Standard Construction Document CCDC 24  1996

SCHEDULE OF VALUES AND WORK PERFORMED


Application number: Initial Schedule of values
Contractor: Sample
Date: November 21, 2005

Work: Period covered from to


title and location

Performed to Previously Current Balance to


Date Performed Period Complete
Number Description Amount Remarks
% Value Value Value Value

1 Sitework 100,000
2 Concrete 400,000
3 Mob/Demob 50,000

(Sub) Total 550,000