement of the effectiveness
of the project QMS, its processes and related resource needs.
Further responsibility and authority include;
Ensuring that project quality requirements are addressed and included within the PES/PEP.
Establishing, implementing and maintaining the project QMS including quality strategy and
PQP.
Establishing the budget, resource estimate for quality and ensuring that appropriate quality
resources are available within their respective project team and contractors organisations in
order to achieve PDO’s Quality Policy & Objectives: Identifying the objectives and providing the
infrastructure and quality resources, clearly defining Roles & Responsibilities and motivating
personnel to improve the processes and product.
Ensuring that project quality requirements are included within contract documents and that
contractors, subcontractors and vendors comply with project QMS requirements.
Team development to ensure all project personnel are aware of quality responsibilities.
Promoting a consistency of approach & sharing learning across projects and for promoting
continuous improvement within their project organisation. Planning for future preventative
actions (identify, collect, store, update, retrieve and review information).
Taking the appropriate action necessary to address quality issues impacting project delivery
including document reviews, and corrective and preventive actions are completed in a timely
manner (Delivering the project by complying to standards and developing, implementing fit for
purpose processes).
Making use of available quality related information to evaluate options and make decisions.
Identifying and implementing quality KPI’s and applying rewards/penalties as applicable under
established contracts.
Written procedures shall be developed in order to adequately control the quality of the work and to
ensure compliance with all aspects of the work and applicable codes, standards and legislative
requirements. Procedures required to complete the works shall be made available at the point of use
prior to commencement of the relative section of the work.
There is no pre-ordained scaling in DCAF. Controls and tools for each discipline have been base-lined
by the Functions, but scaling/applicability is left to the project, as ultimate accountability for controls and
assurance resides with the line of sight of that project.
The BOM/FEDM or PM, dependent on phase/gate, is responsible for the full day-to-day management
of the opportunity/project and is responsible (supported by disciplines) for the PCAP framing and
maintenance. The BOM/FEDM/PM or delegate uses the standard PDO template to draw up the PCAP
(mandatory assurance events and specific controls, including deviations). This shall be a team effort
with all the required disciplines attending.
DCAF works by assigning accountability for an overall decision or deliverable to a single discipline whilst
recognizing that the contribution from other disciplines may be a control in their own right.
In signing off on a business-critical element and/or deliverable the individual is:
ATA – Signing as being ultimately accountable for the control: control point owner, accountable for
exercising the right controls are properly identified/ implemented by qualified individuals. May not claim
full competence in all aspects, but he or she is considered to be responsible enough to pull in necessary
counsel to take on the accountability – approves the end control deliverable.
RTA - Signing as being responsible for their respective discipline input into the control point on behalf
of their discipline: shares in the accountability, personally accountable for their input/action, the role of
an RTA is to QC and endorse the input of his/her discipline into the control point (deliverable/decision),
he/she must fully understand the requirements (CoP/SP/PR/DEP) and deliverables to be produced and
ensure the discipline standards are properly implemented.
PCAP adherence shall be submitted to the DRB at each DG in order to proceed to the next gate. Where
controls have not been achieved, the FEDM/PM will require to demonstrate (endorsed by CFDH as
applicable) that the control has been mitigated and will not impact the project progression, delivery and
asset integrity.
8 HSE in Projects
Safety remains PDO’s first priority.
Overall Project HSE performance is the accountability of the Project Manager however responsibility is
shared by all project team members.
The project shall develop and manage risk registers to identify and manage both personal and process
safety risks. PDO project team members shall take personal accountability for ensuring HSE
performance and a Goal Zero focus.
Each project shall have an HSE Focal Point assigned. The HSE Focal Point shall ensure that the project
complies with the requirements of CP-122 and PR2392.
In addition to the more extensive guidance documents, Project Managers are accountable to ensure
their their project teams and the scope they are delivering are managed according to the 2 simplified &
mandatory sets of rules ie:
Life Saving Rules (LSR)
Engineering Process Safety Fundementals (EPSF)
9 Information management
The Project Manager shall ensure that an IM Focal Point is assigned at the beginning of Define Phase
of each project. The IM Focal Point shall ensure that the project complies with SP-2122, including
preparation of IM Plans and the use of latest IM specifications in all contracts.
The IM Focal point shall ensure timely delivery of information deliverables (EDW, SAP-PM, As-Built,
Vendor MRB, POM, etc), ensuring that Tags are related to drawings and Functional Locations in SAP.
