Professional Documents
Culture Documents
Final Report at Test - Buz
Final Report at Test - Buz
COLLEGE OF
ENGINEERIN
Department Of Construction Technology and Management
DURATION TIME:
FOUR MONTHS
ASSOSA, ETHIOPIA
DECLARATION
I declare that the report here submitted is original except for source material explicitly
acknowledged. I also here by declare that all the information and facts stated are true, correct and
complete that I performed during my internship program. The submitted soft copy with details
listed in the submission details is identical to the hard copy, which is going to be submitted. I
also acknowledge that I aware of university’s policy and regulations on honesty in academic
work, and of the disciplinary guidelines and procedures.
I assure that the report contains actual events and facts that I observed and performed during my
internship practice program. All the contents are not been submitted to any other institute or
university.
ACKNOWLEDGEMENTS
First, I would like to thanks my almighty God for keeping my life from any injures from
beginning to end of my project and for helping me to attend & accomplish my internship
program, all professionals and workers in peace and in good relationship.
I would like to thanks Assosa University college of Engineering and Technology department of
Construction Technology and Management Engineering that have prepared this program &
helped me to have a practical knowledge over our courses.
I also wish to express our deepest gratitude for the company Walabu Construction S.C for giving
me this chance to do my internship in their site.
I would like to thanks my advisor Mr. Tigabu A. (MSc) for helping me in all my needs and I
would like to thanks also, site engineer Eng.KumaA. and foreman Eng.Tadase B. and Bakale E.
and other staff members of the site for their showing different things on site work, answer, and
expression in ambiguous points for their involvement in my internship program.
Finally, I would like to thanks all that who support us in all direction.
EXECUTIVE SUMMARY
This report is an outcome of the exercise I conducted during my internship program from
Octaber 2022 to Fabraury 20223 G.C. The program was an opportunity for me to put in to
practice the theoretical knowledge I had acquired during my four years of study at Assosa
University. The purpose of this report is to put in writing the work experience I had performed
and the learning attained from performing specific tasks while working in a professional
environment.
The first part of the report describes about our hosting company called Walabu construction S.C
grade one general contractor in Ethiopia and Objectives of internship. The company is well
experienced in providing professional services in a wide range of civil, Mechanical and
Electrical engineering works to different user since its establishments in 2018 G.C.
The second part of my report briefly explains the overall internship experience I have gained
during my practical periods. I got into my internship hosting company at its Nekemte Integrated
Agro- Industrial Park project site following the acceptance of my requesting letter by the
company. In this project, the client “Oromia Industrial Parks Development Corporation”, the
consultant “EF Architects and Engineering Consulting Plc”, and the contractor “Walabu
Construction Share Company” are involved.On the internship program, I tried to cover all the
basic work sections in both office and site level activities. Among others, I had performed -
drawing reading, bar schedule and etc works. Regarding the site work, I have also seen the step-
by-step procedures on how to construct beams, columns, and slabs and shear wall.
Both site challenges and personal challenges faced and measures taken during our internship are
also addressed in this report.
The third part of my report briefly explains about the overall benefits we gained from our
internship in terms of improving our practical skills, interpersonal communication skills, team
playing skills, leadership skills, upgrading my theoretical knowledge and work ethics.
Finally, I made a conclusion and some recommendations are forwarded for my company and
university. And the references I used and Appendix.
