Professional Documents
Culture Documents
UNIVERSITY
COLLEGE OF ARCHITECTURE AND CIVIL ENGINEERING
DEPARTMENT OF CIVIL ENGINEERING
Final internship report
Section; B
E mail address;bereketabyohannes@gmail.com
i
DECLARATION
I Bereketeab Yohannes a 4th year civil engineering student in AASTU have undertaken my internship
experience in SEBLE WERK ASMARE GENERAL CONSTRUCTION from July26/2021 to SEPTEMBER 18/2021
under the guidance of Mr.TESFAMICHAEL TSEGAYE (academic advisor) and Mr. NATNAEL GIRMA
(company supervisor).
I classify that my work is original compiled according to the Internship report guide given by the
department.
ii
ACKNOWLEDGMENT
First, I would like to thank my god for his merciful and endless guidance through my life. Next to god I
would like to thank my families for their great support and being beside me in all aspects. And next to
this I would like to thank Addis Ababa science and technology University College of architecture and civil
engineering department for providing this kind of internship program for us. And I would also like to
thank my hosting company seblewerke asmare general construction for their genuine hospitality and
continued effort to educate, supervise and foster my technical and professional skills throughout the
whole internship program.
at last but not the least I would like to express my special thanks to Eng. Natnael girma, all employees in
the site and other internship students for their encouragement and endless cooperation
throughout my stay in the internship programs.
iii
EXECUTIVE SUMMARY
An overall view that shows about what I have been doing. A report about the internship
experience that successes I have achieved during the period of the program in seblewerk asmare
general construction. This report gives detail information about site activities carried for building
project.
The contents of the report have been divided into three chapter. In the first chapter of my report, I
briefly described about over all internship experience. The second chapter of the report briefly explains
about benefit of the internship.in the third chapter of my report contain about, conclusion and
recommendation for my host company. To help anyone reading this report better understands for the
discussed topics and ideas.
iv
TABLE OF CONTENT
DECLARATION..................................................................................................................................... 2
ACKNOWLEDGMENT.............................................. ............................................................................3
EXECUTIVE SUMMARY........................................................................................................................4
List of Figure........................................................................................................................................7
2. spacer...............................................................................................................................................13
3. reinforcement work..........................................................................................................................14
5. beam ...............................................................................................................................................19
6.slab ...................................................................................................................................................21
7. column..............................................................................................................................................28
8. staircase............................................................................................................................................30
CHAPTER TWO.......................................................................................................................................36
v
2.4 INTERPERSONAL COMMUNICATION SKILL ...................................................................................38.
CHAPTER THREE....................................................................................................................................41
3.1 CONCLUSION....................................................................................................................................41
Appendix ................................................................................................................................................43
List of Figure
vi
Fig 11 form work for suspended beam………………………………………………………………………………………………...21
Fig 22 plastering………………………………………………………………………………………………………………………………..…34
vii
1
1
CHAPTER ONE
First, I would like to start with how I got into the company before explaining my internship Experience.
After the application form was given to us from Addis Ababa science and Technology University, I
applied to different companies who could be good mentors for my future in my profession. Some were
polite and some hostile to receive my application and give me the required service. In contrary I faced
some companies who were not willing to accept internship student or give answers politely.
In the bright side I got accepted in different places and I preferred to work in seblewerk asmare general
construction. The reasons why I chose this company were, first the supervisors( site manager) was a
student in our campus AASTU and he also learn his master’s program in our campus and next the
willingness of the company to support the student and the availability of advising staff in the
company, the effort of the company in research and development and its willingness to give project
works for the students, the existence of updating new technology and other facilities.
Site 1: Addis Ababa, bisrate gebriel site 2: Addis Ababa welo sefer
Site 1 has three main purposes which are used for commercial apartment and car parking.
Since it has basement +1 ground and +9 stories. The car parking area occupies basement and the
Commercial floors and parking are from ground floor and the 1st floor to the 9th floor is used for
apartment purpose.
Site 2 has four main purposes which are used for commercial, apartment, office and car parking. The car
parking areas occupies basement and the commercial floors are from ground floor and the 1st floor to
the 3rd is used for office and the 4th to the 10th floor is used for apartment purpose.
1
1.3 project work flow
General Manager
General Manager: - Would be accountable to the company operation and would head the firm based
on his/her authority depicted on memorandum and job description.
material request
sub-contracting agreements
General Forman
Sub-contractors
2
1.4 MY INTERNSHIP EXPERIANCE
In this chapter I will try to show what I have seen and what I have get in my 2-month experience.