He/she shall undertake a handover assurance review before start-up, to verify availability,
completeness and format of information deliverables for SAP-PM, EDW and As-Built, and report
outcome using the template provided in SP-2122.
10 Finance in projects
In PDO, the Finance contribution to projects is delivered through:
Establishing and implementing a risk based controlled project environment, aimed at achieving
business objectives, providing honest, timely, objective and transparent management and financial
information and promoting effective risk management;
Providing guidance on finance/accounting implications in accordance with established internal and
external accounting policies and procedures;
Ensure compliance with PDO’s internal controls including compliance with CMS, work practices,
procedures and guidelines as defined by corporate Finance and international accounting standards.
To ensure that all Investment Decision Manual requirements are followed, support all investment
proposals and assure that proper due diligence and independent review have been performed.
Thorough understanding and disclosure of economic assumptions, contingencies, risks and
accounting, contractual, insurance, tax and treasury implications.
Independent challenge as custodian of the Business Controls and Assurance framework.
Procedures defining the global project execution process and control requirements.
Tools and instructions supporting the process & control requirements
o Budget management
o Management of invoices
o Project cost allocation
o Exchange rate application
o Manual of Authorities
The Competitveness Review is a structured process that is used to add value to a project by comparing
a specific project to projects of similar characteristics executed by the industry.
The process begins with benchmarking of Project Performance to compare PDO projects against other
projects, using both qualitative and quantitative aspects, in order to learn, improve and implement best
practices. On a project level, benchmarking of project performance assesses:
Project practices, compared to the standard defined in the CoP, and
Project metrics (cost, schedule and first year production, UTC,UDC), compared to metrics from
projects (internal and external to PDO) of similar size and complexity.
In addition, by continuous benchmarking of PDO projects, we can improve the effectiveness of our
practices defined in this CoP in order to achieve top quartile performance in project delivery.
Benchmarking should be conducted ideally as early as DG2 and shall be conducted duing Select phase
for all projects. The Competitiveness review shall form part of the Terms of Reference for the VAR3.
For projects where no VAR is taking place, the project team should implement a CR prior to DG3a.
Understand what
we are getting Focus in and evaluate
into – look wide – best and do-able
options culminating in Prepare to lock into Implement the
What’s feasible an investment opportunity Deliver the value
options? Concept Selection
IDENTIFY
SELECT DEFINE EXECUTE OPERATE
@ ASSESS
Appendix 2 – Templates
Project Execution Strategy
Project Execution Plan
FEL Self-assessment
Appendix 3 – Abbreviations
AFC Approved For Construction
AIPS Asset Integrity and Process Safety
ALARP As Low As Reasonably Practicable
BFD Basis For Design
BOM Business Opportunity Manager
BVD Baseline Value Drivers
Capex Capital Expenditure
CCES Contract Cost Estimating System
CCET Central Concept Engineering Team
CCMS Construction Completion Management System
CFDH Corporate Functional Discipline Head
CMS Corporate Management System
CoP Code of Practice
PD Project Delivery
CSU Commissioning and Start-Up
CTR Cost, Time, Resources
DCAF Discipline Controls and Assurance Framework
DE Decision Executive
DEM Design Engineering Manual
DG Decision Gate
DRB Decision Review Board
EMC/ODC Engineering Management Contract/Offplot Development Contract
EPC Engineering, Procurement and Construction
EOR Enhanced Oil Recovery
ESAR Estimate and Schedule Assurance Review
FCP Facility Change Proposal
FDC Field Development Centre
FEA Fire and Explosion Analysis
FEDM Front-End Engineering and Design
FEED Front-End Development Manager
FELT Facilities Engineering Leadership Team
FID Final Investment Decision
FPD Flawless Project Delivery
Hazid Hazard Identification
Hazop Hazards and Operability
HSE Health, Safety and Environment
IPF Instrumented Protective Function
Project Delivery:
Owns PDO’s Project Delivery processes, maintains an overview of process performance, and
drives Continuous Improvement.
Maintains an overview of project portfolio performance and takes balancing / mitigating
action as appropriate.
Engineering Standards:
Owns Policies, Standards and Specifications. Drives and supports their deployment.
Provide challenges and works with CFDHs on standards, ensuring alignment with PDO
priorities.
Organisation Design:
Owns project organisation templates and resourcing methodology. Any
variations/adjustment to be challenged and approved by FELT.
Technology and Digitalisation:
Makes decisions on the adoption of Engineering-related technology and drives deployment.
Promotes the adoption of digitalization in engineering and ensure the roadmap is
implemented accordingly