Prepared by Buzunesh Adugna
Page III
ASU
Table of Contents
............................................................................................................................................................................. i
DECLARATION..............................................................................................................................I
ACKNOWLEDGEMENTS............................................................................................................II
EXECUTIVE SUMMARY...........................................................................................................III
LIST OF FIGURES................................................................................................................................................VI
LIST OF TABLES.................................................................................................................................................VI
ACRONYMS........................................................................................................................................................VII
CHAPTER ONE..............................................................................................................................1
1. INTRODUCTION.......................................................................................................................1
1.1 GENERAL INTRODUCTION ABOUT INTERNSHIP..........................................................1
1.2 GENERAL BACKGROUND OF HOSTING COMPANY................................................................................................1
1.2.1Background of the Company.......................................................................................................................1
1.2.2Mission, Vision and Core Values ................................................................................................................2
1.2.3 Working licensee of company.....................................................................................................................3
1.2.4 The end user of this construction company.................................................................................................3
1.2.5 Governance, Management and Organization Structure.............................................................................4
1.2.6 Work flow of our hosting company.............................................................................................................6
1.2.7 Manpower Description...............................................................................................................................7
1.2.8 Machineries and Equipment of the Company.............................................................................................9
1.3 GENERAL INFORMATION..................................................................................................................................12
CHAPTER TWO...........................................................................................................................13
2. OVER ALL INTERNSHIP EXPERIENCE..............................................................................13
2.1 OBJECTIVE OF INTERNSHIP PROGRAM..................................................................................................13
2.1.1 General objective.....................................................................................................................................13
2.1.2 Specific objective......................................................................................................................................13
2.2 HOW I GET TO THE COMPANY.........................................................................................................................13
2.3 SITE WORK.......................................................................................................................................................14
2.3.1 Super structure work................................................................................................................................14
2.3.2 Office work...............................................................................................................................................14
2.4 MATERIALS AND METHODOLOGY....................................................................................................................15
2.4.1 Concrete Work..........................................................................................................................................15
2.4.1.1 Materials for Concrete..........................................................................................................................15
2.4.1.2 Concrete................................................................................................................................................16
2.4.1.3 Concrete mixing....................................................................................................................................18
2.4.1.4 Column Work.........................................................................................................................................19
2.4.1.5 Beam work............................................................................................................................................20
2.4.2 Slabs.........................................................................................................................................................21
2.4.2.1 Solid slab...............................................................................................................................................22
2.4.3 Stair case work.........................................................................................................................................23
2.4.4 Spacer.......................................................................................................................................................24
2.4.5 Stirrup...................................................................................................................................................... 25
2.4.6 Reinforcement bar....................................................................................................................................26
2.4.7 Scaffoldings..............................................................................................................................................26
2.5 FORM WORK.....................................................................................................................................................27
2.5.1 Fixing form work......................................................................................................................................27
2.5.2 Removal of formwork...............................................................................................................................27
2.6 WALL WORK....................................................................................................................................................28
2.6.1 Plastering.................................................................................................................................................29
2.7, SHEAR WALL...................................................................................................................................................30
2.8 CHALLENGES I FACED ON SITE.........................................................................................................................31
2.9 MEASURES TAKEN TO THOSE CHALLENGES......................................................................................................32
CHAPTER THREE.......................................................................................................................33
3. OVERALL BENEFITS I GAINED FROM THE INTERNSHIP.............................................33
3. 1 IMPROVING PRACTICAL KNOWLEDGE.............................................................................................................34
3. 2 IMPROVING THEORETICAL KNOWLEDGE..........................................................................................................34
3.3 IMPROVING INTERPERSONAL COMMUNICATION SKILLS...................................................................................34
3.4 IMPROVING TEAM PLAYING SKILLS..................................................................................................................35
3.5 IMPROVING LEADERSHIP SKILLS......................................................................................................................36
3.6 UNDERSTANDING WORK ETHICS AND RELATED ISSUES...................................................................................36
3.7 ENTREPRENEURSHIP SKILLS ACQUIRED............................................................................................................38
CHAPTER FOUR.........................................................................................................................39
4. CONCLUSION AND RECOMMENDATION........................................................................39
4.1 CONCLUSION............................................................................................................................................... 39
4.2. RECOMMENDATION..................................................................................................................................40
4.2.1. Recommendation for the company...........................................................................................................40
4.2.2. Recommendation for the university.........................................................................................................40
REFERENCES..............................................................................................................................41
APPENDICES...............................................................................................................................42
LIST OF FIGURES
.........................................................................................................................................................5
Figure 1. 1 Walabu share company structures.................................................................................5
Figure 1.2 General Work Flow at nekemte city project..................................................................6
Figure 2. 1 Coarse and Fine Aggregate.........................................................................................16
Figure 2. 2 box figures for batching aggregate and sand..............................................................17
Figure 2. 3 mixing machines.........................................................................................................18
Figure 2. 4 Column work...............................................................................................................20
Figure 2.5 solid slabs.....................................................................................................................23
Figure 2. 7 Spacer (cover block)....................................................................................................25
Figure 2.8 Stirrups........................................................................................................................25
Figure 2. 9 positive and negative bars...........................................................................................26
Figure 2. 10 Removal of formwork on slab...................................................................................27
Figure 2. 13 shear wall...................................................................................................................31
LIST OF TABLES
Table 1.1 Walabu Equipement and machinery..............................................................................10
Table 2. 1 Mixing Ratio.................................................................................................................17
Table 2. 2 Removal of formwork..................................................................................................28
ACRONYMS
BoD----------------------------Board of Directors
HR--------------------------------Human resource
RC-------------------------------Reinforcement concrete
CHAPTER ONE
1. INTRODUCTION
1.1 General introduction about internship
The term internship program is concerned to integrate, familiarize, combine, and to mix both
theoretical and practical skill.Internship should give us to practical skills, work place experience
and greater knowledge of that industry in exchange for the employer benefiting from our labour.