Before I started my apparent time the site already on superstructure work, in the first two weeks I was
introducing with the project and the staff members who are at the site. I was familiar with the following
categories of works executed.
✓ Formwork
✓ Spacer
✓ Reinforcement work
✓ Beam
✓ Concrete work
✓ Stair
✓ Slab
✓ Column
1. FORMWORK
I was saw wood form work which is depending the shape of the construction work.
The formwork is temporary construction material used as a mold for structure with required size
and shape while controlling its position and alignment to support and form concrete members. It can be
mainly made up of timber plywood of any desired shape mostly rectangular. It also treated with oil or
benzene to prevent sticking of formwork with concrete Thus, it can be named based on the type of
structural member
Construction such as slab formwork, beam formwork, column formwork, stair formwork shear wall for
lift formwork etc.
In our site the formworks that we preferred to use timber they from perspective view of the material,
they are made of i.e. used plywood for the erection of beams, columns, shear walls and stairs cases.
When the concrete has reached the strength, the formwork is no longer needed and is removed.
The operation of removing formwork is called striping. After stripping the removed formwork
3
➢ Vertical formwork for columns, beams and walls…………………...1 days
➢ should be strong enough to carry the lodes placed on it, Example;- dead weight of the fresh
4
Fig 3,stair formwork fig4, beam and slab formwork
Fig 5, paraphet false column Fig 6,shear wall formwork for elevator
2,Spacer
It’s a space b/n reinforcement and formwork or lean concrete. The spacers are tied to the rebar before
casting the concrete
It has the purpose of protecting the rebar from corrosion, fire resistance also give reinforcing
bar
Fig 7, Spacer
5
3. REINFORCEMENT WORK
Reinforcement bars are a rounded steel bars with different size and shape of deformed
type used in reinforced concrete. Steel reinforcement is generally used in the form of bars or
circular cross section in concrete structure. Steel is one of the best forms of reinforcement, to
take care of those stresses and to strengthen the concrete to bear all kinds of loads. All
reinforcement bars are of the specified quality and in accordance with the standard technical
specification. The bars should be store in clean and dry area and also sheltered from rainfall. It
should be reasonably free from corrosion, rust and other impurities, such as grease, oil and other
kind of dirt which affect the strength of reinforcement. When it’s rust we should be brushed it
NB check; - The Bar dimeter by Verner caliper, The Bar length By Meter ,
It’s very important that the reinforcement is made up and placed strictly in accordance with the
drawing and that is so maintained during the placing reinforcement bars overlap location. During
the arrangement of reinforcement for the construction we have different types of reinforcement
bars
Stirrups
Stirrups Serve as shear reinforcement and are tied on longitudinal reinforcement to provide
resistance against outward buckling. The stirrups are different spacing for column and beam.
Most of the time we use 6 and 8 bars for stirrups. They are placed to provide diagonal shear
resistance, the diamond and spiral stirrup used to control lateral load ( earth quake and wind)
in our site I sow D/t types of stirrups for column spiral, rectangular, diamond etc.
Longitudinal bars are the vertical bars, which are in the vertical alignment within the column and
horizontal alignment in the slab and beam. They resist bending forces in beam, axial compression
6
in the column and bending stress in slab. Reinforcement placed to resist moment created by flexure,
torsion, vertical load and it also support shear reinforcement and other force longitudinal
reinforcement proved resistance to compressive and tensile lode and tensile lode with concrete.
Negative bars –
These bars is used to resist negative moment. Most of the time they are found at the support of
the beams. They are placed on 1/3 of span length from the center of the column to top, where
Lapping length
There are overlapping length for beam and column, in our sight we use 5φ
Ties of reinforcement
4. CONCRETE WORK
concrete is made by mixture of cement, sand, aggregate, water, air and admixture if required.
The strength and quality of concrete depend not only on the quality and quantity of the materials,
but on the procedures used in combining these materials and the skill involved in the
Cement: the cement powder, when mixed with water forms paste. This past acts like glue and
Aggregate: used for strength, resistance for cover large volume. Based on size two types of
Fine Aggregate (sand): - Its size greater than 4.75mm pass aggregate example. crashed sand (00)
aggregate and river sand Used for to fill void b/n (filler).