Internship is professional learning experience that offers meaningful practical work related to a
student’s field of study or career interest.
Beverage Share Company, one project with Bishoftu city Administration and two asphalt road
projects were signed with Ethiopia Road Authority. It recorded a significant turn over as
compared to most of local contractors and this paved ways for more potential to execute even
larger projects. In the construction of these projects, WCSH has created a job opportunity for
many contractors and local community. 15 The company also creates job opportunity for 7
contractors, 309 SMEs and about 5,400 local daily laborers. Right now, the company has over
350 employees (permanent and contractual). There are several qualified staff in various disciples,
who are young, energetic, and committed to see the growth and prosperity of the company. The
company is growing and expanding its capacity towards a standardized approach. It is possible to
join and reach higher performers categories and then exceed most of them by integrating
commitment and concerted efforts of management and staffs at all levels. The Company aspires
to be one of the competent construction firms locally and internationally.
WCShC wants to be preferred contractors of choice that plays key roles in economic
development through stakeholders’ partnership, integrity, timely delivery of projects,
high standard of works and customers’ satisfaction enhance by focus wealth creation for
young people who are trained owners of business and specialized sub-contractors
working with integrity and excellence.
B, Vision
Statement to see the leading construction company in 5 years in Ethiopia and10 years in
Africa.
C, Core Values
5) Team Work
Governmental constructions
Private owners
NGO constructions owners etc.
Walabu Board
Prepared by Buzunesh Adugna
Page 4
General Manager
Executive secretary Legal Service Director
Project manager
Administration
Secretary
Storekeeper
Timekeeper
Client: the person or legal entity who contracts with an individual or organization under a
construction contract and pays for the works.
Consultant: - the client’s advisor on design, cost and other matters. Such advisors might include
project managers. Consultants work on the side of the client and they have the responsibility of
conducting necessary quality control mechanisms to make sure that the project is being
constructed as per design.
Contract administration: - is a major element of supervision and it has the following functions.
quality control
time control
Subcontractor :-in building work there has been a long trend to pass the majority of work to
sub-contractors, who specialize in various trades, where many operations are ‘packaged up’ and
sub-let to them. Thus sub-contractors may be let for excavation, formworks, reinforcement
making and erecting, plastering masonry work, etc.
Site engineer: -Is controls all the activities in the site and is responsible for the whole
construction works like directing, planning, organizing, coordinating and controlling the activity
of the site.
Generally, the site engineer;
Weekly or monthly work implementation.
Checks and Controls all construction activities on the site from the
beginning.
Prepares daily laborers output report.
Organizes the monthly reports to be sent to Head office.
Schedules reviews any sub contract payments.
Responsible for whole construction
General Forman: - Acts as the agent’s right hand man for the execution of the work at the field,
his duty is to keep the work moving as the agent has planned it. He often has much authority on
the site, and is often astonishingly capable from their long experience of construction
Trade Forman: - Controls the work most of the skilled (masons, carpenters, plumber…) and
unskilled (gang leaders) labors by giving directions that he receive from the general manager or
the site engineer.
Office engineer :- Studies contract documents, reports, drafts and make himself ,The main
responsibility of the office engineers are:-
Sanitary engineer:-The sanitary work is carried out by a sub-contractor and the sanitary
engineer conducts the sanitary work carried out is as per the drawings and suggest (propose)
constructive ideas if there is any need to change the drawings
Carpenter: - is a craft responsible for making wood structures for supporting different structural
components like beams and columns, formworks, and chip wood works.
Plumber :- responsible for installing, repairing and maintaining pipes and other construction
materials used for water supply and waste water disposal.
Electricians: -perform works required for the repair, maintenance, installation and
modernization of electrical systems.
Machine operators: -operate, fix and maintain different machineries on the site like, vibrator,
mixer, generator etc.
Metalworkers: -fabricate, assemble, install and repair sheet metal products and equipment’s.
Finance-The finance takes care of monthly salary (fee) of the employees; finance the purchasing
of requested materials.
Storekeeper:-Control the amount and type of materials entering and leaving the store
Time keeper: a person who controls time of entrance and exit of workers on the site.
Operation costs are a recurring expense based on frequency of use while idle sitting machines
are a drain he income. Construction fleets should be evaluated continuously to determine
whether new machinery and equipment need to be added to the fleet, any of its parts need to be
replaced, and when underutilized or damaged machines need to be discarded and at what cost.
The choice of construction equipment for a job site is a key factor to be considered for timely
completion of the project within the stipulated budget. It is crucial that the company should
thoroughly understand the tasks that need to be completed, the machines that need to be used, the
budget and time constraints in the execution of the construction project.
9 Truck Mixer 2 2 2 2 4
10 Dump Truck 13 50 13 13 13 50
11 Water Truck 5 14 10 29
12 Carrier Truck 2 2 2 6
13 Feul Truck 1 1 1 3
14 Low-bed Truck
1 1 1 3
15 Small Vehicle 6 2 19 2 12 2 37
16 Automobile 2 3 3 8
17 Concrete Vibrator 63 63 63 63 0
18 Concrete Mixer 17 33 33 33 0
19 Compacters 6 6 6 6 0
20 Building Clamping 42 42 42 0
Winch
21 Blocket Machine 7 7 7 7 0
22 Terazzo Machine 2 2 2 2 0
23 Wood Machine 2 2 2 2 0
24 Generators 17 17 17 17 0
25 Welding Machines 2 2 2 2 0
26 Air Compressor 2 2 2 2 0
27 Feul Dispenser 2 2 2 0
28 Water Pumps 14 14 14 14 0
29 Grinding Machine 6 6 6 6 0
CHAPTER TWO
2. OVER ALL INTERNSHIP EXPERIENCE
Verify the collected data and confirm the quantity of each work.
Shall comply in all respects with the requirements of Ethiopian building code standards.
Portland cement is used on the site of our internship.
3. Aggregates:-Aggregates the most important constituent of concrete and the filler materials
which make up a large portion (approximately 70-75%) of the concrete volume. There are two
types of aggregates used. Those are Fine aggregate and Course aggregates
Fine aggregatesSand,
Usually, the natural river sand is used as a fine aggregate. It is an aggregate which is
passing through the 4.75 -µm sieve and retained on the 75-µm sieve.
Coarse Aggregate
Coarse aggregate for the works should be river gravel or crushed stone. And it should be
hard, strong, dense, durable, and clean.
2.4.1.2 Concrete
Concrete is very important for the structural construction such as in beams, slabs,
columns, retaining wall etc.
Advantages such as:-
- Concrete is highly resistance to compressive force
- Highly resistance to fire and weather.
- Is good insulator.
- Easily molded any shape.
- Water proof if properly mixed, vibrated.
Concrete cover: - A structure must have concrete cover to protect the steel from external heat
and corrosion.
Fixing main and false crasher by the size of column on fresh concrete around the overlap
bars of previous column.
Tying main bars with stirrups and inter connecting main bars with overlap of previous
columns.
Tying spacers that are pre casted for that purposes on stirrups.
Preparing and fixing formwork.
Checking alignment.
Casting.
Removing formwork.
Curing
Concrete C-30 will be casted and compacted using vibrator.
Removing time of formwork 16-24hr.
kerevat
keracheri
Stanga
After differentiate the longitudinal and transversal direction, the main beam constructed on the
longitudinal side.