Coarse aggregate;- Its size at 25mm pass at 20mm retied Its cover large area
Water: Water fit for drinking is generally suitable for concrete. It facilitates the spreading of
7
cement over the aggregate and makes the mix workable.
Admixture: -unlike cement, aggregate and water are not an essential component of the concrete
mix, but they are important and increasingly widespread component that are used to improve
An admixture can be defined as chemical product which is added to the concrete mix in qualities
no longer than 5%by mass of cement during mixing operation prior to the placing of concrete
Type of admixture
1 retarder: - used to increase the initial setting time of concrete, mostly used in transportation
process when the concrete plan Bach is far from construction site
2 accelerators: - used to decrease initial setting time concrete, mostly used in pile casting process
3 air entries
4 plasticizers: - used to reduce amount o f water that present in mixed concrete large enough
5 super-plasticizers: - used to form concrete to jelly property during pumping process of concrete.
On my site, used concrete making materials are: OPC type of cement, well graded coarse
aggregate, with good quality of sand and clean water.
MIXING OF CONCRETE
distribution of materials in concrete mass & this can be judged by consistency of concrete.
Method of mix may be hand mix or mechanical (machine) mix. In our site mixing process is
This all is about how I was investigated on slab work. As I mentioned I explain that, we
were used C-30 for column and C-25 for slab and beam
8
Fig 8, mix truck
PLACING OF CONCRETE
Concrete should be deposited (poured) as near as possible to its final position in order to
reduce segregation. Problems that arise due to poor handling and placing of fresh concrete are
9
Fig 9,placing concrete by tube
COMPACTION OF CONCRETE
After the concrete had been placed, the compaction or consolidation has been started
using vibrator. The purpose of vibration or consolidation is to expel or eliminate the air bubbles
from the concrete mass to the maximum extent in order to achieve maximum density of concrete.
CURING OF CONCRETE
Curing of concrete is a process of keeping mixing water design so hydration continue up to max
compressive strength gained Example; for PPC 45 Day and OPC 28 Day
The curing time may depend on concrete type, the type of the structural element and
environment of the working station. There are two setting times of concrete namely, initial
10
setting time and final setting time.
Initial setting time;- is a time that takes for Mixing, discharging, transporting and casting period
required up to (30-45min)
Final setting time: - is a time that found b/n after cast of concrete to starting period of curing, so
5, Beam
It is a building member used to carry and transfer loads to the consecutive columns and used
subjected to moments and shear loads. Detail provision and reinforcement are provided as
that of grade beams. But the difference is it does not have contact with the ground and thus
the construction needs bottom formwork (soffit) and props for casting. . This beam can be primary
and secondary beam.
Primary(main) beam is a type beam that runs from column to column, in this case the load
Secondary (distributed) beam is a type beam that runs from beam to beam not connected to the
column, in this case the load transfer directly to the primary beam and also the primary (main)
beams are to be made of the same concrete quality they are casted monolithically. On our site
Beam reinforcement
Beam reinforcement placement was started after the form work of slab and Sponda of beam
were placed and slab reinforcement started. The reinforcement bar size were used in a beam
is diameter of 8 for stirrup, for main bar the diameter of the bar vary based on the plane.
During beam reinforcement placement the bottom bar over lap at the support and the top bar
overlap at the middle of the span, because at the bottom tension force is high and to resist
slippery of bar. All quantity of beam reinforcement bar passes through the supported
reinforcement bar. Because to proper transfer of load without sliding of beam down ward.
When two equal span length cross each other, the top one have high amount of negative
11
reinforcement bar to increase the capacity of the beam. The location of stirrup on the beam
reinforcement bar changes at each tied. The use of stirrup is to hold the bar in a given spacing
and to keep the position of reinforcement bar and to keep the shape of the beam also prevent
the shear failure on the structure. Stirrups are tied on the beam reinforcement in alternate way
to resist failures.
The main form works for beam are Sponda and fondo.
Fondo (sofit):-a form work which could be sited on the bottom of the beam.
12
Fig 11, formwork for suspended beam
➢ Both longitudinal bars and stirrups are provided according to their spacing
➢ Spacers are tied with bars and then formwork is constructed for the member
➢ Formworks are removed after expiry of their period and the concrete surface is
6, Slab
Slab is a structural part of the building having plate shape and used to cover the distance
between beams and possibly columns. Generally slabs are constructed monolithically with
beams and concreted in one operation for the full depth. The top surface of the slab is kept
rough to create a proper bond with any type of floor finish desired .there are solid ,flat and ribbed slab.
At our project site they incorporated solid slab at gebriel site and ribbed slab at welo sefer site.
A. solid slab
A concrete slab or solid slab is a common structural element of modern building. It is a plane
horizontal structural element used to support live loads and dead loads and transfer these
13
loads to the supporting beams or walls.
Before slab reinforcement placements were started the formwork was painted gasoline and
the formwork of the slab and the beam is carried by props. Then after, reinforcements have
During slab reinforcement was placed, first the bottom (mesh) bar was placed in two (x and
y) direction with in the same spacing. Then the reinforcement bar has been tied by black wire
to keep the position of the bars and the given spacing. The bars have bend at one end and
extended up to one third of the slab for each partition in external side. The top (negative)
reinforcement bar of slab has been placed up to one third of the span length from the beam or
support. Because, around one third of the span length there is high interaction of load and the
load would be transferred to the column from different parts of the structure through this way.
After have been finished bottom and top reinforcement placement of slab, kabeleto and
spacer was placed. kabaleto was made from wastage bar by bending both sides, which is
placed between bottom and top reinforcement of the slab to prevent the overlap of the bottom
and the top reinforcement during concrete caste and to keep the thickness (space) of bottom
and top reinforcement of slab. Spacer was placed between the formwork and the bottom
14
Fig12,slab rebar
The Procedures on placing of suspended Beam and Slab can be summarized as follows:
15
➢ arrange beam reinforcement
➢ Cast concrete both in slab and beams at once solid slab work
16
Fig15, concrete work
B.RIBBED SLAB
Ribbed slab is type reinforced concrete slab in which some of the volume of concrete in the tension zone
is removed and replaced with hollow blocks or left as voids. This reduction in the volume of concrete in
tension zone (below the neutral axis) is based on the assumption that the tensile strength of the
concrete is zero, hence all the tensile stress is borne by the reinforcements in the tension zone. The
resulting construction is considerably lighter than a solid cross-section.
After completing the form work then we construct girder beam. A girder is a large and deep type of
beam that is used in construction. It is typically capable of longer spans and taking greater loads than a
normal beam, and is often used as a main horizontal structural support for smaller beams. Then after
constructing girder beam, we placed hollow concrete blocks between those hollow concrete blocks
construct rib beams. Then we reinforced the slab by 6mm diameter bar at the top which is used for
strengthening the slab .It is a type of slab which uses HCB, wide bend beams running between columns
and narrow ribs.
In welosefer construction site ribbed slabs are used for all the floors excluding ground floor. Hollow
17
block of 24cm is used but around the bathroom area18cm of hollow blocks are use for more
dampness resistance. The U-bar used has the diameter of 8mm. U-bar is used to
- Prevent the concrete from slipping under stress and moment.
- It also used to hold the ribbed reinforcements in position.
The procedure that were used to constrict this slab are a s follows
➢ The scaffoldings were erected by an appropriate height and put ply wood
➢ Negative bars were placed near the supports and Meshes the upper surface of slab
18
Fig17, placing u bar
The formwork was providing to keep the shape of fresh casted concrete and also it was
removed after the concrete gain the maximum strength. The formwork of the slab was
19
7. COLUMN
Columns are reinforced structures which transmit the axial loads to the foundations. It is used to
Carry and transfer loads from slabs, roofs and beams to the foundation.
Columns vary in size and shape. There are circular as well as rectangular columns in shape, the
circular column have higher required reinforcement than rectangular and esthetically beautiful.
As we know theoretically column has longitudinal (resist lateral load and axial load with aid of
concrete) and lateral reinforcement /stirrups (prevent buckling and tie the longitudinal
reinforcement).
➢ The form work will be fixed with “kerebat” and “stanga” and gindila ,it should be checked for the
actual position by suspending “plumb bob” in two opposite sides of column and with reference of other
columns.
➢ Remove the form work on the next day and curing it with wet cover
20
Fig19, column
21
8. STAIR CASE
Stairs are set of steps leading from one floor to another and are provided in a building to afford
as means of communication b/n varies floor. stair case is seen as connectors between at least two
different levels. this is super structure necessary for the building which has additional floor to
the ground floor of the building to another floor part of the building.
➢ Keep spacer
22
Fig20,stair
Partition
It consists of hardened cement and may be completely solid or contain single or multiple
hollows.