During construction, It is known that 1 bar (berga) =12m length and if the span length is greater
than 12m which means it need additional length for the beam.
Prepared by Buzunesh Adugna
Page 20
ASU
1. Lap length: used for both top and bottom bar. During construction of the beam, the top
bar of the beam was greater than 12m and the maximum length of the bar was 12m,
which means it needed additional bar so the new bar was placed and overlap with the old
bar in the middle between the two columns. Used to transfer tensile force from old bar to
the new bar.
2. Anchorage length: applied on bottom bar. Bottom bar was always anchor at column or
support and overlap at 50*diameter of the bar. Anchor length used to transfer tensile load
from the bar to the concrete.
3. Development length (ganjo): the bar, which is bending in the end part of the beam.
2.4.2 Slabs
Slabs are structural flat plates used to provide useful horizontal surface mainly for roofs and
floors of buildings, parking and other structures. In my site, I have gate the chance to see a solid.
Based on load transferring mechanisms there are two types of slabs. These are one way and two
way slabs.
1. One-way slabs: As tried to define in the introduction one way slab may occurs if slab is
supported on flanged beam or the ratio of longer to shorter span is greater than two.
2. Two-way slabs: In two way slab the ratio of longer to shorter span is less than or equal two.
Supporting system is constructed and form is laid panels and checked entirely for
not being pierced.
Reinforcement are provided according to their detail and spacers are placed between
panel and reinforcement bar.
Concrete is casted properly while fulfilling its requirements.
The form work for slabs has to wait minimum of 21 days to be removed until then
the slabs has to be cured in order to affair its ultimate strength.
Inserting spacers.
Checking alignment.
Casting.
Removing formwork.
2.4.4 Spacer
Spacers are cover blocks that are placed to prevent the steel rods from touching the formwork
and it provide a minimum cover and fix the reinforcements. It made from cement, sand and small
aggregate should match with the mix proportion of the surrounding concrete.
Spacer
2.4.5 Stirrup
A stirrup is a closed or opened loop of reinforcement bar that is used to hold the main
reinforcement bars together in RC structure and to resist shear force and strengthen the structure.
Stirrup
There are steel bars of diameter of Ø 8, Ø 10, Ø 12, Ø 14, Ø 16, Ø 20 & Ø 24 deformed
reinforcement bar. The main purpose of providing reinforcement bars is to resist tension in the
structure.
Positive bars – These kinds of bars are mainly used to resist the positive moment. This
moment is mostly developed at the mid span on the beams.
Negative bars – These are bars used to resist negative moment. This moment is mostly
developed at the support.
Negative bar
Positive bar
2.4.7 Scaffoldings
Scaffoldings are used as a temporary staircase, and for placing wooden formworks, which are
used as a walkway for the workers.
Scaffoldings are constructed from Steel/prop and Wood
- Arranging HCBs on mortared surface by keeping both vertical and horizontal alignments.
- Repeat the above process until the required construction level is to be built
Stretcher
bond
2.6.1 Plastering
Plastering is the process of covering the wall and the skeleton part of the building with a
plastering material like cement mortar. Before plastering the skeletal part of the building need to
be hammered with sharp edged material to change their smooth surface in to, rough in order to
stick the mortar on them. It also provides a protective coating against atmospheric effects.
It has three steps namely first round plastering, second round plastering and third round
plastering. The total thickness off plastering is 20 mm.
Prepared by Buzunesh Adugna
Page 29
ASU
Additionally I have get chance to see the shear wall in our site (its not super
structure but I have see parallel as a chance on because of this I include this
structure in this document )
2.7, Shear wall;- is a verticall element of a system that is designed to resist in plane lateral
forces, typically wind and seistemic loads in many juridisctions.
Shear wall is a structural wall which is used to resist loads mainly horizontal forces and acts as
retaining wall to resist lateral pressure of the soil and to increase the aesthetics value of the
building. In addition to load resistance, it has another function. It is strong and provides security
of the building. The shear wall in our site was 800mm in bottom and 300mm in top thick. I see a
shear walls are constructed around building.