It is made from conventional cement mixes and various types of aggregates. These include:
sand, gravel, crushed stone, expanded Shale or clay, volcanic ciders (Pozzolana), scoria, pumice,
etc.
The partition work used to CHCB cement, sand material. HCB block use in different size that
means the external part 20cm because the external condition happened for different
occasions like –wind
_pressure
_rain snow
23
➢ The interior wall times used 15cm HCB block because interior condition not attach the external
failure band additionally to save interior area.
Fig21,block work
Plastering
Given:-
. 3 meter height
. 5 meter wide
Solution
24
To find wet volume of the plaster
➢ It’s the recent formula it was 1.4 the recent is 1.54 it varies from country to country in our
country Ethiopia , there is poor waste management due to absence of adapting management
tools like lean construction ,kaizen...... etc. that’s why cost of most projects are 200% of initial
budget
To find the volumes of sand and cement we have to know the ratio of plaster it (1:4)
It adds up 5
1+4=5
➢volume of cement
➢Bag of cement
= 2 bag of cement
Volume of sand
25
Fig 22 plastering
26
1.5 CHALLENGES WHILE PERFORM TASK
It is clear that I am a practicing employer. Due to this there are some challenges which faced me
Some of the challenges are: -➢ Unwillingness of some professional persons to share their
experience and practical
knowledge.
➢ During at the time of working on the site there are lacks safety which may endanger health.
➢ The office workers were busy, and they don't have time to help us, especially quantity
➢ terrible accident happens to one of the employees ,he fall from the 7th floor and I’m very disturbed
➢ Creating relation with Forman and site supervisor and I asked them. After that I became
➢ I asked carpenters and other daily laborers, through time I became familiar with all the site
names.
➢ I asked the foreman and he answered me “this is a new and temporary office. Therefore, we
will try to fulfill every facility for future. “Therefore, I did all office works manually.
➢ When I move here and there on the site I moved with great care. As a result, I finished the
➢ I convince myself that I can adopt all site conditions such as the discrepancy of theoretical
➢ I have tried to come with my handouts daily and concerning with each other activity, in
27
CHAPTER TWO
2.1 INTRODUCTION
construction company. And such trends help students to have valuable work experience.
In this internship that means within these four months I observed what the outside
construction world looks like more than what I usedto know when I was at school. At school I
learned or took many theoretical lessons even difficult to understand theoretically. So in this
internship period I have got opportunity to solve these difficulties. Because those things which
were theoretically difficult to understand, were not that much hard to understand when I faced it
practically.
The overall benefits of the internship are not limited to the practical skill only. I would
like to group the overall benefits in terms of d ifferent categories such as:
the first thing I have get from my internship experience is practical skill. This is also the target
Practical skill: - means skill performed by hands (as in tying a knot)or with human intervention
I have theoretical knowledge from my 7 semester classes, thus this internship investigation helps
28
me to compare and contrast my theoretical knowledge with the practical.
➢ I get a knowledge about how my structural designs will apply on real construction, and their
purpose on buildings.
➢ I get technical knowledge about how structural members and components of a structure
➢ I get a knowledge about construction materials and equipment’s with their techniques and
methods of application
➢ I get a knowledge about how reinforcement bars arranged and how it becomes structural
member
➢ I get knowledge about how formwork is constructed for a temporary mold and its techniques
of construction.
➢ I get a knowledge about mixing ratio of concrete materials at desired grade of concrete. And
sizes of boxes.
➢ I get a knowledge about types of construction machines and their methods of operations on
site.
➢ I get a knowledge about how quality of construction materials checked and standards of
Besides improving practical skill this program provides the student a chance to apply our
theoretical knowledge in the real construction world. Because to understand the practical world
As every student & staff knows almost all the courses we took focused on theoretical part, thanks
to this internship program we now able to upgrade our theoretical knowledge by practice. So I
can say that my knowledge is upgraded by the practical things I saw when I was at the site.
29
2.4 INTERPERSONAL COMMUNICATION SKILL
It’s the ability to convey information to another effectively and efficiently. Business managers
with good verbal, non-verbal and written communication skill helps facilitate the sharing of
I have exercised communication skill with contractors, Engineers, Forman, etc. This helps me to
upgrade my listening and understanding abilities. I had also a conversation with non-professional
workers by understanding the way they express their ideas. This needs a great patience,
respecting and understanding people's ideas and using the local language.
While accomplishing my task at the project site i have been able to increase my interpersonal
communication competence i.e. the ability to use verbal and nonverbal language and behavior
Since this internship program have arranged in order to practice theoretically knowledge, share
common experiences and getting addition information from the team which found in site
Especially in case of mistake happens on specific work; I learnt that as a team member how could
investigate such error and reach to the solution. Here, adopt the skill of decision-making and
conflict management whenever necessary. Additionally, I was gain the skill of comparing one’s
idea within a group member before going to reject the idea that might be important and gain
benefits in terms of improving my skills in different way in terms of what is expect from me as
a team member. This means how to accomplish site works, acting as a group or a team. Some of
Task oriented
➢ Asking and sharing questions and ideas with each other about the tasks.
30
Social role oriented
Generally, I can improve team-playing skill very well. This is the main skill have to be improved
Since construction work by itself relates with so many disciplines and different workers,
accordingly these workers have their own position at work place based on their education status
and experience in works so it is necessary to be o ne as a leader and the others leaded. Leadership
is a skill to guide, control and monitor peoples. A leader is basic for the whole project to be
hindered well. Leadership started from planning. This helps to know the progress of the work
have to be done and the required goal to be achieved. After having a good plan by organizing the
If there is a good leadership throughout the whole construction work, the following things done
smoothly
In my internship time, I have observed some tasks, which were related more of with leadership.
➢ I have seen how each worker is controlled and organized to perform its day-to-day activities.
➢ I have actually observed the method of controlling the working time and amount of work
done by each worker so that the work proceeds according to the work plan.
Generally, the internship time helps me to get and improve the skills to be a leader. Some of
31
them are good speaking ability, to have the ability to listen to others, to be decisive, good
The company has rules and regulations about the work ethics at work place, and this helps me to
workers to be punctual.
➢ Reliability; I understand that my reliability for the company brings me works satisfaction and
➢ Efficiency; being efficient helps to decrease errors at construction and if there is no error
➢ Open mindedness; open mindedness can bring a good communication with labors. This helps
From this internship investigation, I get a knowledge about how can i become an entrepreneur
and helps me to understand job opportunities and application mechanism of the construction
So after graduation I’m ready to invent a job opportunity and generate an income for myself and
The following works are recommended for fresh graduates, because those works need a small
➢ HCB production
32
CHAPTER THREE
3.1 CONCLUSION
I think it would be fair to say the internship program has been a helpful experience in exposing
us to the real engineering work. It can also be expressed as an exciting even depending upon how
Also, this program creates an opportunity to think in what way we should learn and what type of
knowledge should we have to gather before we leave. For the students the program opens the
space to have some relation with some personnel and company. Which in turn minimize the
These days the technology of construction industry has been improved. Consequently, modern
and new construction techniques and material usage is in practice. This has greatly required the
improvement of the work methodology. As a result, the supervision work shall also be improved.
So, it is clear that the supervisor has a big role to improve the time quality and cost controlling
in the construction industry. To implement these parameters (time, cost and quality) the
experience of the supervisor shall be carefully determined by the consultant depending on the
Additional to the above having this internship in this time helps us to know what will be expected
Generally, the purpose of this Internship (apparent) program was to introduce students with
working condition and mostly it helps students to grasp knowledge from practicing the theory
which they have been learning in the class. This program gave us good practical skills and made
us familiar to the outside real construction world. Most the theoretical things we been leaned got
illustrated here in this program, which develops more our confidence in the theoretical
knowledge.
33
3.2 RECOMMENDATION
During my internship experience period I have seen some positive and negative sides about the
internship hosting company and area of improvement of the internship program. So, I want to
raise my personal opinion to improve the internship for future students. In this part of my report
I will try to suggest some ideas for my internship hosting company and my department .
The following are the recommendations that I made to solve the problems and I hope they might
➢ Necessary safety materials ,they have to close duct cause its dark and first aid should be prepared for
workers and site visitors.
➢ Poor Handling of steel (rebar) on the site the problem with drawing should be corrected.
Because each and everything must have done with only the design given unless and
➢ Slump test and silt content test should be conducted on the site.
➢ All construction rules should be respected in day to day activities to avoid or reduce
different problems
34
Appendix
Cristy T shape like scaffold for slab and beam to keep stand the formworks
Soleta Slab
Stafa Stirrup
35