The size of reinforcement used in our site are 12Ø for horizontal and 12Ø for vertical this is
because shear wall are resist loads mainly horizontal forces and the vertical.
We were make the following major works when shear wall constructed like:
Formwork preparation
Reinforcement work
Ø80mm PVC pipes
Concrete casting
I have faced some challenges during my internship experience in the past four months. Most of
the challenges are at the work place are;-
o Challenge to communicate with the workers, foreman’s, carpenters, masons & site
engineer, because the words they use on the site are new, and hard to memorize in the
first few weeks of the internship period.
o Not having enough number of safety materials like helmet, safety clothes for the students.
Lack of enough safety material like helmet, safety shoes and glove…. etc.
Misunderstanding and some workers were not happy to accept interns‟ suggestions’’.
I tried to refer books and asked my site engineer to help me how I use drawings,
installation methodologies and symbols of drawing. I have learned the words they used
by asking and trying to memorize each word. I tried to resolve this by translating the
terminologies to their English equivalent and having a lesson about the points with the
help of general Forman and site engineer.
CHAPTER THREE
3. OVERALL BENEFITS I GAINED FROM THE INTERNSHIP
Work experience gives me the opportunity to gain greater understanding about I chosen field. As
a full time student, one of the best ways to gain this experience is by working as an intern in my
field of study to gain practical experience. An internship offers me the chance to learn by doing
in a setting where I was supervised by a work-place professional, and have the opportunity to
achieve own learning goals, without the responsibilities of being a permanent employ.
Open the door to a job offer or a recommendation about the next steps I should take on
career path.
Provide a better understanding of what is ex pected if, I was to succeed in the workplace.
Provide evidence that i have initiative, reliable and have a sense of responsibility.
In my near four-month internship, I have been able to acquire the following benefits:-
It was really fascinating and inspiring to see and experience the lessons I have been learning for
the past four years. So I tried to experience and learn every work as much as I can. I tried to learn
every aspects of the work both technical and non-technical terms.
Practice makes us to be familiar with construction of some building components
Such as: Concrete, Beam, Column, Slab, Stair, Formwork, Scaffolding etc…
Some of the practical skills that I gained or learned during the internship program
Preparation of take-off sheet, Preparation of bar schedule, Quality control, checking the work
3. 2 improving theoretical knowledge
I believe that I have upgraded my theoretical knowledge by working on site. Most of the courses
I take are in theory. They are not accompanied by practice. So this internship program has helped
me interrelate what I learned at school in theory with the actual reality of the construction
industry.
Theoretical knowledge is all about logic, calculation and principles. Theories can be understood,
but they can be forgotten if they are not supported by real visualization. When I was working I
started to compare my theoretical knowledge to how and why things are applied in practice.
It was a new and challenging experience until I became familiar with the words. But learning
them was/is of great importance because it will surely avoid communication barriers which
would have been inevitable with little or no knowledge.
The fact is that, apart from the necessities, one need to be equipped with habits of good
communication skills, as this is what will make us a happy and successful social being, which
refers to interpersonal communication.
Interpersonal communication skill is very vital in the construction world. Due to the job’s
character, I supposed to meet different personal for the successful accomplishment of tasks, good
communication is obligatory with those personal I was faced.
I have been able to grasp the main attributes of effective interpersonal communication such as:
Truthfulness and Honesty, Being respectful, Fair and rational.
During internship, I had the opportunity to team up with other intern students from other
universities. While performing different tasks at the office and at the site by forming individuals.
Being trained in a project office which has a lot of experience, working with people possessing
lot of experience in all aspects of life and getting a chance to work with people from different
parts of the country gives me a lot of social benefits regarding to :-
Then in my site I gained team playing skill during construction time to solve the problem and
how to modified the drawing in peace way.
I have seen how each worker is controlled and organized to perform its day-to-day
activities. Among all other managements, I have seen that human resource management
is the most important one.
I have actually observed the method of controlling the working time and amount of work
done by each worker so that the work proceeds according to the work plan (schedule).
During my internship, I have proved that proper application of ethical values benefits both the
company and the employees.
Punctuality: Punctuality doesn’t always refer to arriving on the work place on time, it
also infers to delivering given any task according to the deadline and being always
available if needed in working hours.
Office disciplines- in work place you don’t have to disturb the working atmosphere. For
example abstain from opening loud voice, loud music, songs and things which disturb
other workers’ working mood.
Honesty- Regarding this value each worker regardless of its status should abstain
from bad behaviours such as cheating , bias , corruption etc..
Proper utilization of instruments and labor: this would prevent any wastage which
could result from careless and excessive use of instruments and labor, in turn saving
precious time and money.
Cooperation: A worker should be able to team up and develop good relation with his/her
partners so as to be effective and create a smooth working platform.
Appearance Present a neat, clean appearance Practice personal hygiene, wear clothing
suitable to the job, task and environment.
After the completion of internship more motivated to look forward in construction business and
to start taking sub contract with different technique.
A construction project mainly requires large human, financial, physical (material and equipment)
institutional (management) resources. Entrepreneurship is defined as special human talent that
helps manage those factors of production such as labor machinery and capital and takes risks of
making loses.
Having a quality worker is a must if one needs to be productive and the need for employment
testing comes to picture to determine the candidate’s ability to perform the job, in addition
interviewing provides more opportunity to verify information on hand and to find out more about
the person’s interest, aspiration and expectation.
Construction equipment management helps a person to plan implement and monitor construction
equipment to:
CHAPTER FOUR
4. CONCLUSION AND RECOMMENDATION
4.1 CONCLUSION
The period of internship program has major role in equipping practical knowledge and
understanding the meaning of some courses that I have taken in the field of Construction
Technology and Management.
The internship time is a time that let me to build up and test real building construction world.
And it helped me to develop self-confidence and introduced us to the practical world of
construction Industry. In addition to this it helps me to understand the theory that I have learned
in the class.
Internship program is proved to be a construction between the theoretical and practical
knowledge. The various types of orientation programs, tasks and trainings that I have been
undertaking during this past four month on the site and the office increased my knowledge not
only in building construction but also on knowing the working environment. I’m very lucky to
see that what I have learnt in the university can be repeated in the working world.
I have been involved in the internship program for the last four months in Walabu
ConstructionS.C
The internship experience has helped us to: -
Upgrade my theoretical knowledge.
What the real working environment looks like.
In predicting what my future work stream will be.
Learn Practical consideration for building construction & design.
Learn about project evaluations & cost management
4.2. RECOMMENDATION
The interns were not taken information in proper way that is why there were no learning
classes.
The host company is responsible for supply of cement and reinforcement bars but due to
shortage of these construction materials, the construction was delayed. For the future I
recommended that the company should increase its manufacturing efficiency so that the
projects will not be delay.
▪ The teaching learning method shall be more practical other than theoretical. The
attachment program helps in incorporating the practical and theoretical. A practice has to
go hand in hand with the theoretical learning. It will help students to easily visualize what
is being told in class.
▪ I would like to recommend that the construction technology and management add
software course (Sap, ETAB, and 3DAutoCAD etc.). In to the curriculum to make
student more competitive with the outside world.
REFERENCES
Reinforced Concrete Structures 2. (April 23, 2020). Addis Ababa institute of Technology .
APPENDICES
Fonte: is a post or straight standing woods, which support formwork of slab& beam at
bottom.
Skuadra: made up of metal used to check for right angle or 90 degrees.
Staffa: is stirrup, which used as a shear resistance members of columns, beams and
shears walls.
Phondo: is bottom soffit, which used as a formwork for beams and slabs at the bottom.
Esponda: is sideboard, which used as a formwork for beams and slabs on vertical sides.
Stanga: is vertical bracing woods, which used to kill column.
Ganch: is a wood used to attach stanga on it.
Christi: is vertical beam support wood used to support slab formwork.
Tumbi: is plumb bob, which used for checking alignment of structures.
Sibago: is a string, which used to maintain horizontal alignment.
Cravat: which used to fix the formwork of column together in their position
Maincracher: is two piece of wood used to fix the column.
Ferayo: is bar bender, or cutter.
Modin: is a horizontal slab support.
Kebelato: Separate between bottom and top reinforcement, it is used like as spacer.
Armata; is a concrete
Berga; which is 12 meter reinforcement bar